Esc

↑↓ move↵ openIndex · Pagefind

Reading your project dashboard

Six tiles, one sentence each, and the arithmetic behind them. Read the project desktop and the Budget & cost pack on Riverside Medical Center, and learn which number to question first.

Visual explainer6 min scrollSample data · Riverside Medical Center

Start here

The project desktop

Desktop in the dock opens the project home: widgets that sum up the job, each showing only numbers from tools you're allowed to see. Here they are on Riverside (sample data; the committed figure is illustrative).

  • Contract$49.3M$48.2M original + $1.1M approved COs
  • Committed$36.8M86.3% of the $42.64M original budget
  • Billed$33.0M66.9% of the contract
  • Margin$5.62M11.4% · revised contract vs projected cost

Two percent-completes, never mixed: billed is 66.9% of the contract, but cost to date is 72.6% of estimated cost. The gap is why cost-to-cost percent complete and under billing matter.

Analytics · Budget & cost pack

Six tiles, one chain of arithmetic

The pack says it plainly: these numbers use the same math as the Budget tool, line for line. Scroll to build each tile from the one before.

  1. Tile 1 · sample data

    Revised budget

    The original cost budget plus transfers and approved budget changes. Pending changes aren't in it yet; they're added to get the projected budget.

  2. Tile 2

    Projected costs

    What you've committed (subcontracts and POs with their approved changes), plus direct costs, plus pending cost changes. It's money already spoken for, not money spent.

  3. Tile 3

    Forecast to complete

    The cost still to come. Where the PM has entered a manual forecast to complete on a budget line, the pack uses it; otherwise it falls back to the remaining budget, never negative.

  4. Tile 4

    Estimated cost at completion

    Projected costs plus forecast to complete. On Riverside that lands on the job's estimated total cost.

    $38,950,000 + $4,729,800 = $43,679,800
  5. Tile 5

    Forecast over/under

    Projected budget minus EAC. Positive means the forecast is inside budget; negative is a forecast overrun. Here it's a thin +$120,200: worth watching, not celebrating.

  6. Tile 6

    % committed

    Committed costs over revised budget. High and rising means buyout is mostly done and the remaining risk is in what's not bought yet. The Bought out vs burned chart on the Cost codes tab sets it against percent complete by cost code.

  7. Back on the desktop

    Margin ties it to the contract

    The desktop's Margin widget sets the revised contract against projected cost. Same EAC, one more subtraction.

    $49,300,000 − $43,679,800 = $5,620,200 (11.4%, against 13.2% at bid)
The budget bridge

How did we get from the original budget to today's?

The pack's first chart walks original budget → transfers → approved changes → pending changes → projected budget. Riverside's version, with illustrative budget lines; the axis starts at $42M so the changes are visible.

Budget bridge, illustrativeOriginal budget $42,640,000, transfers $0, approved changes $860,000, pending changes $300,000, projected budget $43,800,000.$42M$42.5M$43M$43.5M$44MOriginal budget: $42,640,000$42.64MOriginalbudgetTransfers: $0+$0KTransfersApproved changes: $860,000+$860KApprovedchangesPending changes: $300,000+$300KPendingchangesProjected budget: $43,800,000$43.80MProjectedbudget
Budget totalChangeAxis starts at $42M
In the app

The Budget & cost pack

Recorded in the app on a test project, so the figures differ from Riverside. The Forecast tab holds the six tiles, the budget bridge and a Reading the forecast panel with the formulas above. Filters for division, cost code and period sit above the tabs.

The Budget and cost analytics pack showing revised budget, projected costs, forecast to complete, estimated cost at completion, forecast over/under and percent committed tiles, the budget bridge chart and the Reading the forecast panel.
Budget & cost pack, Forecast tab: tiles, budget bridge and the formulas. Recorded in the app · sample data

The Cost codes tab answers "is each division forecast inside its budget?": bars for EAC and committed, a tick for the revised budget that turns red when EAC runs more than 10% over, then which cost codes are burning fastest and bought out vs burned.

The Cost codes tab of the Budget and cost pack with a horizontal bar chart of estimated cost at completion and committed costs by cost code against revised budget ticks, and charts of cost codes burning fastest and bought out vs burned.
Cost codes tab: EAC and committed against each revised budget. Recorded in the app · sample data

Beyond the pack

Packs are read-only; Save a copy to change one. Export downloads CSV, XLSX or a PDF, Subscribe… schedules it to recipients who each get their own render, and TV mode runs it full screen. Every tile still follows each viewer's permissions in each tool. Analytics is in preview; cash forecasting is planned.

Text version

Every tile, as a table

Budget & cost tiles on Riverside (budget lines illustrative)
TileValueHow it's calculated
Revised budget$43,500,000$42,640,000 original + $860,000 approved changes = $43,500,000
Projected costs$38,950,000$36,800,000 committed + $1,650,000 direct + $500,000 pending = $38,950,000
Forecast to complete$4,729,800Manual FTC entered by the PM: $4,729,800
Estimated cost at completion$43,679,800$38,950,000 + $4,729,800 = $43,679,800
Forecast over/under+$120,200$43,800,000 projected budget − $43,679,800 = +$120,200
% committed84.6%$36,800,000 ÷ $43,500,000 = 84.6%
Desktop margin$5,620,200$49,300,000 contract − $43,679,800 = $5,620,200 (11.4%)

Keep going

Sample project included

Try this workflow on the sample project

Every trial workspace includes a sample project with sample data, so you can follow these steps in the app before touching a live job.

Try it on the sample project

Want this on live job data?

The project desktop and Analytics (in preview) are live in os.construction, built from the same records as the Budget tool. Cash forecasting remains planned; company Accounting covers the ledger, AP, AR and payroll.

Your role (optional)

14-day free trial. Pricing for paid plans isn't set yet. Talk to us. Already have an account? Sign in →

All figures are illustrative sample data, not a real project. Contract terms and state law decide how retainage, stored materials and change orders work on your job. Check both.

Ask the OS

Reading this page

Ask anything about this page. Answers use what you're reading as context.

Suggested

    AI · may be imperfect · sample data where shown

    Open file