Progress Fell. Where Did the Work Go?
Forty completed units stay complete as total scope grows from 100 to 120. Check the quantity, total, measurement basis and reporting date.
An animated teaching example with AI narration. The illustrations explain the process; they are not a recording of the app.
Video transcript
The progress meter drops. But watch the completed work: none of it disappears. What changed?
In this example, every unit counts equally. Forty completed units out of one hundred total means forty percent complete.
Now assume twenty additional units are approved for this measured scope. Forty out of one hundred twenty is about thirty-three point three percent.
The completed quantity stayed forty. The total grew. Check the completed count, total scope, measurement basis, and reporting date before comparing percentages.
Keep the old scope reference and explain the change. Explore progress measures at os dot construction.