A guaranteed maximum price (GMP) contract pays the contractor its actual cost of the work plus a fee, but only up to a stated ceiling. Costs above the GMP that no approved change order covers are the contractor’s. Costs below it go back to the owner or are split through a shared savings clause. GMP is the usual pricing model for CM at risk.
Think of it as cost-plus with a lid. The owner gets open books and the upside of savings; the contractor gets reimbursed for real cost but carries the risk of going over.
How it works
- The contractor builds up the GMP. On a CM at risk or progressive design-build job, preconstruction estimates are refined as the design develops. Once the drawings are far enough along, the contractor submits a GMP proposal with its assumptions, clarifications and exclusions.
- The GMP is broken into buckets. Cost of the work, general conditions, contractor contingency, allowances, insurance and bonds, and the fee. Each bucket has its own billing rules.
- The owner accepts it as an amendment. On AIA forms, the GMP is often set in an amendment to A133 or stated in A102. The fee may be a percentage of cost or a fixed amount.
- Work is bought out and billed at cost. Each month the contractor bills actual cost with backup, plus fee, less retainage. The owner or its cost consultant can audit the books.
- Changes move the ceiling. Owner changes, allowance reconciliations and other events the contract treats as changes adjust the GMP by change order. The contractor’s own misses don’t.
- Final accounting settles it. When the job closes, final cost plus fee is compared with the adjusted GMP. Savings are returned or shared; overruns stay with the contractor.
What goes into a GMP
| Bucket | What it covers | How it’s usually billed |
|---|---|---|
| Cost of the work | Subcontracts, materials, self-performed labor, equipment | Actual cost, with backup |
| General conditions | Field staff, temporary facilities, site costs | Actual, fixed or capped, per contract |
| Contractor contingency | The contractor’s risk allowance inside the GMP | Not billed directly; moved into cost when used |
| Allowances | Owner-defined amounts for undesigned scope | Reconciled to actual; overs and unders adjust the GMP |
| Fee | Home-office overhead and profit | Percentage of cost, or a fixed amount |
Worked example
Illustrative: a contractor proposes a GMP built from these numbers, with a fixed fee and a 75/25 owner/contractor savings split.
| Line | Amount |
|---|---|
| Cost of the work | $38,000,000 |
| General conditions | $3,200,000 |
| Contractor contingency | $1,200,000 |
| Subtotal | $42,400,000 |
| Fixed fee (4% of subtotal) | $1,696,000 |
| GMP | $44,096,000 |
Case 1, savings. The job finishes at an actual cost of $41,600,000, including the contingency it used. Cost plus fee is $43,296,000, which is $800,000 under the GMP. Under the 75/25 split, the owner keeps $600,000 and the contractor earns $200,000 on top of its fee.
Case 2, overrun. Actual cost reaches $42,900,000 with no change order to cover the extra. Cost plus fee would be $44,596,000, which is $500,000 over the GMP. The owner pays only $44,096,000, so the contractor’s fee effectively shrinks from $1,696,000 to $1,196,000.
If the owner had added scope worth $300,000 by change order, the GMP would have risen to $44,396,000 before either comparison.
Why it matters
GMP jobs are open-book. The owner can audit your costs, so job cost coding, commitments and backup have to be clean. And because overruns come out of your fee first, you need an honest monthly cost to complete forecast against the adjusted ceiling, not only against the budget.
The savings clause also changes behavior. Buyout savings on a GMP job may belong to the owner, to contingency or partly to you, depending on the contract. Know which before you move money between cost codes.
GMP vs other pricing models
| GMP | Lump sum | Cost-plus (no cap) | |
|---|---|---|---|
| Owner pays | Actual cost + fee, up to the cap | The fixed price | Actual cost + fee |
| Overrun risk | Contractor, above the GMP | Contractor | Owner |
| Savings | Owner or shared | Contractor | Owner |
| Books open to the owner | Yes | Usually no | Yes |
| Typical delivery | CM at risk, progressive design-build | Design-bid-build | Uncertain scope, emergency work |
See lump sum and cost-plus for those models in detail.
Common mistakes
- Billing costs the contract defines as non-reimbursable, such as home-office staff or certain equipment.
- Drawing contractor contingency without documenting why, then facing the owner’s auditor at closeout.
