Scheduling / The schedule on a phone or tablet: touch view

The schedule on a phone or tablet: touch view

Use the Planner's touch view on a phone or tablet. Read activities as cards or a pinch-and-pan Gantt that follows your layout's timescale, bars, baselines, filters and progress line, mark work started or finished, set percent complete and remaining duration, then save and recalculate.

On this page

The Planner has a touch view built for phones and tablets. It runs in the phone’s browser; there’s no app to install. It’s designed for the quick jobs you do away from a desk: checking what’s next, reading the critical path in a meeting, or recording progress on site.

When it appears

On a touch device with a screen narrower than 900 px, the Planner opens in touch view. To switch by hand, use Touch view on the desktop grid or Desktop view in touch view. The browser remembers your choice.

Read the schedule

Choose List or Timeline:

  • List shows each activity as a card: ID, name, status, critical flag, float, dates, duration, remaining duration, progress and a mini bar.
  • Timeline is a touch Gantt. Drag with one finger to pan (it keeps moving when you flick), pinch with two to zoom, tap a bar to open the activity, and long-press for its actions.

The touch Gantt follows your layout

The Timeline draws with the same layout as the desktop Planner. If the desktop Planner is open in the same browser tab, it uses that working layout, unsaved changes included. Otherwise it loads the layout the Planner opens with: your default, the project default, or Classic Schedule.

  • Timescale. The layout’s tiers, fiscal and ordinal labels, timescale start and sight lines. To fit, it shows at most two lines on a phone (narrower than 640 px) and three on a tablet. The zoom chips change the interval for the touch view only.
  • Bars. The layout’s bar list with its colours and bar filters, and the legend for the bars in view. Shapes are simplified: hatching becomes a soft fill with a border, bar labels aren’t drawn, and at most five bars draw per row. The data-date line follows Bar Chart Options.
  • Baselines. In the default look, BL1 is a dashed bar under the activity and BL2 and BL3 are thin lines. With a bar list, baselines come from the bar list. A baseline you show from Baselines takes BL1’s place.
  • Progress Spotlight and the progress line. The spotlight band shows on the Timeline, and its end has a 44 px handle you can drag. The layout’s progress line draws over the rows, with its ahead and behind summary under the chart.
  • Layout filters. A filter in Show mode hides the rows that don’t match. In Highlight mode every row stays, and matches are tinted and marked Matches filter on the cards and in the Gantt. The summary counts the matches. Clear highlight (or Clear layout filter) ignores the layout’s filters until you leave the page.

Only the rows on screen are drawn, so a large plan still scrolls smoothly.

View options opens as a bottom sheet:

  • Sort by plan order, start, finish, total float, % complete, duration, activity ID or name.
  • Group by none, WBS, status, criticality, float band, calendar, trade or location.
  • Filter chips for status, critical, negative float, unfinished, longest path, milestones, constrained and open ends.

Bottom sheets close when you drag or flick their handle down.

Record progress

  1. Tap an activity to open its Field update sheet.
  2. Mark started or Mark finished, or Clear actual dates to undo a mistake.
  3. Set percent complete with the 0, 25, 50, 75 and 100 buttons, or Set % for any value.
  4. Adjust remaining duration a day at a time, or Set it.
  5. Save and recalculate. Like any Planner edit, nothing changes until you save, and you can Undo before then.

The sheet also lists the activity’s predecessors and successors. Edit all fields opens the full Activity Details, and More actions… covers the rest. When editing is on, you can also drag bars on the Timeline to move or resize them.

Limits

  • Online only. The touch view needs a connection to load and save. To read the schedule and record progress without signal, use Field mode (offline).
  • You can’t choose a layout in touch view. The Timeline uses the desktop Planner’s working layout, else your default layout. Switch layouts on the desktop.
  • Saved views on a phone stay in that browser. The touch view’s own sort, group and filter-chip views aren’t the server layouts you use on the desktop.
  • Bar labels and patterns are simplified on the touch Gantt, as described above.
  • Marking activities for linking is a desktop action. On touch, use Link to successor.
  • The Activity Network, Trace Logic, Assignments view, Resource Usage, Group & Sort dialog, filter builder and columns dialog are desktop views, as are range selection, fill down, paste and Global Change.
  • Mistake: Marking an activity finished on site and walking away

    In the app: Tap Save and recalculate. Until you save, the change exists only in your draft.

  • Mistake: Expecting a phone saved view on your laptop

    In the app: Touch views are per browser. Save shared views as a Project or Shared layout on the desktop.

Keep exploring

Related across os.construction

Run it on your own project.

Start a 14-day free trial. Want a say in what ships next? Join the founding program.

Your role (optional)

14-day free trial. Pricing for paid plans isn't set yet. Talk to us. Already have an account? Sign in →

Ask the OS

Reading this page

Ask anything about this page. Answers use what you're reading as context.

Suggested

    AI · may be imperfect · sample data where shown

    Open file