Esc

↑↓ move↵ openIndex · Pagefind
Accounting

Earned revenue

Definition

The portion of contract value a contractor has earned to date, typically percent complete times total contract value.

Part of: Construction cost reporting: accruals, earned revenue, EAC and WIP

Topic: Accounting & WIP

Updated

Earned revenue: cost-to-cost percent complete times contract value, compared with billingsCost to date of $8.30 million divided by an estimate at completion of $11.80 million gives 70.34 percent complete. Multiplied by a $12.60 million contract, earned revenue to date is $8.86 million, and gross profit to date is $0.56 million. Billed to date is $9.15 million, so the job is over billed by about $287,000, a liability. Illustrative numbers.EARNED REVENUE, MONTH 9Cost to date$8.30M÷Est. at completion$11.80M= 70.34% complete% complete70.34%×Contract value$12.60MEarned revenue to date$8.86Mless cost $8.30M = profit to date $0.56MCOMPARE WITH BILLINGSBilledEarnedOver billed $287k: a liability
Earned revenue follows progress, not invoices. Billing ahead of it creates over billing on the WIP schedule. Illustrative numbers from this page.

Earned revenue is how much of a contract you have earned by doing the work, regardless of what you have billed or collected. Under the cost-to-cost method, earned revenue = (cost to date ÷ estimated total cost) × current contract value, which includes approved change orders.

Unapproved changes enter contract value only when they meet the accounting criteria for inclusion.

In plain English

Illustrative: you sign a $1,000,000 contract that you expect to cost $800,000. So far you have spent $300,000, so the job is 37.5% complete ($300,000 ÷ $800,000). You have earned $375,000 of revenue (37.5% × $1,000,000) and $75,000 of profit to date, whatever you have invoiced. If you have billed $450,000, you are $75,000 over billed: you have collected or invoiced ahead of the work.

Why it matters

Earned revenue is the revenue line on the income statement for contractors that recognize revenue over time, which under ASC 606 covers most construction contracts. Billing is a separate decision. The gap between earned revenue and billings becomes over billing (a liability) or under billing (an asset) on the WIP schedule.

If you report billed revenue instead of earned revenue, profit swings with your pay app strategy rather than with progress. A front-loaded schedule of values would make early months look rich and late months look broke. Banks and sureties know this, which is why they read earned revenue and the over/under column alongside the income statement.

How it works

  1. Start with the estimate at completion. The estimate at completion (EAC) is cost to date plus the PM’s cost to complete, from the cost report.
  2. Measure progress. With the cost-to-cost method, percent complete = cost to date ÷ EAC.
  3. Apply it to the contract. Earned revenue to date = percent complete × current contract value.
  4. Take the difference for the period. Revenue this month = earned revenue to date − earned revenue through last month.
  5. Compare with billings. Billed to date − earned revenue = over (+) or under (−) billing.

The formula in one line:

earned revenue = (cost to date ÷ estimated total cost) × current contract value

Because every input is cumulative, any change in the forecast or the contract is caught up in the current month. That is intended: it is a change in estimate, not the correction of an error.

Worked example

Illustrative job at month 9, from the construction cost reporting guide:

Line Amount
Contract, including $600,000 of approved change orders $12,600,000
Estimate at completion $11,800,000
Cost to date, including accruals $8,300,000
Percent complete ($8.3M ÷ $11.8M) 70.34%
Earned revenue to date (70.34% × $12.6M) $8,862,712
Earned revenue through month 8 $7,686,860
Revenue recognized in month 9 $1,175,852
Billed to date $9,150,000
Over billing ($9.15M − $8.86M) $287,288

Gross profit earned to date is earned revenue minus cost to date: $562,712. Revenue for the month will almost never equal that month’s pay application, and it should not.

What changes earned revenue

  • The forecast. Raising the EAC lowers percent complete on the same cost. This job’s EAC was $11.72M in month 8 and $11.80M in month 9, so each dollar of cost now earns a little less.
  • Change orders. Approved change orders raise contract value and usually the budget. Pending ones are generally left out of contract value until approved or until they meet your policy for variable consideration, while their cost can already be in cost to date. That is why unapproved work drags margin.
  • Costs that do not show progress. When progress is measured with an input method, ASC 606 says to leave out costs that do not depict performance, such as wasted materials or rework the owner will not pay for.
  • Uninstalled materials. Materials bought for the job but not yet installed can be recognized at cost with no margin until installed, so they do not inflate percent complete.
  • Loss contracts. If EAC exceeds contract value, the whole expected loss is generally recorded at once as a loss provision, separately from the earned revenue calculation.

Common mistakes

  • Using billed to date as revenue. It ties revenue to invoicing instead of progress.
  • Counting unapproved change orders in contract value before they are probable and estimable, or before they meet your policy for variable consideration.
  • Updating cost but not the forecast. Cost to date rises, EAC stays stale, percent complete jumps and earned revenue is overstated. This is a common source of surprise margin fade.
  • Leaving out accruals. Work in place that has not been invoiced understates cost to date and therefore earned revenue. See accrual.
  • Holding contract value constant while the budget moves, or the reverse, after a change order.
  • Assuming tax and book revenue match. Long-term contract rules for tax under IRC section 460 can differ from ASC 606 reporting; your CPA reconciles the two.

