Esc

↑↓ move↵ openIndex · Pagefind

Budget, commitments and cost: one ledger

The budget doesn't ask accounting for numbers. It reads the job's own commitments, change orders and direct costs, every time you open it. Build Riverside's cost picture column by column, from original budget to estimated cost at completion.

Visual explainer6 min scrollSample data · Riverside Medical Center

Riverside's budget and cost, column by column

  1. Column 1 · Budget · sample data

    Original budget

    Each budget line is a cost code plus a cost type (Labor, Equipment, Materials, Subcontracts or Other). You enter the original amount, or quantity × unit cost. Once it's final, Lock Budget keeps the original what you bid.

    Riverside original cost budget: $42,640,000
  2. Columns 2–4

    Modifications and approved changes

    Transfers between lines are Modifications, so contingency drawdown stays visible. Approved Budget Changes come from approved prime contract change orders and approved Budget Changes; a change event can also post its budget-change amounts by cost code when it's closed.

    $42,640,000 + $0 + $860,000 = $43,500,000 revised
  3. Columns 5–6

    Pending changes make the projected budget

    Prime contract change orders still in pricing, pending or proceeding show as Pending Budget Changes. Drafts don't count anywhere.

    $43,500,000 + $300,000 = $43,800,000
  4. Commitments

    Subcontracts and POs become committed cost

    A subcontract counts once it's Approved (or Complete); a PO once it's Approved. Approved commitment change orders add to it. Out for signature, its lines sit in Pending Cost Changes instead; drafts don't count.

    Committed: $36,800,000, 84.6% of revised budget
  5. Direct and pending cost

    Everything not on a commitment

    Direct Costs are costs that aren't on a subcontract or PO, counted when approved, pending or revise-and-resubmit. Pending commitment lines and change orders add Pending Cost Changes.

    $1,650,000 direct + $500,000 pending cost
  6. Projected costs

    Money already spoken for

    Committed plus direct plus pending cost changes. If a cost code has cost but no budget line, it still appears, tagged No budget line, so cost never drops out of the report.

    $36,800,000 + $1,650,000 + $500,000 = $38,950,000
  7. Forecast tab

    Forecast to complete: where the PM earns their keep

    By default, forecast to complete is projected budget minus projected costs, never below zero: $4,850,000 here, which would just say "we'll land on budget". The PM knows the remaining mechanical work is running heavy and types a manual forecast on those lines.

    $38,950,000 + $4,729,800 manual FTC = $43,679,800 EAC
  8. At completion

    A thin cushion, said out loud

    Projected budget minus EAC is +$120,200. Against the $49,300,000 contract, EAC leaves $5,620,200 of margin (11.4%). Capture a snapshot at month-end, and the Variance tab shows what moved next month.

One commitment, up close

Summit Mechanical's subcontract

A subcontract holds the contract company, retainage, inclusions and exclusions, a schedule of values by cost code, its change orders and the invoices billed against it. Its status decides where it lands in the budget.

  1. DraftNot counted yet
  2. Out For BidNot counted yet
  3. Out For SignaturePending Cost Changes
  4. ApprovedCommitted Costs
  5. CompleteCommitted Costs

Purchase orders go Draft, Processing, Submitted, Partially Received, Received, Approved, Closed: approved lines are committed, and processing, submitted or received lines are pending cost. Terminated and Void are also subcontract statuses.

Original contract$8,960,000
CCO-03 · fire dampers (CO #14)+$68,000
Revised contract$9,028,000

Subcontract amount illustrative; CCO-03 is the Riverside sub change behind CO #14. The Revised Contract card adds original amount, approved PCOs and approved CCOs.

Sub invoices are entered against the commitment's SOV: this period, materials stored, and retainage at the commitment's rate. The budget reads committed cost from the commitment, not from a spreadsheet someone updates on Fridays.

In the app

The same numbers, by cost code

The Budget tool shows these columns line by line, grouped by division. Analytics' Budget & cost pack (preview) reads the same math and draws it: here EAC and committed cost against each line's revised budget, on a test project with seeded data.

The Cost codes tab of the Budget and cost analytics pack with bars for estimated cost at completion and committed costs by cost code against revised budget ticks.
EAC and committed against revised budget, by cost code. Recorded in the app · sample data
Text version

Every column, as a table

Riverside budget and cost (budget lines illustrative)
ColumnComes fromRiverside
Original budgetEntered per cost code and cost type$42,640,000
ModificationsTransfers between lines$0
Approved budget changesApproved prime contract COs and Budget Changes$860,000
Revised budgetOriginal + modifications + approved$43,500,000
Pending budget changesPrime COs in pricing, pending or proceeding$300,000
Projected budgetRevised + pending$43,800,000
Committed costsApproved subcontracts, POs and commitment changes$36,800,000
Direct costsApproved, pending or revise-and-resubmit direct costs$1,650,000
Pending cost changesCommitment lines and changes not yet approved$500,000
Projected costsCommitted + direct + pending$38,950,000
Forecast to completeDefault projected budget − projected costs; manual override$4,729,800 (manual)
Est. cost at completionProjected costs + forecast to complete$43,679,800
Over/under at completionProjected budget − EAC+$120,200

Keep going

Sample project included

Try this workflow on the sample project

Every trial workspace includes a sample project with sample data, so you can follow these steps in the app before touching a live job.

Try it on the sample project

Want this on live job data?

Budget, commitments, change orders and direct costs are live in os.construction. Company Accounting tracks posted job costs separately; review and reconcile the project and accounting views.

Your role (optional)

14-day free trial. Pricing for paid plans isn't set yet. Talk to us. Already have an account? Sign in →

All figures are illustrative sample data, not a real project. Contract terms and state law decide how retainage, stored materials and change orders work on your job. Check both.

Ask the OS

Reading this page

Ask anything about this page. Answers use what you're reading as context.

Suggested

    AI · may be imperfect · sample data where shown

    Open file