Project management

Assignments View

Definition

A schedule view with one row per resource assignment across all activities, showing units, costs, rates, dates and curves, for reviewing and editing resource loading in bulk.

Topic: Scheduling

In a resource-loaded schedule, each activity can have several resource assignments: a crew, a piece of equipment or a cost account, each with its own units, rate and cost. The Assignments view (P6’s Assignments window) lists those assignments across the whole plan as one table, instead of one activity at a time. Each row pairs activity columns (ID, name, WBS, dates, duration type) with resource columns (resource, role) and the loading itself: budgeted, actual, remaining and at-completion units and cost, units per time, price per unit and curve.

Worked example

Illustrative: the estimator revises the concrete crew rate. The scheduler opens the Assignments view, groups by resource, finds the 42 assignments of the concrete crew, and checks the group total of budgeted cost before and after updating the rate on the affected rows.

Why it matters

Cost and resource loading errors hide inside individual activities. Seeing every assignment of a resource, role or area together, with totals, makes rate mistakes, missing assignments and over-budget trades easy to spot.

How os.construction handles it

Assignments is a display mode in the Planner. It groups by resource, role, activity or activity code with totals, sorts on up to four keys, and edits units, units per day, price per unit, costs and curve in place under the activity’s duration-type rules, one undo step per edit. Its setup is saved in the layout. See Views and layouts.