How os.construction handles it

The Accounting module’s WIP app computes earned revenue from supported contract, cost, forecast and revenue-method inputs: contract from executed prime contracts and approved change orders, cost to date from posted job cost, and estimated cost from the controller-approved PM forecast. Review exceptions and approve a revision before posting it; the WIP schedule and construction reports read the posted snapshot. See job cost and WIP and construction WIP software. To run the math on one job in your browser, use the free over/under billing calculator.

Watch the explainer · 3:05

Earned revenue explained: accrual, cost-to-cost, WIP

  1. 0:00Earned, billed, collected
  2. 0:16Accrual versus cash
  3. 0:41A month-end accrual
  4. 1:06Revenue over time under ASC 606
  5. 1:28One illustrative job
  6. 1:52This month's revenue versus billings
  7. 2:15Why earned revenue moves
  8. 2:42Earned revenue in os.construction
Read the transcript

Earned revenue is the part of a contract a contractor has actually earned by doing the work. It is not what you have billed, and it is not what you have collected. Those are three different numbers, and in construction they almost never match in any given month.

Start with the basis. Cash accounting records revenue when the money arrives and costs when you pay them. Accrual accounting records them when they are earned or incurred. So if a drywall sub finishes work in September but invoices in October, that's a September cost on the accrual basis. Sureties and lenders usually ask contractors for accrual-basis, GAAP financial statements.

Here's how that looks at month-end. On September thirtieth, accrue one hundred eighty thousand dollars of sub work in place: debit job cost, credit accrued liabilities. On October first, the entry reverses. When the real pay app arrives on October eighth, it posts through payables. September carries the cost once, and October nets to zero.

For revenue, most construction contracts are recognized over time under ASC 606, because the owner controls the work as it goes in. That means you need a measure of progress. The most common one is cost-to-cost: percent complete equals cost to date divided by the estimate at completion, which is the total cost you now expect for the job.

Here's an illustrative job at month nine. The contract, with approved change orders, is twelve point six million dollars. Cost to date is eight point three million, and the estimate at completion is eleven point eight million. That's seventy point three percent complete. And seventy point three percent of twelve point six million is about eight point eight six million of earned revenue to date.

Revenue for month nine is earned to date minus earned through month eight, seven point six nine million, so about one point one eight million. Meanwhile, the job has billed nine point one five million. Billings ahead of earned revenue is over billing, a liability of about two hundred eighty-seven thousand. Earned ahead of billings would be under billing, an asset.

Earned revenue is cumulative, so every change gets caught up in the current month. Raise the estimate at completion, and percent complete drops on the same cost, which can make a month's revenue small, or even negative. Unapproved change orders generally stay out of contract value until they meet the accounting criteria. And wasted materials, or materials not yet installed, shouldn't inflate progress.

In os.construction Accounting, the WIP app computes earned revenue from executed contracts and approved change orders, posted job cost and the approved forecast. You review exceptions, then post a snapshot. This is general information, not accounting or tax advice.

FAQ

What is earned revenue in construction?

Earned revenue is the part of a contract's value a contractor has earned by doing the work, measured by progress rather than by what has been billed or collected. Under the cost-to-cost method it is percent complete (cost to date divided by estimated total cost) times the current contract value, including approved change orders.

How do you calculate earned revenue?

Divide cost to date by the estimate at completion to get percent complete, then multiply by the current contract value. A job with $8.3M of cost, an $11.8M estimate at completion and a $12.6M contract is 70.3% complete and has earned about $8.86M. Revenue for the month is earned revenue to date minus earned revenue through the prior month.

What is the difference between earned revenue and billings?

Billings are what you have invoiced the owner, usually through pay applications against the schedule of values. Earned revenue is what you have earned by performing the work. When billings exceed earned revenue the job is over billed, a liability on the balance sheet; when earned revenue exceeds billings the job is under billed, an asset.

Is earned revenue the same as recognized revenue under ASC 606?

For a contractor that recognizes revenue over time under ASC 606 and measures progress with cost-to-cost, earned revenue to date is the cumulative revenue recognized on the contract. ASC 606 adjusts the input method for costs that do not depict progress, such as wasted materials, and for uninstalled materials, so earned revenue should follow those adjustments too.

Why did earned revenue go down this month?

Usually because the estimate at completion went up. Earned revenue uses estimated total cost as the denominator, so raising the forecast lowers percent complete on the same cost to date, and the catch-up adjustment can make a month's revenue small or even negative. A reduced contract value, such as a deductive change order, has the same effect.

What is the difference between earned and unearned revenue?

In general accounting, revenue is earned when the work or goods have been delivered, and unearned (deferred) revenue is cash received before that, recorded as a liability. Construction has the same idea at contract level: earned revenue follows percent complete, and billing ahead of it creates over billing, a contract liability. Billing behind it creates under billing, a contract asset.

Sources

Open file