Anatomy of a WIP schedule

Build a work-in-progress schedule for four jobs, one column at a time, and see exactly how over billing, under billing and fade fall out of the math. Then see it the way your banker and surety do.

Visual explainer4 min scrollSample data · Riverside Medical Center

The WIP schedule, built column by column

  1. Month-end · sample data

    One question per job

    A WIP schedule asks, for every open job: have we billed more or less than we've earned? Four jobs, nine columns. Let's build it.

  2. Column 1

    Contract

    Original contract plus approved change orders. Riverside includes CO #14, so it's $49,300,000, the same contract sum to date as Pay App #9.

  3. Column 2

    Estimated total cost

    What the PM expects the whole job to cost now: cost to date plus cost to complete. Not the original budget. A stale estimate breaks every column after this one.

  4. Column 3

    Cost to date

    Actual job cost posted through month-end: labor, material, subs, equipment. It comes from the job cost ledger, not from billing.

  5. Column 4

    Percent complete, cost-to-cost

    Cost to date divided by estimated total cost. It's the most common method for recognizing revenue over time under ASC 606.

    Riverside: $31,700,000 ÷ $43,679,800 = 72.6%
  6. Column 5

    Earned revenue

    Contract times percent complete. This is the revenue you've actually earned, whatever you've billed.

    $49,300,000 × 72.6% = $35,778,781
  7. Column 6

    Billed to date

    Gross billings including retainage. Riverside's ties to G702 line 4 on Pay App #9: $33,000,000.

  8. Column 7

    Over or under billed

    Billed minus earned. Positive is over billing, a liability: cash you owe back in work. Negative is under billing, an asset: work you've financed for the owner.

    Harbor Point: $15,100,000 − $13,800,000 = +$1,300,000
  9. Column 8

    Projected gross profit

    Contract minus estimated total cost: what the job will make if the estimate holds.

    Portfolio: $9,252,200 · 10.5% margin
  10. Column 9

    Fade

    The change in projected profit since last month's WIP. Eastgate's cost estimate grew, so its profit dropped $382,500, from 9.0% to 6.0%.

    Fade is the trend lenders watch. One bad month is a story; three is a pattern.

  11. The other side of the table

    What your banker and surety see

    They read the totals, then go straight to the outliers. Under billings get the hardest look: many sureties discount them because they're the asset most likely to evaporate.

    Try your own numbers in the WIP calculator.

Text version

The whole WIP schedule, as a table

Every number from the walkthrough above, month-end, sample data. Over/under is billed minus earned: positive is over billed, negative is under billed.

Work-in-progress schedule
JobContractEst. total costCost to date% completeEarned revenueBilled to dateOver / (under)Projected GPFade vs last month
Riverside Medical Center 24-118$49,300,000$43,679,800$31,700,00072.6%$35,778,781$33,000,000−$2,778,781$5,620,200 (11.4%)−$49,300
Harbor Point Lofts 24-131$18,400,000$16,560,000$12,420,00075.0%$13,800,000$15,100,000+$1,300,000$1,840,000 (10.0%)$0
Eastgate Elementary 25-007$12,750,000$11,985,000$6,591,75055.0%$7,012,500$6,800,000−$212,500$765,000 (6.0%)−$382,500
Mill Street Warehouse 25-019$7,900,000$6,873,000$2,061,90030.0%$2,370,000$2,900,000+$530,000$1,027,000 (13.0%)$0
Total$88,350,000$79,097,800$52,773,65066.7%$58,961,281$57,800,000−$1,161,281$9,252,200 (10.5%)−$431,800
Backlog
$29,388,719
Over billings (liability)
$1,830,000
Under billings (asset)
$2,991,281
Net
−$1,161,281 (under billed)

Mistakes that make a WIP lie

  • A stale estimate

    Percent complete, earned revenue, over/under and profit all move with estimated total cost. If the PM hasn't updated it, every number is wrong at once.

  • Overruns inflate percent complete

    Spend more than planned without raising the estimate and the job looks further along, so earned revenue and under billing both look better than they are.

  • Unapproved change orders

    Cost for pending CO work lands in cost to date while the revenue isn't in the contract yet. Decide how you treat it, and be consistent.

  • Re-keyed from three systems

    Job cost from accounting, estimates from the PM's spreadsheet, billing from the pay app file. Every copy is a chance to be a month behind.

Keep going

Sample project included

Try this workflow on the sample project

Every trial workspace includes a sample project with sample data, so you can follow these steps in the app before touching a live job.

Try it on the sample project

Want this on live job data?

Change orders and pay apps are live in os.construction; WIP and AP are planned. On one record, every number on this page is entered once.

Your role (optional)

14-day free trial. Pricing for paid plans isn't set yet. Talk to us. Already have an account? Sign in →

All figures are illustrative sample data, not a real project. Contract terms and state law decide how retainage, stored materials and change orders work on your job. Check both.