- Not tracking the adjusted GMP ceiling separately from the cost forecast.
- Setting the GMP on drawings that are too early, with assumptions and exclusions that don’t hold up.
- Treating allowance overruns as contingency draws instead of reconciling them to the GMP by change order.
This is general information, not legal advice. GMP terms vary widely by contract form and owner.
How os.construction handles it
A prime contract can be set to bill by GMP in Accounting. You send the period’s costs through the API and accounting prices them with the contract’s terms: the fee, the GMP cap checked against what was already billed, and shared savings at settlement, then drafts the invoice. On the project side, the budget shows commitments, approved and pending changes and the forecast against each cost code, and contingency transfers are recorded as modifications. See Accounts receivable and Budget. Assembling the owner’s pay-app backup directly from job cost is planned.
See CM at risk software.
Watch the explainer · 1:57
Design-build vs design-bid-build vs CM at risk
- 0:00Three ways to buy a building
- 0:12Design-bid-build
- 0:31Design-build
- 0:49CM at risk and the GMP
- 1:14Side by side
- 1:36One project record
Read the transcript
Design-bid-build, design-build and construction manager at risk are three ways an owner can buy a building. The difference comes down to how many contracts the owner signs, and when the builder gets involved.
Design-bid-build is the traditional sequence. The owner hires an architect, the design is finished, and then contractors bid on it. The low responsive bidder usually wins. The owner holds two separate contracts, so when the drawings have gaps, the owner sits between the designer and the builder.
In design-build, the owner signs one contract with one team that both designs and builds. Design and construction can overlap, which can shorten the schedule, and one party answers for both. The trade-off is less owner control over design details once the criteria are set.
Construction manager at risk keeps the architect on its own contract, but hires the builder early, during design, to advise on cost, schedule and constructability. When the design is far enough along, the construction manager commits to a guaranteed maximum price, or GMP, and then holds the trade contracts. Costs above the GMP are generally the construction manager's risk, unless the scope changes.
So, design-bid-build: two contracts, and a builder picked on price after design. Design-build: one contract for both. CM at risk: two contracts, with the builder in early and a price ceiling set before construction. The right one depends on how much speed, design control and price certainty the owner needs.
Whatever the method, the builder tracks the same things. In os.construction, the prime contract, budget, commitments, change orders and payment applications sit on one project record, so a GMP job and a lump-sum job are run from the same data.
Video page with chaptersMore in Construction concepts explained
FAQ
What is a GMP in construction?
A guaranteed maximum price (GMP) contract pays the contractor its actual cost of the work plus a fee, up to a stated ceiling. If cost plus fee runs over the GMP, the contractor pays the difference unless an approved change order raised the ceiling. If it comes in under, the savings go back to the owner or are shared, depending on the contract.
What is included in a guaranteed maximum price?
Usually the estimated cost of the work (subcontracts, materials, self-performed labor and equipment), general conditions, the contractor's contingency, allowances for undesigned scope, insurance and bond costs, and the contractor's fee. The contract defines which costs are reimbursable; home-office overhead is commonly excluded from the cost of the work and covered by the fee.
Who keeps the savings on a GMP contract?
It depends on the shared savings clause. Some GMP contracts return all savings to the owner. Others split them, for example 75 percent to the owner and 25 percent to the contractor, sometimes with a cap on the contractor's share. Without a savings clause, the owner simply pays actual cost plus fee, which is below the ceiling.
What happens if a GMP is exceeded?
Costs above the GMP that are not covered by an approved change order are the contractor's. In practice the contractor first draws its contingency, then the overrun eats into its fee, and past that it loses money. Owner-directed changes, differing site conditions and other events the contract treats as changes adjust the GMP instead.
What is the difference between GMP and lump sum?
In a lump sum contract the owner pays a fixed price and the contractor keeps any savings, so its costs are private. In a GMP the owner pays actual cost plus fee up to a cap, the books are open to audit, and savings go to the owner or are shared. Both put overrun risk on the contractor.
When is the GMP set?
Usually during design, once drawings are developed enough to price with reasonable contingency, often somewhere between design development and construction documents. On CM at risk and progressive design-build jobs, the contractor's preconstruction estimates build up to a GMP proposal, which becomes a contract amendment, such as Exhibit A to an AIA A133.
