An allowance is a fixed dollar amount carried in the contract for a known item whose details aren’t settled yet, like finish hardware, signage or a specific fixture package. Unlike contingency, an allowance is tied to a named scope. When the item is finally selected and bought, the actual cost is compared to the allowance and the contract is adjusted up or down, usually by change order.
How it works
- The owner or designer sets the amount. The specification or bid form lists each allowance, its amount and what it covers. Every bidder carries the same figure, so allowances don’t affect who is low.
- The contract defines what’s inside it. AIA A201’s allowances clause is a common default: the allowance covers the cost of materials and equipment delivered to site, plus required taxes, less trade discounts. Unloading, handling, installation labour, overhead and profit sit in the contract sum outside the allowance. Many contracts modify that, so each allowance should say whether labour, freight, tax and markup are in or out.
- The owner selects the item. Selection deadlines belong in the schedule, because a late choice can delay procurement.
- The contractor buys it and documents the cost. Invoices and quotes are the backup for reconciliation.
- The contract is adjusted by change order. Overages add to the price; underruns come back to the owner as a credit.
On the schedule of values, allowances are usually shown as their own lines so billing and reconciliation stay visible.
Worked example
Illustrative: Riverside Medical Center carries two allowances. Under this contract they cover material and tax only; installation and markup are in the base price, and the contract allows 10% markup on any overage.
| Allowance | Amount | Actual cost | Difference | Change order |
|---|---|---|---|---|
| Signage | $150,000 | $171,400 | +$21,400 | +$21,400 + $2,140 markup = +$23,540 |
| Door hardware | $60,000 | $52,500 | −$7,500 | −$7,500 credit |
The signage package the owner chose costs more than the allowance, so the contract price goes up. The hardware came in under, so the owner gets the $7,500 back. Netting the two into one change order is common, but showing each line keeps the backup clear. Whether markup is also credited on an underrun depends on the contract wording.
If the signage overage also needed extra installation labour, for example because the selected signs are larger, that labour change belongs in the same change order as a separate line, since installation sits outside this allowance.
Allowance vs related terms
| Term | What it covers | How it’s settled |
|---|---|---|
| Allowance | A named item not yet selected | Change order for the difference from actual cost |
| Contingency | Unidentified risks or scope gaps | Drawn down under the contract’s rules |
| Alternate | An optional scope priced at bid | Owner accepts or rejects at award |
| Unit price | A rate for work of uncertain quantity | Rate × measured quantity |
| Provisional sum (UK) | Work that can’t be fully described at tender | Valued and adjusted when instructed |
Why it matters
Allowances let a job start before every selection is made, but they are a common source of disputes. The contract should say what the allowance includes (material only, or labor, freight, tax and markup too) and how overages and savings are handled. On a lump sum job, a large allowance total means a large part of the price isn’t really fixed yet. On a GMP job, allowance overruns can eat into contingency or the contractor’s fee if the contract isn’t clear about where they go.
Common mistakes
- Not defining whether labor, tax and markup are inside the allowance.
- Letting allowance reconciliation slip to closeout, where it collides with final billing.
- Treating unspent allowance as contractor savings when the contract returns it to the owner.
- Missing selection deadlines, so the allowance item becomes a schedule problem.
- Unrealistically low allowance amounts, which make the budget look better at bid and all but guarantee overage change orders later.
For pricing the reconciling change, see how to price a change order.
How os.construction handles it
A change event can be typed Allowance, so allowance draws and the reconciling change travel through the same change event and change order record, and an owner allowance can be added to the budget on the Budget Changes tab. See Change events and change orders and Budget.
Watch the explainer · 0:46
Allowance or Contingency? 💡 Know the Difference
Read the transcript
This lobby needs lights, but the fixtures are not selected. Is that an allowance or contingency?
A ten-thousand-dollar fixture allowance carries an amount for that named scope. Check whether installation, freight, tax, and markup are included.
Contingency is a separate provision for uncertain costs and risks. Owner and contractor contingencies can cover different risks and have different controls.
Before using either, check the contract: what is covered, who controls it, and who must approve its use?
Name the purpose before moving the money. Find the allowance guide at os dot construction.
Video page with chaptersMore in Construction lessons in a minute
FAQ
What is an allowance in a construction contract?
An allowance is a stated amount included in the contract price for a specific item that hasn't been fully selected or designed at bid time, such as door hardware, signage or light fixtures. When the item is chosen and bought, the actual cost is compared with the allowance and the contract price is adjusted by change order.
What happens if an allowance is not fully used?
Under most standard forms the difference goes back to the owner as a credit change order. AIA A201 adjusts the contract sum up or down to reflect actual cost against the allowance. A contract can say otherwise, so check the allowance clause before treating unspent allowance as savings.
What is the difference between an allowance and a contingency?
An allowance is tied to a named scope item and is reconciled against that item's actual cost. A contingency is a pool for unknown or unassigned risks, with rules for who can draw on it. An allowance is spent on something specific; a contingency covers what nobody has identified yet.
Does an allowance include labour and markup?
Only if the contract says so. Under AIA A201, allowances cover the cost of the materials and equipment delivered to site plus required taxes, while installation, handling, overhead and profit are carried in the contract sum outside the allowance. Many contracts change that, so each allowance should state what it includes.
What is an allowance called in the UK and Canada?
In the UK the closest equivalent is a provisional sum, and prime cost sum is an older term for an amount set aside for goods or work from a named supplier or specialist. Canadian CCDC contracts use cash allowance.
