An activity can have room before the project finish and still have no room before the next trade arrives. That is the practical difference between total float and free float. Treating them as interchangeable turns a coordination decision into a surprise.
In a simple unconstrained network, total float measures available movement before delaying project completion. Free float measures movement before affecting a successor’s early timing. Oracle’s About Float explains the distinction for P6.
A separate worked example
Use one working-day calendar, finish-to-start links, zero lag, and time boundaries measured from day zero. This fictional network has two paths to the finish:
| Activity | Duration | Predecessor | Earliest interval |
|---|---|---|---|
| A: equipment preparation | 4 days | Start | Day 0–4 |
| B: equipment installation | 3 days | A | Day 4–7 |
| C: parallel fit-out | 10 days | Start | Day 0–10 |
| Finish milestone | 0 days | B and C | Day 10 |
Path A–B needs seven days; path C needs ten. A has three days of total float in this example, but zero free float: moving A’s finish immediately moves B’s early start. B has three days of free float before it affects the finish milestone.
The three days are shared along A–B. They are not three days for A plus another three days for B. If A consumes two and B then consumes two, the combined path is eleven days and completion moves by one day, assuming everything else remains unchanged.
Why the real file needs more context
Constraints can introduce negative float. Multiple calendars can make two activities’ displayed “days” hard to compare. A chosen total-float definition can differ from a longest-path classification. These are reasons to inspect the network and settings rather than treating a float column as a complete explanation.
Record the milestone being protected. A task can threaten an interim handover even when overall completion has room. Similarly, a subcontractor may have a real crew commitment on an early date that the network does not represent.
Use float to ask a better question
Instead of “This has float, so it can wait,” ask: “What moves if we defer this work, how much shared path margin remains, and who needs to agree to the new handoff?” Review the next trade, procurement commitments and site access before making the change.
Float arithmetic does not determine who is entitled to use the time. If ownership or entitlement matters, identify the applicable contract provisions and obtain a project-specific interpretation.
To check this arithmetic on your own network, enter the activities in the critical path calculator: it calculates total float and free float for every activity and writes out each step.
Next, read constraints and negative float or concurrent delay. The resource library connects these concepts to a complete review workflow.