A layout stores how a schedule is displayed, not what it says. A layout typically holds the columns and their widths, filters, Group & Sort, the Gantt timescale and bar options, and which panes are open. In P6, layouts can be personal, project-wide or global, and new projects usually open in the Classic Schedule Layout.
Worked example
Illustrative: the project controls lead saves an “OAC review” layout to the project. It’s grouped by area, filtered to work due in the next six weeks, and highlights critical activities. Every scheduler on the job opens the same view before the meeting. A superintendent saves a personal “My floor” layout without affecting anyone else.
Why it matters
Shared layouts make schedule reviews repeatable. Everyone looks at the same columns and the same filter, so a number in the meeting means the same thing to every reader. Personal layouts let people work their own way without changing the team’s view.
How os.construction handles it
The Planner opens in Classic Schedule and saves layouts at Mine, Project or Shared (company-wide) scope, with personal and project defaults. See Views and layouts.