THE SOURCE DESK

Find the requirement.
Then check the edition.

A scheduling threshold only helps when you know where it came from. Use this directory to find the publisher, then match the document to your project.

Before you apply a rule

  1. Identify the incorporated document. Start with the executed contract, amendments, special provisions, and order of precedence.
  2. Record the edition and clause. A current web page may differ from the edition your contract incorporates.
  3. Read the applicability and exceptions. Note project category, units, approval routes, and any bracketed options.
  4. Keep the evidence. Record the source URL, document date, retrieval date, and the review decision in a specification matrix.

Publisher portals checked 2026-11-08. These are navigation references, not a certification that a clause applies to your project. Agency training and review guidance are not automatically contract terms.

State agencies

Alabama DOT ↗

Highway construction specifications and amendments.

Check: Match the specification edition and effective amendments to the letting and contract documents.

Arizona DOT ↗

Road and bridge specifications, stored specifications, and pay items.

Check: Read the contract special provisions alongside the applicable standard book; do not assume the newest posted book governs.

Caltrans ↗

Construction contract standards, specifications, and implementation notices.

Check: Confirm the edition and schedule bid item before applying a CPM requirement. The portal includes an implementation notice for 2026 standards.

Colorado DOT ↗

Construction specification editions and related guidance.

Check: Check the project advertisement and special provisions for the applicable schedule requirements.

Idaho Transportation Department ↗

Standard specification book, supplementals, and construction manuals.

Check: Keep the applicable supplemental specifications with the base book when assembling the review record.

Iowa DOT ↗

Specification guidance and access to the Electronic Reference Library.

Check: Record the ERL issue and the project-specific provisions; distinguish standard, supplemental, and developmental specifications.

Maryland State Highway Administration ↗

Standard and supplemental specifications with dated special provision inserts.

Check: Look for schedule and claims provisions in the incorporated contract, not only in a keyword search of the standard book.

Michigan DOT ↗

Construction guidance with links to specifications and construction scheduling.

Check: Use the scheduling resources and contract special provisions together; distinguish review guidance from contract obligations.

Minnesota DOT ↗

Standard specifications for construction and edition history.

Check: Confirm the applicable special provision and required schedule type before applying a CPM checklist.

New Jersey DOT ↗

Standard specification divisions for road and bridge construction.

Check: Read the project supplementary specifications and schedule submission requirements with the base specification.

New York State DOT ↗

Official electronic specifications with adoption dates.

Check: Identify the incorporated CPM item and type, then obtain the relevant scheduling guidance; a training guide is not a contract amendment.

PennDOT ↗

Publication 615, the agency scheduling manual.

Check: Confirm the revision and whether the procedure concerns design or construction; also check the construction contract requirements.

South Carolina DOT ↗

Highway construction specification editions and change information.

Check: Match the project to its incorporated edition before using schedule update or recovery requirements.

Tennessee DOT ↗

Construction special provisions and dated specification notices.

Check: Locate the applicable standard book and special provisions together; read the effective dates and obsolete-provision notices.

Texas DOT ↗

The 2024 standard specification book and related resources.

Check: Check contract items and special provisions for schedule type, updates, and supporting submissions; retain a record of the edition used.

Utah DOT ↗

Standard specifications, drawings, and special provisions by edition.

Check: Identify the applicable standard specification and project-specific revisions before selecting schedule review criteria.

Virginia DOT ↗

Road and bridge specifications, supplements, and prior editions.

Check: Confirm the contract schedule category and applicable special provision; do not carry clause numbers between categories.

Wisconsin DOT ↗

Standard specifications and updates for highway and structure construction.

Check: Record the contract edition and supplemental provisions before comparing a submission against schedule requirements.

Washington State DOT ↗

Road, bridge, and municipal construction specifications with revision history.

Check: Read the contract scheduling provision and required schedule type, along with amendments to the selected edition.

West Virginia Division of Highways ↗

Road and bridge specifications, archives, and publications.

Check: Confirm the contract schedule classification, incorporated edition, and project special provisions.

Federal guidance

GAO Schedule Assessment Guide ↗

GAO-16-89G explains practices for developing and assessing reliable schedules.

Check: Use it to structure a quality review; separately identify which requirements the contract incorporates.

UFGS: USACE Project Schedule ↗

Guide specification 01 32 01.00 10 for project schedules.

Check: Compare the guide with the issued project specification, including edited options and dates. A guide specification is a starting point for contract drafting.

USACE ER 1-1-11 ↗

Official regulation directory: search for ER 1-1-11, Project Schedules.

Check: Distinguish agency schedule-management policy from the requirements actually included in a construction contract.

DCMA policy library ↗

Current policy publications, including earned value management surveillance.

Check: Do not present historical 14-point metrics as universal construction acceptance criteria or as proof of current agency policy.

FHWA state specification directory ↗

A starting point for locating specification publishers across the United States.

Check: Follow through to the state publisher and confirm the edition and contract applicability; directory links can change.

Professional guidance

AACE recommended practices ↗

Publisher library for recommended practices, including forensic schedule analysis.

Check: Obtain the relevant practice from the publisher under its access terms. Method selection still depends on the question and available records.

ASCE 67-17: Schedule Delay Analysis ↗

Publisher entry for the schedule delay analysis standard.

Check: Confirm the edition cited by the engagement or contract and use the licensed standard directly for detailed interpretation.

SCL Delay and Disruption Protocol ↗

The Society of Construction Law protocol, second edition, February 2017.

Check: Read its scope and the contract context. Guidance does not replace contract terms or jurisdiction-specific legal advice.

Turn a reference into a clear review comment

Write: “The imported file contains [condition] on [activity IDs]. The project specification [edition, clause] requires [your paraphrase]. Please provide [record or explanation] so the reviewer can resolve [question].” Keep the measured condition, requirement, and requested decision separate.

Use the review checklist → · Download the templates →