Total float and free float: explain the difference at the coordination meeting

Use a simple construction network to distinguish total float from free float and understand why an activity can affect a trade before completion.

Charley Forey2 min readSchedulingSchedule forensics
On this page
  1. A separate worked example
  2. Why the real file needs more context
  3. Use float to ask a better question

An activity can have room before the project finish and still have no room before the next trade arrives. That is the practical difference between total float and free float. Treating them as interchangeable turns a coordination decision into a surprise.

In a simple unconstrained network, total float measures available movement before delaying project completion. Free float measures movement before affecting a successor’s early timing. Oracle’s About Float explains the distinction for P6.

Illustrative, single-calendar network. Structure and procurement start together; installation waits for both. The longer branch controls the finish.

A separate worked example

Use one working-day calendar, finish-to-start links, zero lag, and time boundaries measured from day zero. This fictional network has two paths to the finish:

Activity Duration Predecessor Earliest interval
A: equipment preparation 4 days Start Day 0–4
B: equipment installation 3 days A Day 4–7
C: parallel fit-out 10 days Start Day 0–10
Finish milestone 0 days B and C Day 10

Path A–B needs seven days; path C needs ten. A has three days of total float in this example, but zero free float: moving A’s finish immediately moves B’s early start. B has three days of free float before it affects the finish milestone.

The three days are shared along A–B. They are not three days for A plus another three days for B. If A consumes two and B then consumes two, the combined path is eleven days and completion moves by one day, assuming everything else remains unchanged.

Why the real file needs more context

Constraints can introduce negative float. Multiple calendars can make two activities’ displayed “days” hard to compare. A chosen total-float definition can differ from a longest-path classification. These are reasons to inspect the network and settings rather than treating a float column as a complete explanation.

Record the milestone being protected. A task can threaten an interim handover even when overall completion has room. Similarly, a subcontractor may have a real crew commitment on an early date that the network does not represent.

Use float to ask a better question

Instead of “This has float, so it can wait,” ask: “What moves if we defer this work, how much shared path margin remains, and who needs to agree to the new handoff?” Review the next trade, procurement commitments and site access before making the change.

Float arithmetic does not determine who is entitled to use the time. If ownership or entitlement matters, identify the applicable contract provisions and obtain a project-specific interpretation.

To check this arithmetic on your own network, enter the activities in the critical path calculator: it calculates total float and free float for every activity and writes out each step.

Next, read constraints and negative float or concurrent delay. The resource library connects these concepts to a complete review workflow.

Share this article

Written by

Charley Forey

Founder of os.construction. We're building the operating system for construction. Project Financials follows job money, and company Accounting covers the books and controls. AI agents remain planned. We write about how money and data actually move on a job, and we build in public.

Apply to the founding program →Start a free trial →
Open file