Billing

AIA G703

Definition

The AIA Continuation Sheet: the line-by-line detail of a pay application, showing progress and retainage for each schedule of values item.

Part of: Getting paid: pay apps, retainage, lien waivers and notices

Topic: Payment & liens

Updated

AIA Document G703, the Continuation Sheet, is the detailed page (or pages) behind the G702 Application and Certificate for Payment. Each row is a schedule of values line, and the columns show how much of that line has been completed, stored, billed and retained. The column totals carry to the G702, so the continuation sheet is where every number on the summary page comes from.

Why it matters

The G703 is where the architect, the owner’s rep and the lender check your billing against what they see on site. A reviewer walks the job, looks at a line (“Level 3 drywall, 60% complete”) and decides whether it is true. If it is not, the pay app comes back, and every day it spends in review is a day later you get paid.

It is also the bridge between billing and job cost. If the SOV lines map to your cost codes, you can compare billed percent complete with cost percent complete line by line and see where you are over or under billed before the WIP schedule does. See earned revenue for why the two numbers differ.

The columns

Column Heading What goes in it
A Item no. The SOV line number
B Description of work The SOV line description, including change order lines
C Scheduled value The value of the line from the SOV
D Work completed, from previous application Column D + E from the last application
E Work completed, this period Value of work put in place since the last application
F Materials presently stored (not in D or E) Stored materials delivered but not installed
G Total completed and stored to date D + E + F
G ÷ C Percent complete Column G divided by column C
H Balance to finish C − G
I Retainage Per line, if the retainage rate varies by line

How it ties to the G702

The G702 summary lines read straight from the continuation sheet totals:

  • Contract sum to date (original contract plus net change orders) equals the column C total.
  • Total completed and stored to date equals the column G total.
  • Retainage is calculated on completed work (columns D + E) and on stored material (column F), at the contract’s rates, or taken from column I.
  • Total earned less retainage, minus previous certificates for payment, gives the current payment due.

Worked example

Illustrative pay application #4 on a $1,250,000 contract with one approved change order and 10% retainage:

A B C Scheduled D Previous E This period F Stored G Total G÷C H Balance I Retainage
1 Sitework 200,000 200,000 0 0 200,000 100% 0 20,000
2 Concrete 450,000 300,000 100,000 0 400,000 89% 50,000 40,000
3 Structural steel 600,000 150,000 210,000 60,000 420,000 70% 180,000 42,000
4 CO #1 Added footings 36,000 0 18,000 0 18,000 50% 18,000 1,800
Totals 1,286,000 650,000 328,000 60,000 1,038,000 81% 248,000 103,800

On the G702 that becomes: contract sum to date $1,286,000; total completed and stored $1,038,000; retainage $103,800; total earned less retainage $934,200; less previous certificates $585,000 (90% of the $650,000 previously billed); current payment due $349,200; balance to finish including retainage $351,800.

Two details a reviewer will check: the $60,000 of steel in column F needs backup (invoices, proof of insurance and location, as the contract requires), and the change order sits on its own line so its billing can be traced to the approved change order.

Common mistakes

  • Column D that doesn’t match the last application. D must equal last month’s D + E, line by line. Any difference looks like re-billing.
  • Percent complete ahead of the field. Billing 70% on a line the reviewer can see is half done gets the line, and sometimes the whole app, cut.
  • Moving value between lines without the owner’s approval of a revised schedule of values.
  • Billing stored materials without backup, or billing them again in column E when installed without taking them out of F.
  • Spreading change orders across existing lines instead of adding them as new lines.
  • Arithmetic and rounding errors that make the G703 totals differ from the G702 by a few dollars. Reviewers send those back too.

For the monthly procedure, column by column with a worked example that ties to the G702, see how to fill out a G702/G703 pay application.

How os.construction handles it

In the Payment Applications tool the G703 lines come from the contract’s schedule of values. You enter work completed this period and materials stored; totals, percent complete, balance to finish and retainage calculate per line, and the totals roll up to the G702. See payment applications and progress billing with G702 and G703. The free pay application builder builds a G702/G703-style pay app in your browser, and the anatomy of a pay app walks through one line by line.

Watch the explainer · 2:02

What is a schedule of values?

  1. 0:00The contract sum, line by line
  2. 0:18Who prepares it
  3. 0:39Billing against the lines
  4. 0:57Change orders get their own lines
  5. 1:17Front-loading
  6. 1:39The SOV in os.construction
Read the transcript

A schedule of values, or SOV, breaks the contract sum into line items, such as general conditions, sitework, concrete, steel, mechanical and electrical, each with a dollar value. The lines add up to the contract sum, and every pay app bills against them.

The contractor prepares it. Under AIA A201, section nine point two, on stipulated sum and GMP contracts, the contractor submits it before the first application for payment. The architect reviews the values and can ask for backup. Once it's accepted, it's the basis for reviewing every pay app.

Each month, the continuation sheet reports every line: work from previous applications, work this period, materials stored, total to date, percent complete, balance to finish and retainage. The summary page rolls those columns up into the current payment due.

Approved change orders change the contract sum, so each one is added, usually as its own line. On the sample Riverside job, change order fourteen, eighty-six thousand four hundred dollars for fire dampers, becomes its own line, and the SOV now totals forty-nine point three million. Pending changes stay off the bill.

Front-loading means putting more value on early lines, like mobilization or general conditions, than the work is worth, so more is billed early. It helps the contractor's cash flow, but leaves the owner paying ahead of the work, which is why architects look for it. A good SOV has lines you can measure progress on, each tied to cost codes.

In os.construction, prime contracts, subcontracts and purchase orders each hold a schedule of values. Payment applications fill the continuation sheet from the contract's SOV, add executed change orders and carry the previous column forward, so nobody retypes the SOV each month.

FAQ

What is an AIA G703?

AIA Document G703, the Continuation Sheet, is the detailed page of an AIA pay application. Each row is a line from the schedule of values, and the columns show the scheduled value, work completed in previous applications and this period, materials presently stored, total completed and stored to date, percent complete, balance to finish and retainage. Its totals carry to the G702 summary.

What is the difference between the G702 and the G703?

The G702, Application and Certificate for Payment, is the one-page summary: contract sum, change orders, total completed and stored, retainage, previous certificates and current payment due, signed by the contractor and certified by the architect. The G703 is the line-by-line support behind it. The G702's total completed and stored to date comes from the G703's column G total.

How do you fill out a G703 continuation sheet?

Copy the schedule of values into columns A to C, carry each line's total from the last application into column D, enter the value of work completed this period in column E and materials stored but not installed in column F. Column G is D + E + F, percent complete is G divided by C, balance to finish is C minus G, and retainage is calculated per line where the rate varies.

Where do change orders go on a G703?

Approved change orders are usually added as their own lines on the continuation sheet, with their own scheduled values, rather than spread across existing lines. That keeps what has been billed against each change visible. The G702 shows the net change by change orders as a separate line.

Is the G703 required on every project?

Only if the contract calls for it. AIA owner-contractor agreements reference the G702 and G703, and many owners and lenders ask for them on other contracts too, but private owners can require any format they like. Lenders and public agencies often have their own forms that follow the same structure.

Sources

See it in the app

AIA G703 in os.construction

Build a G702/G703-style pay app from the contract’s schedule of values; executed change orders land on line 2 automatically. Read the guide: Payment applications.

  1. 1Contract SOV
  2. 2This period on the G703
  3. 3G702 totals
  4. 4Submit and approve

Try it on the sample project in a free trial.

Start free trial Sign in
Open file