Esc

↑↓ move↵ openIndex · Pagefind
Analytics

Percent complete (cost-to-cost)

Definition

A job's progress measured as cost incurred to date divided by total estimated cost; the most common basis for recognizing contract revenue.

Part of: Construction cost reporting: accruals, earned revenue, EAC and WIP

Topic: Accounting & WIP

Updated

Percent complete measures how far along a job is. The cost-to-cost method, the most widely used for contract revenue, divides cost to date by estimated total cost (cost to date plus estimated cost to complete). It’s an input method under ASC 606, which lets most contractors recognize revenue over time as work progresses.

How it works

  1. Cost to date. Posted job cost through the period cutoff, with unbilled sub and supplier costs accrued.
  2. Cost to complete. The PM’s current cost-to-complete forecast, built by cost code.
  3. Estimated total cost. Cost to date plus cost to complete. This is the job’s estimate at completion.
  4. Percent complete. Cost to date ÷ estimated total cost.
  5. Earned revenue. Percent complete × current contract value, including approved changes, gives earned revenue.
  6. Compare with billing. Earned revenue minus billed to date is under billing if positive, over billing if negative. Both go on the WIP schedule.

Why it matters

Percent complete drives earned revenue, which drives over and under billing, which drives reported profit. If the estimated total cost is wrong, every number downstream is wrong too. It’s also different from physical percent complete or billed percent complete, and mixing them up is a common source of bad WIP schedules. Earned value vs percent complete explains why cost-based percent complete can’t measure performance.

Worked example

Illustrative: Riverside Medical Center has a $49.3M contract and a projected margin of 11.4%, so estimated total cost is $49.3M times 0.886, or $43.68M. Cost to date is $31.7M.

Percent complete = $31.7M / $43.68M = 72.6%.

Pay App #9 shows $33.0M billed, 66.9% of the contract, and the field’s physical estimate is close to that. A 5.7-point gap is worth a conversation: it can mean costs are front-loaded (material bought early), or that the cost estimate is too low.

Suppose $1.2M of the cost to date is switchgear delivered to site but not yet installed. Excluding it from both cost to date and estimated total cost:

Line All cost included Switchgear excluded
Cost counted $31.70M $30.50M
Estimated total cost counted $43.68M $42.48M
Percent complete 72.6% 71.8%
Revenue on the measured work $35.78M 71.8% × $48.10M = $34.54M
Revenue on the switchgear (at cost) n/a $1.20M
Earned revenue $35.78M $35.74M

The difference is about $44,000: the margin that would otherwise have been recognized on equipment nobody has installed yet. Here the effect is small; on a job where a large share of cost is long-lead equipment, it can move earned revenue by much more. See uninstalled materials.

Ways to measure progress

Measure Basis Typical use
Cost-to-cost Cost to date ÷ estimated total cost Revenue recognition, WIP
Labor hours Hours to date ÷ estimated total hours Labor-heavy self-performed work
Physical percent complete Field assessment of work in place Progress reporting, sanity check
Units installed Quantities in place ÷ total quantities Unit-price work, repetitive scopes
Billed percent Billed to date ÷ contract value Pay applications, not revenue

ASC 606 calls the first two input methods and the units measure an output method. Whichever one is used for revenue should be applied consistently to similar contracts. Physical percent complete is still worth collecting even when revenue uses cost-to-cost: when the two drift apart by more than a few points, either the field estimate is optimistic or the cost forecast is out of date, and both are worth knowing before the WIP is signed off.

Common mistakes

  • Using billed percent from the pay app instead of cost-to-cost.
  • Including uninstalled stored materials in cost to date, which can overstate progress. Many contractors exclude them from the calculation.
  • Updating cost to date monthly but the cost estimate only quarterly.
  • Counting costs that don’t reflect progress, such as rework from the contractor’s own errors or wasted materials.
  • Leaving late invoices out of cost to date, which understates progress and pushes revenue into later periods.
  • Applying percent complete to the original contract value after approved change orders have changed it.

