User-Defined Field (UDF)

Definition

A custom field added to schedule activities, such as text, a number, a cost, a date or an indicator, for information the standard fields don't hold.

Topic: Scheduling

A user-defined field adds a column of your own to every activity: a permit number, an inspection reference, a risk rating, or a date promised by a supplier. Unlike an activity code, a UDF holds a free value rather than a choice from a list. P6 supports text, number, cost, date, indicator and code-list UDFs.

Worked example

Illustrative: a healthcare renovation adds an Infection control class indicator UDF (green, yellow or red) and an ICRA permit no. text UDF. A filter on red indicators shows every activity that needs the strictest containment before work starts.

Why it matters

UDFs keep project-specific information next to the activity it belongs to, so it can be filtered, grouped and printed with the schedule instead of living in a separate spreadsheet.

How os.construction handles it

The Planner supports Text, Integer, Number, Cost, Start date, Finish date, Indicator and Code list UDFs, editable in Activity Details. They export to XER and P6 XML. Indicator and code-list values export as text, so they come back from P6 as text fields. Three-point risk estimates can also travel as three numeric UDFs.