How the critical path works

Eight activities, two passes and one late delivery. Step through the forward pass, the backward pass and the float between them, find the critical path, then watch a three-day slip move the finish date and hand the critical path to a different chain.

Visual guide9 min read

The short answer

What is the critical path?

The critical path is the longest chain of dependent activities through a schedule, and it sets the earliest date the project can finish. Its activities have no total float: delay one by a day and completion moves by a day. Every other activity has some room to slip before it matters.

The critical path method (CPM) finds it with two passes through the network. The forward pass gives every activity its earliest dates; the backward pass, run from the finish, gives its latest dates. The difference is float. Step through it below, on an illustrative eight-activity building shell.

Step by step

Two passes, one critical path

Step 5 of 6: The critical path

Activity-on-node network with early dates, late dates, float and the critical pathA Mobilize, 2 days: early 0 to 2, late 0 to 2, total float 0. B Excavate, footings, 5 days, after A: early 2 to 7, late 2 to 7, total float 0. C Steel fabrication, 10 days, after A: early 2 to 12, late 3 to 13, total float 1. D Foundation walls, 6 days, after B: early 7 to 13, late 7 to 13, total float 0. E U/G plumbing, 3 days, after B: early 7 to 10, late 12 to 15, total float 5. F Erect steel, 6 days, after C and D: early 13 to 19, late 13 to 19, total float 0. G Slab on grade, 4 days, after D and E: early 13 to 17, late 15 to 19, total float 2. H Roof, dry-in, 5 days, after F and G: early 19 to 24, late 19 to 24, total float 0. Critical path A → B → D → F → H, finish day 24. After a 3-day steel delay: critical path A → C → F → H, finish day 26.FORWARD PASS → early dates, top row← BACKWARD PASS: late dates, bottom rowES 02dEF 2A MobilizeLS 0TF 0LF 2ES 25dEF 7B Excavate, footingsLS 2TF 0LF 7ES 210dEF 12C Steel fabricationLS 3TF 1LF 13ES 76dEF 13D Foundation wallsLS 7TF 0LF 13ES 73dEF 10E U/G plumbingLS 12TF 5LF 15ES 136dEF 19F Erect steelLS 13TF 0LF 19ES 134dEF 17G Slab on gradeLS 15TF 2LF 19ES 195dEF 24H Roof, dry-inLS 19TF 0LF 24Finish: day 24+3 days late
  1. Eight activities, each with a duration in working days and the activities it waits for. Mobilize (A) comes first; footings (B) and steel fabrication (C) can both start once the site is mobilized; roofing (H) cannot start until steel is erected (F) and the slab is poured (G). This is an activity-on-node network with finish-to-start links, the way Primavera P6 and Microsoft Project draw logic.

  2. Work left to right. Each activity’s early start (ES) is the latest early finish (EF) of its predecessors, and EF = ES + duration. A runs 0 to 2. B runs 2 to 7 and C runs 2 to 12. Erect steel (F) waits for both C (12) and the walls (D, 13), so it starts at 13. Roofing starts at 19, the later of F (19) and G (17), and finishes at day 24: the project duration.

  3. Work right to left from the finish. Each activity’s late finish (LF) is the earliest late start (LS) of its successors, and LS = LF − duration. Roofing must finish by 24, so it must start by 19. The walls (D) feed both F (LS 13) and G (LS 15), so D must finish by 13, the earlier of the two. Steel fabrication must finish by 13 and start by 3.

  4. Total float (TF) = LS − ES. Steel fabrication has 1 day of total float, the slab 2 days and underground plumbing 5 days. Free float (FF) is the slip that delays no successor’s early start: plumbing has 3 days of free float but 5 of total float, because using more than 3 days pushes the slab, which has float of its own.

  5. The activities with zero total float form the critical path: A → B → D → F → H, 24 working days. It is also the longest path through the network. Delay any activity on it by a day and the finish moves a day. Shorten an activity that is not on it and the finish does not move at all.

  6. The steel fabricator reports a 3-day delay, so C takes 13 days instead of 10. C had 1 day of float, so the first day is absorbed and the remaining 2 push the finish from day 24 to day 26. The critical path moves to A → C → F → H. Footings and walls, critical a moment ago, now have 2 days of float.

Critical (zero total float)Has floatES/EF early start and finish · LS/LF late start and finish · TF total float · d duration, in working days
Illustrative network. Choose a step, use Previous and Next, or press Play. Day 0 is the data date: an activity with ES 0 and a 2-day duration works days 1 and 2 and finishes at 2.
Worked example

The numbers, before and after the slip

Every date in the network comes from two rules applied in order. Forward: ES = the largest EF among predecessors, EF = ES + duration. Backward: LF = the smallest LS among successors, LS = LF − duration. Float is the difference.

