THE LANGUAGE OF THE PLAN

A shared vocabulary.
A clearer schedule review.

Understand the terms behind the dates. These 46 definitions connect the language of CPM schedules to practical examples, review questions, and deeper guides.

A

Activity

A defined piece of work represented in a schedule. Its dates depend on its duration, calendar, relationships, progress, and any constraints. Activity types matter: a milestone or summary is not the same as a task.

Build useful activities
Actual finish

The recorded date and time work finished. It describes reported history, not a calculated forecast. Confirm it against field records and the status cutoff before relying on it.

Understand the status cutoff
Actual start

The recorded date and time work began. An actual start should have a supporting record; importing or calculating a schedule does not verify that the work happened.

Document progress
ALAP (as late as possible)

A scheduling instruction that places an activity as late as the calculation permits. Its treatment is software-specific and can change displayed dates or float. Record the instruction rather than interpreting its dates in isolation.

Review constraints and placement
As-built schedule

A representation of what happened, assembled from actual dates and supporting records. A list of actual dates is not necessarily a logic network that can be recalculated for a modeled analysis.

Match methods to available records
As-planned schedule

The plan used as the reference for an analysis of intended work. Identify the exact version and its status; the first file received is not automatically the agreed baseline.

Establish the reference plan

B

Baseline

A preserved reference schedule against which later progress and forecasts are compared. Record its version, assumptions, and acceptance status; a routine update does not automatically replace it.

Read the baseline definition

C

Calendar

The working-time rules used to translate durations into dates, including shifts, holidays, and exceptions. Five working days on one calendar may cover a different elapsed period from five days on another.

See a calendar example
Collapsed as-built

A modeled analysis that removes selected event effects from a reconstructed as-built network to investigate a counterfactual completion. The reconstruction, removed effects, and recalculation assumptions need to be explained.

Compare analysis methods
Concurrency

A question about whether multiple delays affected the relevant completion during the period being analyzed. Overlapping event dates alone do not settle it. State the analytical test, affected paths, period, and assumptions.

Investigate concurrent delay
Constraint

A scheduling rule that imposes a date limit or placement instruction beyond ordinary activity relationships. Different constraint types affect early dates, late dates, or both. Inventory the type, date, reason, and authority.

Review schedule constraints
Critical activity

An activity classified as critical under a stated test, such as a float threshold or membership of a driving path. Name the test: different settings can classify the same activity differently.

Interpret quality checks
Critical path

The driving sequence behind a selected completion milestone under the modeled logic, calendars, and settings. A zero-float filter is not always the same as tracing the relationships that drive the milestone.

Read the critical path definition

D

Dangling logic

Relationships that leave an activity start or finish insufficiently connected even though the activity has a predecessor and successor. Check both ends: counting links alone can miss a finish that does not drive any following work.

Use the audit checklist
Data date

The status cutoff separating recorded progress from the remaining-work forecast. Record its date, time, and convention so readers know which reporting period an actual event belongs to.

Read the data date definition
Driving relationship

A relationship that sets a date bound controlling its connected activity in the calculation. More than one relationship can tie at the controlling bound, so the driving network can branch.

Trace schedule logic
Duration

The working time assigned to an activity. Distinguish original duration, remaining duration, and the software’s at-completion duration. Keep units and calendar assumptions with the number.

Explain a duration basis

F

Finish-to-finish (FF)

A relationship linking the successor’s finish to the predecessor’s finish, adjusted for any lag. It does not, by itself, define the successor’s start.

Model relationship types
Finish-to-start (FS)

A relationship linking the successor’s start to the predecessor’s finish, adjusted for any lag. With zero lag, the linked event is completion of the predecessor before the successor can start.

Understand relationship timing
Float

Calculated timing flexibility. Specify which float, the calculation anchor, and the calendar. Float is a network result; it does not establish ownership or entitlement.

Read the float definition
Fragnet

A small linked group of activities representing an event or change inside a larger schedule. Its attachment points, durations, calendars, and event timing are analytical choices that need evidence.

Build an explainable time impact analysis
Free float

The timing flexibility before an activity movement delays a successor’s early date under the modeled relationships and calendars. It answers a different question from total float.

Compare free and total float

H

Hard constraint

A label often used for constraints that can force dates or interfere with normal network calculation. Software and review tools may classify types differently, so examine the actual constraint rather than relying on the label.

Inspect the actual constraint type

L

Lag

A time offset on a relationship rather than a separate activity. Check its value, relationship type, and calculation calendar. A long waiting period may be clearer as a named activity with an owner.