For when the method gives misleading answers, see cost-to-cost percent complete: when it lies.

How os.construction handles it

In Accounting, the WIP app calculates cost-to-cost percent complete from posted job cost and the approved forecast frozen at period end, and a cost code’s forecast can use physical percent complete. Schedule progress feeds earned value in Analytics, so cost progress and field progress can be compared. See Job cost and WIP and Dashboards, earned value and WIP.

Watch the explainer · 0:48

Progress Fell. Where Did the Work Go?

Read the transcript

The progress meter drops. But watch the completed work: none of it disappears. What changed?

In this example, every unit counts equally. Forty completed units out of one hundred total means forty percent complete.

Now assume twenty additional units are approved for this measured scope. Forty out of one hundred twenty is about thirty-three point three percent.

The completed quantity stayed forty. The total grew. Check the completed count, total scope, measurement basis, and reporting date before comparing percentages.

Keep the old scope reference and explain the change. Explore progress measures at os dot construction.

Watch the explainer · 1:55

Cost-to-cost percent complete: when it lies

  1. 0:00One formula, one assumption
  2. 0:21An illustrative job
  3. 0:37Material bought, not installed
  4. 0:56A stale cost to complete
  5. 1:16Get a second opinion
  6. 1:37Percent complete in os.construction
Read the transcript

Most contractors measure percent complete with the cost-to-cost method: cost to date divided by estimated total cost. It's simple, and auditors know it. It also assumes every dollar spent is the same amount of progress. When that isn't true, earned revenue and over and under billing are wrong too.

Take an illustrative job: a ten million dollar contract with nine million dollars of estimated cost, a ten percent margin. With three point six million dollars spent, the job is forty percent complete, and you've earned four million dollars of revenue.

Now the mechanical sub buys six hundred thousand dollars of rooftop units early. The invoice posts, and cost to date jumps to four point two million. Percent complete jumps to about forty-seven percent, and about six hundred sixty-seven thousand dollars more revenue is recognized for equipment sitting in a warehouse.

The bigger risk is the forecast. Later, five point four million is spent. If the cost to complete still says three point six million, the job looks sixty percent complete with a ten percent margin. An honest forecast of four point three million makes it about fifty-six percent, with a three percent margin.

Unaccrued costs, rework and miscoded invoices distort it too. The fix is a cross-check. Compare cost-to-cost with the field's physical percent complete and with billing, and ask why when they spread apart. Uninstalled materials can be tracked separately, and your accountant sets the policy for leaving them out.

In os.construction, the WIP app computes each job's snapshot from posted job costs, the approved cost-to-complete forecast and billings, so you can review the evidence before you post it.

FAQ

How do you calculate percent complete in construction?

Under the cost-to-cost method, divide cost incurred to date by estimated total cost, where estimated total cost is cost to date plus estimated cost to complete. Multiply the result by the current contract value to get earned revenue to date.

Is percent complete the same as percentage of completion?

Closely related. Percentage of completion is the name of the revenue recognition method; percent complete is the progress measure it uses. Cost-to-cost is the most common way to measure that progress, but not the only one.

Why doesn't percent complete match billed percent?

Billed percent comes from the pay application and the schedule of values, which can be front-loaded, lag the work or exclude unapproved changes. Cost-to-cost comes from the cost ledger and the forecast. The difference between the two, in dollars, is over or under billing.

Should uninstalled materials count toward percent complete?

Usually not at full value. Under ASC 606, costs that don't reflect progress, such as significant materials delivered but not yet installed, can be excluded from the measure of progress, with revenue recognized only to the extent of their cost. Many contractors exclude them from the calculation.

Do tax rules use the same percent complete?

For long-term contracts subject to the percentage-of-completion method under Internal Revenue Code Section 460, progress is measured with a cost-to-cost comparison, but which costs count follows the tax rules, so the tax figure can differ from the book figure.

Sources

Open file