Forward pass    ES = max(predecessor EF)      EF = ES + duration
Backward pass   LF = min(successor LS)        LS = LF − duration
Total float     TF = LS − ES  (= LF − EF)
Free float      FF = min(successor ES) − EF
Critical        TF = 0   →   A → B → D → F → H, 24 days
Illustrative shell · working days · before the slip, and after steel fabrication runs 3 days long
ActivityWaits forBefore the slipAfter
DurESEFLSLFTF / FFDurTF
A Mobilize–202020 / 020
B Excavate, footingsA527270 / 052
C Steel fabricationA102123131 / 1130
D Foundation wallsB67137130 / 062
E U/G plumbingB371012155 / 337
F Erect steelC, D6131913190 / 060
G Slab on gradeD, E4131715192 / 244
H Roof, dry-inF, G5192419240 / 050
Project finishDay 24 · critical path A → B → D → F → HDay 26 · A → C → F → H

Read the slip the way a scheduler would. Steel fabrication was 3 days late but the finish moved only 2, because C had 1 day of float to absorb. The foundations, critical before, now have 2 days of float, so a crew on the walls could be moved without cost to the finish. And roofing, critical in both versions, now starts on day 21 instead of 19.

The critical path calculator runs the same two passes on your own activities, with start-to-start, finish-to-finish and lag relationships, a Gantt and a network view, and every step of the math written out.

Float

Total float, free float, and who gets to use it

Total float is how far an activity can slip before the finish moves; free float is how far it can slip before the next activity moves. Underground plumbing shows the difference. It finishes at day 10 and the slab cannot start until day 13 anyway, so it has 3 days of free float. Slip it further and the slab starts later, but the slab has 2 days of float of its own, so plumbing’s total float is 5.

  • Float belongs to a path. Plumbing and the slab share the slab’s 2 days. Use them on plumbing and the slab has none left. Adding up float activity by activity double-counts it.
  • Near-critical matters. Steel fabrication had one day. Paths with a few days of float are where next month’s critical path usually comes from, so many schedulers watch everything under a float threshold, not only zero.
  • Ownership is a contract question. Some contracts make float a shared project resource, available to whoever uses it first; others assign it. The arithmetic does not decide that. See the guide to total float and free float.
Real schedules

What changes on a live schedule

The two passes never change, but a live schedule feeds them more than durations and logic. Four things make real critical paths harder to read than the example:

  • The data date. On an updated schedule the forward pass starts from the data date. Work before it is recorded as actuals; only remaining work is calculated, so the critical path can only run through what is left.
  • Out-of-sequence progress. When an activity starts before its predecessor finishes, the scheduler has to choose. Under retained logic, the remaining work still waits for the unfinished predecessor; under progress override, it does not. The same file can produce different finish dates and different critical paths.
  • Calendars and constraints. Activities on different calendars count float in their own working days, and a hard constraint can make an activity critical, or give it negative float, regardless of the logic. That is why “zero total float” and “on the longest path” stop meaning the same thing, and why Primavera P6 offers both definitions of critical.
  • Missing logic. An activity with no successor (an open end) has float measured to the project finish, which is usually meaningless. A critical path is only as trustworthy as the links behind it.

In os.construction, Scheduling runs the CPM calculation on every save and returns, for each activity, early and late start and finish, total and free float in working days, the critical flag and whether it is on the longest path, plus the ordered longest path and the driving predecessors behind each date. Retained logic is the default progress mode, progress override is available, and the result records which mode produced it. See planning and CPM in the docs.

FAQ

Common questions

How do you find the critical path?

Run a forward pass through the network to get each activity’s early start and early finish, then a backward pass from the project finish to get its late start and late finish. Total float is late start minus early start. In a network with one calendar and no date constraints, the activities with zero total float form the critical path, which is also the longest path through the logic.

What is the difference between total float and free float?

Total float is how far an activity can slip before it delays the project finish. Free float is how far it can slip before it delays the early start of any successor. Free float is never more than total float. In the example, underground plumbing has 5 days of total float but only 3 of free float: a fourth day of slip pushes the slab, though the finish still holds.

Can the critical path change during a project?

Yes, and it usually does. When a non-critical activity slips by more than its float, or a critical activity finishes early, a different chain becomes the longest. In the example, a 3-day steel delay uses up steel’s 1 day of float, moves the finish 2 days and makes steel, not the foundations, the critical path. That is why the path should be re-checked at every schedule update.

Can a schedule have more than one critical path?

Yes. If two chains of activities are exactly as long, both have zero total float and both are critical. A delay on either one moves the finish. Near-critical paths, with only a few days of float, matter too: a small slip turns them critical, which is why schedulers often report everything under a float threshold rather than only zero.

What does negative float mean?

Negative float appears when a date constraint, such as a contract completion date, is earlier than the network can achieve. The backward pass then starts from the constraint, late dates come out earlier than early dates, and total float goes below zero. Minus 5 days means the logic forecasts finishing 5 working days after the required date.

Keep going

Sources and further reading

  • GAO Schedule Assessment Guide: best practices for project schedules, including a valid critical path and reasonable total float.
  • PMI standards: the Practice Standard for Scheduling covers the critical path method, float and the forward and backward pass.
  • AACE International: recommended practices for planning and scheduling and for schedule analysis.

General information only. Every figure on this page is illustrative.

Want this on live job data?

In os.construction Scheduling, every save runs the CPM calculation: early and late dates, total and free float, the critical flag and the longest path for each activity, with the driving predecessors behind every date.

Your role (optional)

14-day free trial. Pricing for paid plans isn't set yet. Talk to us. Already have an account? Sign in →

General information, not scheduling or legal advice. The job and every figure on this page are illustrative. Real schedules add calendars, constraints, progress and contract terms that change both the arithmetic and who owns the float.

Ask the OS

Reading this page

Ask anything about this page. Answers use what you're reading as context.

Suggested

    AI · may be imperfect · sample data where shown

    Open file