Analytics / Job cost reports and cost-to-complete

Job cost reports and cost-to-complete

How the job cost report is built by cost code from budget, commitments, actual cost and the forecast, how cost-to-complete is set in the Budget tool, and which flags are planned.

Preview

Partly in the app today. Items marked Planned are not built yet.

On this page

The job cost report answers one question per cost code: will this scope finish on budget? This page explains the columns, how cost-to-complete is maintained, and how the Budget tool keeps it current instead of rebuilt at month-end.

The columns

A job cost report lines up, by cost code, everything known about cost:

Column Meaning Source
Original budget As estimated at award Budget
Approved changes Budget changes from approved change orders Change records
Revised budget Original + approved changes Calculated
Committed Subcontracts and POs, including approved commitment changes Commitments
Actual cost Posted invoices, labor, equipment and other costs Accounting
Cost to complete Estimated remaining cost Forecast
Estimate at completion Actual + cost to complete Calculated
Variance Revised budget − estimate at completion Calculated

Pending changes can appear as an extra column so you can see exposure next to the budget without mixing it into approved numbers. See Change events and potential change orders.

In the app

The Budget tool is the job cost report. Its Budget tab shows, per cost code and cost type: Original Budget, Modifications, Approved Budget Changes, Revised Budget, Pending Budget Changes, Projected Budget, Committed Costs, Direct Costs, Pending Cost Changes, Projected Costs and Projected Over/Under. The Forecast tab adds Forecast to Complete and Est. Cost at Completion. Lines roll up by division to a grand total.

This project report uses project financial records such as direct costs and commitments. Company Accounting separately records supported posted job-cost actuals and provides a job-cost forecast; do not assume all project activity is automatically posted to the ledger.

Reading a line

Cost code Revised budget Committed Actual Cost to complete EAC Variance
26 Electrical $4,780,000 $4,971,200 $2,690,000 $2,281,200 $4,971,200 ($191,200)
23 HVAC ductwork & dampers $2,938,100 $2,838,000 $1,710,000 $1,228,100 $2,938,100 $0

26 Electrical is forecast at about 4% over its revised budget. The committed column is the early warning: when committed cost is already at or above the revised budget (26 Electrical is committed $191,200 over), or when invoices are exceeding commitments, the line is heading for a variance before actual cost shows it.

How cost-to-complete is set

There are a few common ways to forecast remaining cost on a line. In the Budget tool’s Forecast tab, the default is calculated (projected budget minus projected costs, never below zero), and the PM can type a manual number on any line to override it. Clearing the override returns the line to automatic. The common methods:

  • Manual: the PM enters the remaining cost. The most common and, with good judgment, the most accurate.
  • Remaining commitment: for fully bought-out scopes, cost to complete is what’s left on the commitments plus anything not yet bought. Enter it as a manual forecast.
  • Budget remaining: revised budget minus actual. Simple, and only honest when the line is tracking to budget. This is close to the app’s automatic forecast.
  • Productivity-based: for self-performed labor, remaining quantity at current productivity. Planned.

Whatever the method, the result is the PM’s number to own.

Updating the forecast

  1. Open the Forecast tab

    The PM sees revised and projected budget, committed and direct costs, pending changes and the current forecast on each line.

  2. Change the number, add a note

    For example: raise 26 Electrical cost to complete by $160,000 because conduit runs in the L3 corridor are longer than estimated. Required notes above a threshold are Planned.

  3. Snapshot it

    Take a budget snapshot at month-end. The Variance tab compares any snapshot with today, line by line, so you can see how the forecast moved.

  4. Everything that reads it updates

    Est. Cost at Completion and Projected Over/Under update from the same change. Projected margin, percent complete and over/under billing on the WIP are Planned.

Forecast history

A single month’s estimate at completion tells you little. The trend tells you whether a job is fading. Today, monthly budget snapshots and the Variance tab give you the trend; a per-line forecast history chart is Planned.

revised budgetM1M2M3M4M5M6EAC
Estimate at completion by month for one cost code. Illustrative.

Flags (Planned)

Planned: the report flags lines worth a look, rather than leaving every line for a person to scan. Today, a negative Projected Over/Under shows in red.

  • Forecast is stale: actual cost moved materially since the last forecast update.
  • Over commitment: invoices exceed the remaining commitment on a line.
  • Committed above budget: commitments exceed the revised budget.
  • Progress disagrees: cost-to-cost percent complete differs from the PM’s physical percent complete by more than a set amount.
  • Cost ahead of approval: costs posted against changes that aren’t approved.

A Risk agent that summarizes flagged lines is Planned. See How agents work.

Keep exploring

Related across os.construction

Run it on your own project.

Start a 14-day free trial. Want a say in what ships next? Join the founding program.

Your role (optional)

14-day free trial. Pricing for paid plans isn't set yet. Talk to us. Already have an account? Sign in →

Ask the OS

Reading this page

Ask anything about this page. Answers use what you're reading as context.

Suggested

    AI · may be imperfect · sample data where shown

    Open file