Review lags and leads
Lead

A negative relationship lag that permits overlap relative to the linked predecessor event. It can make the work sequence harder to explain; review whether explicit activities and relationships express the plan more clearly.

Make overlap visible
Level of effort

An activity type representing support work whose time span depends on other activities, such as ongoing supervision. Review how the software derives its dates and whether the contract permits or requires that modeling approach.

Distinguish work and support activities
Longest path

A path identified by tracing driving relationships to a selected finish using the scheduling software’s rules. It may differ from a list of activities below a total-float threshold. Identify the endpoint and calculation settings.

Compare path and float definitions

M

Method Implementation Protocol (MIP)

A method identifier in AACE’s forensic schedule analysis framework. A familiar method name alone may not describe the implementation: identify the reference schedules, time periods, and modeling steps as well.

Navigate the professional references
Milestone

A zero-duration activity marking an event such as access, approval, or completion. Start and finish milestones represent different boundaries; connect the milestone to the work that actually controls it.

Define meaningful milestones

N

Negative float

A result in which calculated late dates precede early dates under the applicable rules, often indicating conflict with a required date. Investigate its constraint and network basis; the sign alone does not establish fault.

Interpret the float calculation

O

Open end

An activity lacking a predecessor, successor, or both in the reviewed network. It can indicate missing logic, an intentional endpoint, or an incomplete export. Check the context before calling it an error.

Investigate open ends
Out-of-sequence progress

Recorded work that starts or progresses before the modeled relationships would normally allow it. It signals a difference between the plan and reported execution; field records and scheduling settings explain what happens next.

Review out-of-sequence work

P

Predecessor

The activity supplying the start or finish event to which another activity is linked. Its relationship type and lag determine which event matters.

Follow the logic links
Progress override

A scheduling option that can allow remaining work on a started activity to proceed despite unfinished predecessor logic. Its effect depends on the network and software; preserve the setting when comparing updates.

Review P6 scheduling options

R

Relationship

A logic link between activity events: finish-to-start, start-to-start, finish-to-finish, or start-to-finish. The link describes a dependency; a WBS grouping or a nearby bar on a chart does not.

Build a meaningful network
Remaining duration

The estimated working time still needed for an activity as of the status cutoff. It is a forecast that needs a field basis, not an automatic consequence of a reported percent complete.

Explain the remaining-work forecast
Retained logic

A scheduling option that continues to respect predecessor logic for remaining work when progress occurs out of sequence. Review the actual relationships and software behavior rather than assuming a fixed difference from progress override.

Compare scheduling settings

S

Schedule update

A version of the schedule recording progress and a remaining-work forecast at a stated data date. Preserve the sequence of updates and the reasons for changes so a reviewer can reconstruct what was known over time.

Write a useful update narrative
Soft constraint

A date-limit constraint that influences calculation while allowing network logic to continue, such as a no-earlier-than or no-later-than restriction. “Soft” does not mean harmless; it can still change float and the forecast.

Understand date limits
Start-to-finish (SF)

A relationship linking the successor’s finish to the predecessor’s start, adjusted for lag. Because that dependency is easy to misunderstand, explain the actual handoff it represents.

Explain the dependency
Start-to-start (SS)

A relationship linking the successor’s start to the predecessor’s start, adjusted for lag. It models a start dependency; additional logic may be needed to represent a finish dependency.

Check overlapping work
Successor

The activity whose start or finish event is linked to a predecessor. Review both incoming and outgoing relationships when tracing an impact through the network.

Trace the affected work

T

Time impact analysis (TIA)

An analysis that inserts an event model into a selected schedule and compares calculated milestone dates. Name the selected update, event timing, and whether the analysis is prospective or retrospective.

Read the TIA definition
Total float

The difference between early and late dates under the selected calculation rules. Its interpretation depends on the backward-pass anchor, constraints, and calendars; it is not automatically an independent buffer for each activity.

Work through the float example

W

Windows analysis

A family of approaches that investigates the project in periods rather than as a single span. State how the windows were chosen, which schedules were used, and whether the analysis observes records or models changes.

Distinguish method implementations
Work breakdown structure (WBS)

A hierarchy for organizing project scope and activities. It helps readers navigate the plan but does not create the relationships that drive dates.

Structure a reviewable baseline

Where these definitions come from

This glossary is an original adaptation of the scheduling vocabulary developed in the Schedule Forensics project, rewritten for the os.construction field guide. It covers every concept in that source glossary and links to worked explanations rather than reproducing standards text.

Use the primary-source directory to consult GAO guidance, agency specifications, and professional references. This page explains vocabulary; it does not prescribe a contract interpretation or determine a claim.