Using the app / Budget

Budget

Build the project budget by cost code and cost type, transfer money between lines, forecast cost at completion, take snapshots, compare variance and lock the budget.

Preview

Partly in the app today. Items marked Planned are not built yet.

On this page

The Budget tool is the project’s cost plan. You enter the original budget per cost code and cost type; the tool computes the rest from the other financial tools: approved and pending change orders, commitments and direct costs. This page walks through the screens. For the ideas behind it, see Cost codes and budgets.

Open it from the project: Tools → Budget (/companies/{company}/projects/{project}/tools/budget).

The budget grid

The Budget tab groups lines by division (the root of each cost code) with subtotals and a grand total. Each line is a cost code plus a cost type: Labor, Equipment, Materials, Subcontracts or Other.

Column Where the number comes from
Original Budget What you entered on the line
Modifications Net transfers in and out of the line
Approved Budget Changes Approved prime contract change orders and approved Budget Changes
Revised Budget Original + modifications + approved budget changes
Pending Budget Changes Prime contract change orders still in pricing, pending, revised or proceeding
Projected Budget Revised budget + pending budget changes
Committed Costs Approved subcontract and purchase order lines, plus approved commitment change orders
Direct Costs Direct costs that are approved, pending or revise-and-resubmit
Pending Cost Changes Commitment lines and commitment change orders not yet approved
Projected Costs Committed + direct + pending cost changes
Projected Over/Under Projected budget − projected costs. Negative means a projected overrun

Owner changes move the budget columns; commitment changes move the cost columns. Drafts don’t count anywhere. If a cost code has committed or direct cost but no budget line, it still shows up, tagged No budget line, so cost never disappears from the report.

Add a line

  1. Create

    Click Create and pick the Cost Code and Cost Type.

  2. Enter the amount

    Type an Original Budget Amount, or enter Quantity, Unit of Measure and Unit Cost and let the tool multiply. Add a Description if the code alone isn’t clear.

  3. Save

    The line appears in its division. Cost codes themselves are set up in the project’s Admin tool, on the Cost Codes tab.

Move money between lines

Transfers are Modifications. Click Create Modification, choose From Line Item and To Line Item, enter the Transfer Amount and a note. The Modifications tab lists every transfer with its from and to lines, so contingency drawdown and buyout savings stay visible.

Budget changes that come from outside the budget (an owner allowance, a scope addition you are carrying yourself) go on the Budget Changes tab. A Budget Change starts as a draft, goes under review, and is either approved or voided. Approved ones show up in Approved Budget Changes. The Change History tab lists them with their amounts.

A change event can also post to the budget: when you close it, its budget-change amounts post by cost code.

Forecast cost at completion

The Forecast tab adds three columns:

  • Forecast to Complete. By default this is projected budget minus projected costs, never less than zero. Type your own number to override it on a line; clear it to go back to automatic.
  • Est. Cost at Completion. Projected costs + forecast to complete.
  • Projected Over/Under at completion.

A manual forecast is the PM saying “I know something the commitments don’t show yet”. Use it.

Snapshots and variance

  1. Capture a snapshot

    On the Snapshots tab, click Capture snapshot and give it a name, for example “Month-end September”. It freezes every line and column as they are now.

  2. Compare

    On the Variance tab, pick a snapshot. Each cost code shows the snapshot value, the current value and the delta for each measure.

  3. Download

    Each snapshot has Download snapshot CSV.

Lock the budget

Once the original budget is final, someone with Admin on Budget can click Lock Budget. While locked, original line items, modifications and forecast overrides are read-only, and a banner says so. Changes after that go through a Budget Change or a change event, so the original stays what you bid. Unlock Budget reverses it.

Export

Export Budget CSV downloads every current line with the budget and forecast columns. It exports the current budget, not a filtered view; use a snapshot’s CSV for a frozen copy. See Export to CSV and PDF.

“Budget data unavailable”

If a source the budget reads from is inconsistent (for example, a change order chain that points at the wrong contract), the tool shows Budget data unavailable with the reason instead of a wrong total. Fix the record it names, then click Retry budget. Your snapshots are still available from that screen.

Permissions

Read Only can view the budget. Standard can create and edit lines, modifications and forecasts. Admin can delete and lock or unlock. See Set up permission templates.

Keep exploring

Related across os.construction

Run it on your own project.

Start a 14-day free trial. Want a say in what ships next? Join the founding program.

Your role (optional)

14-day free trial. Pricing for paid plans isn't set yet. Talk to us. Already have an account? Sign in →

Ask the OS

Reading this page

Ask anything about this page. Answers use what you're reading as context.

Suggested

    AI · may be imperfect · sample data where shown

    Open file