Accounting

Loss provision

Definition

On a contract expected to lose money, the immediate recognition of the full anticipated loss, not just the share of it incurred so far.

Part of: Construction cost reporting: accruals, earned revenue, EAC and WIP

Topic: Accounting & WIP

Updated

How a loss provision is sizedA $1,000,000 contract has an estimate at completion of $1,050,000, so the total expected loss is $50,000. At 40% complete, $20,000 of that loss is already reported through revenue and cost to date. The remaining $30,000, the share for the 60% of work left, is booked now as a loss provision, so the full $50,000 loss is reported immediately.Contract price$1,000,000Estimate at completion$1,050,000Total expected loss: $50,000$20,000$30,00040% done:already reported60% left: provisionbooked nowLoss reported to date: −$50,000
Illustrative contract. The loss already in revenue and cost to date plus the provision equals the whole expected loss.

A loss provision is the accrual a contractor books when a contract is expected to lose money overall. When a contract’s estimated cost at completion exceeds its price, US GAAP requires the whole anticipated loss to be recognized as soon as it can be estimated (ASC 605-35, the loss-contract guidance that stayed in place alongside ASC 606). Percent-of-completion accounting alone would only recognize the loss as the job progresses, so a provision books the remaining portion now, as a cost and an accrued liability, which is drawn down as the work is done. Under IFRS, used in the UK and by many Canadian companies, the comparable idea is an onerous contract provision under IAS 37.

How it works

  1. The estimate turns negative. A cost-to-complete review produces an estimate at completion (EAC) above the contract price, including approved changes and any variable consideration that passes the constraint.
  2. Measure the total loss. Total loss = EAC minus contract price.
  3. Measure what’s already reported. Under the cost-to-cost method, revenue to date is the percent complete times the price. Revenue to date minus cost to date is the gross profit (or loss) already in the books.
  4. Book the difference. Provision = total loss minus loss already reported. This equals the total loss times the percent of work remaining. The entry debits a contract loss expense and credits an accrued loss liability.
  5. Draw it down. As the rest of the work is done, the further revenue and cost produce more loss, and a matching release of the provision offsets it.
  6. Remeasure each period. If the EAC moves, the provision is recalculated. It can grow, shrink, or reverse entirely if the job recovers.

Worked example

Illustrative: a contract priced at $1,000,000 has a revised EAC of $1,050,000. Cost to date is $420,000, so the job is 40% complete on a cost-to-cost basis.

Item Amount
Contract price $1,000,000
Estimate at completion $1,050,000
Total expected loss −$50,000
Revenue to date (40% × $1,000,000) $400,000
Cost to date $420,000
Loss already reported −$20,000
Provision needed ($50,000 × 60% remaining) −$30,000
Gross profit to date reported −$50,000

The entry is Dr Provision for Contract Losses $30,000 / Cr Accrued Loss on Contracts $30,000. Over the remaining 60% of the work, the job earns $600,000 of revenue against $630,000 of cost. That $30,000 further loss is offset by releasing the accrued $30,000, so the job reports no more loss if the estimate holds.

Term What it means Relation to a loss provision
Loss provision Accrual for the not-yet-incurred part of an expected contract loss The subject of this entry
Margin fade Any decline in a job’s expected profit Only needs a provision once margin goes below zero
Over-billing Billings ahead of earned revenue, a liability on the WIP schedule A separate balance; a loss job can be over- or under-billed
Contingency Budgeted reserve inside the estimate for risk Part of the EAC, not an accounting provision
Onerous contract (IFRS) A contract whose unavoidable costs exceed the benefits expected from it The IFRS counterpart, measured under IAS 37

Why it matters

Conservatism: a surety, bank or buyer needs to see the loss today, not spread across the remaining months. A loss job that shows a small gross loss each month for a year looks very different from one that shows the full loss at once, and the second picture is the honest one. Sureties read the WIP schedule to judge bonding capacity, and a late-recognized loss that surfaces at year end damages trust in every other number on it. A late-recognized loss is also one of the most common restatement triggers.

The provision also forces a conversation. If nobody wants to book it, the real debate is usually about the EAC, and that debate belongs in a documented cost-to-complete review, not in the close.

Common mistakes

  • Recognizing only the “to date” share of the loss.
  • Holding an optimistic EAC to avoid the provision.
  • Counting unapproved change orders or claims in the price at full value to make the loss disappear.
  • Forgetting to remeasure the provision when the EAC improves or worsens, so last quarter’s number lingers.
  • Releasing the whole provision at once instead of in step with the remaining work.
  • Leaving loss jobs off the WIP schedule review because they are “nearly done”.

For where the provision fits in the month-end routine, with a three-job example, see how to prepare a WIP schedule. For checking the estimate behind it, see how to run a cost-to-complete review.

How os.construction handles it

WIP computes loss provisions from reviewed estimates and keeps their calculation trace. An independently approved snapshot posts the provision to its mapped account, and close checks tie that account to the posted revision. See the accounting guide.

FAQ

What is a loss provision on a construction contract?

It is an accrual that recognizes the whole expected loss on a contract as soon as the loss can be estimated. Percent-of-completion accounting by itself would only show the loss gradually as work is done, so the provision books the part of the loss that relates to the remaining work immediately.

How do you calculate a loss provision?

Work out the total expected loss (estimated cost at completion minus the contract price). Subtract the loss already reported through revenue and cost to date. What is left, which works out to the total loss times the percent of work remaining, is the provision.

When should a contractor record a loss provision?

In the period the loss first becomes estimable, usually when a cost-to-complete review shows the estimate at completion is above the contract price. Waiting for the loss to show up in the job cost reports month by month is what the provision is meant to prevent.

Is a loss provision the same as margin fade?

No. Margin fade is any drop in the expected profit on a job. A loss provision is only needed once the fade pushes the job below zero, so the estimated cost at completion exceeds the price. A job that fades from 10% to 2% margin has fade but no provision.

What happens to the loss provision as the job continues?

It is drawn down as the remaining work is done. Each period's further revenue and cost will show a loss, and releasing part of the provision offsets it, so the job reports roughly zero gross profit from then on if the estimate holds. If the estimate changes, the provision is remeasured.