Progress Spotlight

Definition

A P6 view feature that highlights the activities that should have progressed between the current data date and a new one, as a guide for statusing.

Topic: Scheduling

Progress Spotlight is a P6 feature for updating a schedule. You move the data date line forward, and P6 highlights every activity scheduled to start or finish between the old and new data dates. Those are the activities that need a status this period.

Worked example

Illustrative: the last update’s data date is 1 June. The scheduler drags the data date to 1 July, and forty activities light up: work forecast to start or finish in June. The scheduler collects actual dates and remaining durations for exactly those forty before recalculating.

Why it matters

The spotlighted set is the minimum a monthly update must address. Activities that were due to start but show no progress are the first sign of slippage. Activities that progressed outside the window may be out of sequence.

How os.construction handles it

The Planner’s Progress Spotlight tints the window from the data date by whole timescale intervals. You size it with + and −, by dragging its edge on the Gantt, or with the arrow keys, and it lists the unfinished activities whose remaining work falls inside it. Update Progress fills their progress in as planned for you to review, can advance the data date, and is one undo step until you save and calculate. If an update period is open, the spotlight can run to that period’s data date. When you submit the update, the Progress not reported check lists activities forecast to start by the new data date that show no actual start. See The update cycle.