Progress Line

Definition

A line drawn down a Gantt chart through the data date that bends out to each activity's progress point, showing at a glance which work is ahead of plan and which is behind.

Topic: Scheduling

A progress line is a status picture on a Gantt chart. It starts as a vertical line at the data date, or another date you choose. For each activity that should be progressing then, the line bends out to that activity’s progress point and back. A point to the right of the line means the work is ahead of plan; a point to the left means it’s behind. The more jagged the line, the more the work has drifted from plan.

The progress point can be placed by percent complete (how far along the bar the work has got), by remaining duration (how far back from the bar’s finish), or by the variance between the baseline and current dates. It’s usually drawn on the baseline bar, so the line compares progress with the plan of record.

Worked example

Illustrative: the data date is 1 November. Duct rough-in is 70% complete on a baseline bar running 20 October to 9 November, so its point sits at about 3 November, right of the line: ahead. Hydronic piping is 10% complete on a bar from 25 October to 20 November, so its point sits at about 28 October: behind.

Why it matters

A table of percentages hides patterns that a progress line shows instantly, such as a whole floor or trade falling behind together. It’s a common exhibit in monthly reports and delay discussions.

How os.construction handles it

The Planner’s Progress Line panel, beside Bar Chart Options, draws the line on the Gantt by percent complete, remaining duration or baseline difference, against the project baseline, your primary baseline or a fixed date, with a count of activities ahead, behind and on plan. It’s saved in the layout and drawn by the print Gantt and the touch Gantt too. See Views and layouts.