Anatomy of a pay app

Watch an AIA G702/G703 get built line by line, from the schedule of values to the current payment due. Every cell, what it means and where it comes from.

Visual explainer4 min scrollSample data · Riverside Medical Center

Pay App #9, built step by step

  1. Pay App #9 · sample data

    Two forms, one number

    A pay app on AIA forms is two documents. The G703 continuation sheet has one row per schedule of values line. The G702 is the one-page summary the architect certifies and the owner pays.

    We'll build Riverside Medical Center's Pay App #9 from scratch: $2,310,400 of work this period.

  2. G703 · columns A–C

    Start with the schedule of values

    Each row is an approved SOV line with a scheduled value. Change orders get their own lines: CO #14 for the fire dampers is line 10.

    Column C total = $49,300,000 = contract sum to date
  3. Column D

    What you already billed

    Work completed and billed on Pay Apps #1 through #8, line by line. It carries forward from the last application, so it never changes this month.

    Previous applications = $30,689,600
  4. Column E

    Work put in place this period

    The progress the field actually installed since the last cutoff. This is the column the architect checks on the site walk.

    Work this period = $1,971,920
  5. Column F

    Stored materials

    Material delivered but not yet installed: air handlers, switchgear and the dampers for CO #14. Most contracts allow billing it with backup (invoices, insurance, location).

    E $1,971,920 + F $338,480 = $2,310,400 this period
  6. Column G and %

    Completed and stored to date

    Add D + E + F on every row. Divide by C for percent complete. The bars behind each line show how far it has come.

    G = $33,000,000 · 66.9% of the contract
  7. Column H

    Balance to finish

    Scheduled value minus completed and stored. What's left to bill on each line, before retainage.

    C − G = $16,300,000
  8. Column I

    Retainage

    The owner holds back 10% of column G on every line until the job is complete. On CO #14 that's $6,912.

    10% × $33,000,000 = $3,300,000

    How retainage works

  9. G702 · lines 1–3

    Roll it up: contract sum to date

    The original contract plus executed change orders. The change order summary box has to agree, and line 3 has to equal G703 column C.

    $48,200,000 + $1,100,000 = $49,300,000
  10. G702 · lines 4–6

    Earned, less retainage

    Line 4 comes straight from column G. Retainage splits into completed work (5a) and stored material (5b), and must equal column I.

    $33,000,000 − $3,300,000 = $29,700,000
  11. G702 · lines 7–9

    Current payment due

    Subtract what was certified on earlier pay apps (line 6 of Pay App #8). What's left is this month's check.

    $29,700,000 − $27,620,640 = $2,079,360

    Sanity check: $2,310,400 this period − $231,040 retainage = $2,079,360. It ties.

  12. Signatures

    Sign, certify, pay

    The contractor signs (notarized where required). The architect certifies the amount after checking the work, and the owner pays what's certified, usually with lien waivers attached.

    Next: why pay apps get rejected.

Text version

The whole pay app, as tables

Every number from the walkthrough above. Riverside Medical Center, Job 24-118, Pay App #9 (sample data).

G703 continuation sheet
A · ItemB · DescriptionC · Scheduled valueD · PreviousE · This periodF · StoredG · Completed & stored% (G÷C)H · Balance to finishI · Retainage
1General conditions$3,850,000$2,656,500$115,500$0$2,772,00072%$1,078,000$277,200
2Sitework$2,640,000$2,640,000$0$0$2,640,000100%$0$264,000
3Concrete$6,920,000$6,574,000$138,400$0$6,712,40097%$207,600$671,240
4Structural steel$5,480,000$5,206,000$109,600$0$5,315,60097%$164,400$531,560
5Mechanical & plumbing$11,260,000$5,630,000$486,000$225,200$6,341,20056%$4,918,800$634,120
6Electrical$8,140,000$3,663,000$402,800$96,000$4,161,80051%$3,978,200$416,180
7Fire protection$1,910,000$764,000$152,800$0$916,80048%$993,200$91,680
8Interiors & finishes$8,000,000$2,786,100$448,980$0$3,235,08040%$4,764,920$323,508
9Approved COs #1–13$1,013,600$770,000$66,000$0$836,00082%$177,600$83,600
10CO #14 Fire dampers$86,400$0$51,840$17,280$69,12080%$17,280$6,912
Grand total$49,300,000$30,689,600$1,971,920$338,480$33,000,00067%$16,300,000$3,300,000
G702 application and certificate for payment
LineDescriptionAmount
1Original contract sum$48,200,000
2Net change by change orders (from the change order summary)$1,100,000
3Contract sum to date (line 1 ± 2)$49,300,000
4Total completed & stored to date (column G on G703)$33,000,000
5a10% of completed work (columns D + E)$3,266,152
5b10% of stored material (column F)$33,848
5Total retainage (5a + 5b, or column I)$3,300,000
6Total earned less retainage (line 4 − line 5)$29,700,000
7Less previous certificates (line 6 from Pay App #8)$27,620,640
8Current payment due (line 6 − line 7)$2,079,360
9Balance to finish, incl. retainage (line 3 − line 6)$19,600,000
Before you submit

Common rejection reasons

What gets a pay app sent back, in the order reviewers usually find it.

  1. 01

    The math does not tie

    G702 line 4 has to equal the G703 column G total, line 5 has to equal column I, and line 3 has to equal column C. One transposed digit and the whole package comes back.

  2. 02

    Unapproved change orders

    Only executed change orders go on the SOV. A pending PCO billed as a line is the fastest way to lose an architect’s trust.

  3. 03

    Percent complete ahead of the field

    The architect walks the site. If column G says drywall is 60% done and the third floor is still open studs, expect a markup.

  4. 04

    Stored materials without backup

    Most contracts want invoices, proof of insurance and the storage location (and a bill of sale for off-site storage) before they pay for material that is not installed.

  5. 05

    Missing lien waivers

    Owners and lenders commonly want conditional waivers for this period and unconditional waivers for the last one, from you and your subs. On Riverside, Apex Steel and CoreDry are still missing (sample data).

  6. 06

    Wrong retainage rate

    Reducing retainage at 50% complete only counts if the contract allows it and the owner has approved it. Billing the reduction early gets the pay app rejected.

  7. 07

    SOV values moved without approval

    Shifting value between lines (or front-loading early trades) without owner sign-off is a red flag reviewers look for.

  8. 08

    Paperwork gaps

    Wrong application number or period, missing signature or notarization, or a continuation sheet that does not match the summary page.

Keep going

Sample project included

Try this workflow on the sample project

Every trial workspace includes a sample project with sample data, so you can follow these steps in the app before touching a live job.

Try it on the sample project

Want this on live job data?

Change orders and pay apps are live in os.construction; WIP and AP are planned. On one record, every number on this page is entered once.

Your role (optional)

14-day free trial. Pricing for paid plans isn't set yet. Talk to us. Already have an account? Sign in →

All figures are illustrative sample data, not a real project. Contract terms and state law decide how retainage, stored materials and change orders work on your job. Check both.