An extension-of-time request needs a traceable explanation of the event, its effect and the applicable contractual process. Waiting until project closeout makes that work harder: people leave, records become scattered and the original forecast assumptions become difficult to reconstruct.
This is an evidence-preparation workflow, not a determination of entitlement or a notice deadline. Read the incorporated terms, amendments and relevant communications with the people responsible for administering the contract. Do not borrow a deadline from another project.
Start an event record
Give the event an identifier and record the first known occurrence, discovery date, affected work, people involved and immediate actions. Preserve the actual documents rather than relying only on a later summary.
| Record group | What to collect |
|---|---|
| Contract process | Applicable provision, notice route, recipients and required information |
| Event | Instruction, RFI response, access record, delivery record or other direct evidence |
| Schedule | Relevant baseline and updates, data dates, settings and narrative |
| Field effect | Daily reports, locations, crew records, photographs and progress evidence |
| Response | Mitigation options, decisions, approvals and implementation records |
| Submission history | Notices, transmittals, responses and receipt evidence |
The SCL Delay and Disruption Protocol discusses records and delay procedures. Use it as a further reference while establishing what your own contract requires.
Explain the chain from event to milestone
In a fictional project, a revised equipment requirement affects fabrication. Identify the instruction, the affected procurement activity, the manufacturer’s revised commitment and the installation/testing sequence. Then examine whether that sequence drives the relevant milestone during the period.
The event’s duration is not automatically the extension requested. Available float, overlapping work, other controlling paths and actual mitigation can change the effect. State the analysis method and the evidence supporting the connection.
Maintain a living chronology
Use one row per material development: date, event, source reference, affected activity, action and unresolved question. Keep factual observations separate from the team’s interpretation. If two records conflict, preserve both and identify the issue rather than silently choosing the convenient one.
Track notice and submission obligations independently from the schedule analysis. A strong model does not demonstrate that a communication reached the right recipient at the right time.
Make the request reviewable
Prepare an index linking each material assertion to its record. Explain the requested milestone adjustment, the calculation units, the method, assumptions and remaining uncertainty. Keep time and money analyses distinguishable; they may require different evidence and contractual treatment.
Before submission, have the responsible project and contract reviewers check completeness and consistency. Continue with time impact analysis, concurrent delay and the Schedule Forensics resource library.