Cost codes and budgets
How cost codes, cost types and budgets work in job costing, and how os.construction keeps budget, committed cost and actual cost on the same structure.
On this page
Job costing only works if every dollar lands in the right bucket. Those buckets are cost codes. This page covers how cost codes and budgets work in construction accounting generally, and how os.construction uses one cost structure for the field, the office and the forecast.
Cost codes and cost types
A cost code identifies a piece of the work. Many contractors base theirs on CSI MasterFormat divisions, then add their own detail:
| Cost code | Description |
|---|---|
| 03-300 | Cast-in-place concrete |
| 05-120 | Structural steel |
| 09-250 | Gypsum board |
| 23-330 | HVAC air duct accessories (fire dampers live here) |
| 26-100 | Electrical, power distribution |
A cost type says what kind of cost it is. In the app the cost types are Labor, Equipment, Materials, Subcontracts and Other. Cost code plus cost type is the most common level at which contractors budget and track cost: “26-100 subcontract” is the Volt Electric subcontract; “03-300 labor” is your own concrete crew.
The four numbers on every cost code
For each cost code on a job, four numbers matter:
- Original budget: what you estimated at contract award.
- Revised budget: original budget plus approved budget changes, mostly from change orders.
- Committed cost: what you have agreed to pay through subcontracts and purchase orders, including their change orders.
- Actual cost: what has been spent, according to the view’s sources. Project Budget uses direct costs and invoiced commitments. Company Accounting job-cost inquiry uses supported posted accounting actuals, including AP, payroll and equipment charges; review the source and posting date when comparing the two.
From those you get the numbers PMs and controllers actually manage by:
- Uncommitted budget = revised budget minus committed cost. Room left to buy out.
- Cost-to-complete = the PM’s estimate of what it will still cost to finish that scope.
- Estimated cost at completion = actual cost plus cost-to-complete.
- Projected over/under = revised budget minus estimated cost at completion.
On Riverside Medical, cost code 26 Electrical (Volt Electric) is running 4% over budget in the sample data. That shows up as a projected overrun on the cost code, and it rolls up into the job’s projected margin of 11.4%.
One structure everywhere
In a disconnected stack, the PM tool and the accounting system each hold a copy of the cost code list and the budget. They drift: a code added in one is missing in the other, or the budget revision for a change order is posted in accounting two weeks after the PM approved it.
In os.construction there is one cost structure per job, and every record that touches money uses it: budget lines, change event lines, change order lines, commitment SOV lines, sub invoice lines and direct costs all carry the cost code.
A superintendent logging extra work or a hidden condition does not need to pick a cost code. When it turns into a change event, the PM attaches the cost code on the change event’s line items, and from then on the cost is visible on the job.
The Budget tool shows original, revised, committed, direct and projected cost by cost code, computed from the other financial tools. Approved owner change orders and approved budget changes update the revised budget on the affected codes, and closing a change event posts its budget change. Forecast to complete is entered against the same codes.
Sub invoices are entered against the commitment they bill, line by line on its schedule of values, so they land on the commitment’s cost codes. Direct costs are coded when they are entered. Company Accounting supports AP coding and supported payroll and equipment postings to the job-cost subledger. These follow their own approval and posting workflows; a project record alone is not a posted cost. See Job cost and WIP.
Budget revisions
Budgets change for three main reasons:
- Owner change orders. CO #14 ($86,400 for fire dampers) increases the contract and adds budget to 23-330.
- Internal transfers. Moving budget from one code to another, for example from contingency to a code that is running short.
- Buyout adjustments. Recording buyout savings or losses when a subcontract is awarded below or above the budget.
In the app, transfers between lines are budget modifications, owner-driven changes come in as approved change orders or budget changes, and change events post their own amounts. Original budget stays as entered, and once you lock the budget it can’t be edited. Snapshots keep a frozen copy you can compare against on the Variance tab.
Commitments against budget
A commitment should never be bigger than the budget it buys without someone deciding that on purpose. Comparing Committed Costs with Revised Budget per code in the Budget tool shows where a commitment is bigger than its budget. The Budget tool doesn’t block or flag an overrun on its own; a negative Projected Over/Under is the signal. On the invoice side, Accounting AP’s commitment match raises an over-commitment exception when a bill exceeds the revised commitment. In the sample data, INV-4471 from Volt Electric ($48,200) exceeds the remaining commitment on PO-118 by $6,150, which is the kind of invoice that check is for. A purchase request also shows its cost codes’ budget figures before anyone approves it (Purchase requests, expenses and direct costs). See Commitments and change orders.
In the app
The Budget guide covers the grid, the Forecast tab, modifications, budget changes, snapshots and variance, locking, CSV export and the Work Breakdown Structure tool where cost codes and code segments are set up.
Next
Read Commitments and change orders to see how buyout and changes flow into these numbers.
Keep exploring
Related across os.construction
- GlossaryCost codeA code that classifies a cost by type of work, and usually by cost type, so budgets and actuals can be compared at a useful level of detail.
- GlossaryCost reportA job report showing, by cost code, the original and revised budget, committed cost, actual cost, cost-to-complete, forecast and variance.
- DocsBudgetBuild the project budget by cost code and cost type, transfer money between lines, forecast cost at completion, take snapshots, compare variance and lock the budget.
- BlogConstruction job costing: how to set up cost codesA cost code list decides what your job cost report can tell you. Too coarse and overruns hide; too fine and the field codes everything to the first line on the list. Here's how to structure codes and cost types, when to follow CSI MasterFormat and when to build your own, a worked tenant improvement budget, and the rules that keep coding clean.
- BlogSchedule of values vs budget: billing lines and cost codes are not the same thingThe schedule of values splits the contract price into lines the owner pays against. The budget splits expected cost into cost codes the contractor manages against. Here is how they differ, why they shouldn't be the same list, how to map one to the other, a worked example and the mistakes that hide over-billing.
- DocsBuyout: from budget to committed costHow construction buyout turns budget lines into subcontracts and POs, how buyout savings and losses are measured per cost code, and how os.construction checks each award against a frozen budget snapshot.
Was this helpful?
Run it on your own project.
Start a 14-day free trial. Want a say in what ships next? Join the founding program.
14-day free trial. Pricing for paid plans isn't set yet. Talk to us. Already have an account? Sign in →