Esc

↑↓ move↵ openIndex · Pagefind
Contracts

Lump Sum Contract

Definition

A contract where the contractor agrees to deliver a defined scope for one fixed price, keeping savings and absorbing overruns.

Part of: Project delivery methods: design-build, CMAR, GMP and more

Topic: Project delivery & contracts

Updated

In a lump sum (stipulated sum) contract, the contractor commits to a single price for a defined scope. The owner doesn’t see your costs. If you buy out cheaper, you keep the difference. If you blow the estimate, you eat it. The price only changes through change orders for scope changes, unforeseen conditions or other contract-defined events. Billing usually follows a schedule of values approved at the start.

How it works

Lump sum work usually follows a design-bid-build path:

  1. The owner issues complete documents. Drawings and specifications define the scope. The more complete they are, the less the price relies on guesses.
  2. Contractors bid. Each prices the work from its own takeoff and sub quotes. On public work the award often goes to the lowest responsive, responsible bidder.
  3. The contract fixes the price. Standard forms include AIA A101 (stipulated sum), CCDC 2 in Canada (stipulated price) and ConsensusDocs’ lump sum agreement. US federal agencies use firm-fixed-price contracts under FAR 16.202.
  4. The contractor buys out. Subcontracts and purchase orders lock in most of the cost. Buyout savings stay with the contractor.
  5. Billing runs on a schedule of values. Each pay application bills percent complete by line, less retainage.
  6. Changes go through change orders. Added scope, owner-caused delay and differing site conditions get priced and added. Everything else is the contractor’s risk.

Items not designed at bid time are often carried as allowances, which are reconciled against actual cost later.

Worked example

Illustrative: a $10.0M lump sum job is estimated at $9.1M cost, a $900,000 (9%) margin. Unbilled extra work of $86,400, like the fire dampers behind RFI-212, would cut margin to $813,600 (about 8.1%) if it isn’t captured as a change order. That’s why the RFI-to-CO path matters most on hard-bid work.

Now add buyout. The drywall subcontract was estimated at $640,000 and bought for $605,000, a $35,000 saving that stays with the contractor. A late steel price increase adds $22,000 that the contract doesn’t let the contractor pass on. Net, margin moves to $900,000 + $35,000 − $22,000 = $913,000 before the unpriced dampers. Under a cost-plus contract, both of those swings would have gone to the owner.

Lump sum vs other contract types

Type Price basis Who carries cost risk Owner sees costs?
Lump sum One fixed price Contractor No
GMP Cost plus fee, capped Contractor above the cap Yes
Cost-plus Actual cost plus fee Owner Yes
Unit price Fixed rate × measured quantity Owner for quantity, contractor for rate Partly

When lump sum fits

Lump sum works best when the design is complete, the scope is well defined and site risk is understood. Repeat building types, fit-outs with good existing-condition surveys and public projects that must be competitively bid are typical. It fits poorly when the design is still moving, when hidden conditions are likely, as in renovation of old buildings, or when the owner wants the contractor involved early to help shape the design. In those cases contractors either price large contingencies into the number or carry risks they can’t control, and owners often turn to GMP or cost-plus instead. Contractors can protect themselves on lump sum bids with clear qualifications and exclusions, and by pricing allowances and unit prices exactly as the bid documents define them.

Why it matters

Lump sum puts the most cost risk on the contractor. Margin depends on estimate quality, buyout discipline, and catching change-worthy events fast. Every hidden condition that you don’t turn into a change order comes straight out of profit. Because the owner pays the same price whatever the work costs, any cost growth shows up as margin fade rather than as extra revenue.

Common mistakes

  • Front-loading the SOV so aggressively that the owner rejects it or you end up underbilled late.
  • Treating RFI answers as “free” clarifications when they change scope.
  • Missing notice deadlines that forfeit change order rights.
  • Bidding incomplete documents as if they were complete, with no qualifications or exclusions.
  • Letting unpriced potential change orders pile up while the cost is already in the job.

For pricing changes on fixed-price work, see how to price a change order.

How os.construction handles it

RFIs, change events and change orders sit on one record: a change event names its origin RFI and is priced as a potential change order, so scope changes on fixed-price work are less likely to slip through unpriced. See Change events and change orders.

FAQ

What is a lump sum contract in construction?

It is a contract where the contractor agrees to complete a defined scope of work for a single fixed price. The contractor keeps any savings and absorbs any overruns. The price changes only through change orders for events the contract allows, such as owner-directed changes or differing site conditions.

Is a lump sum contract the same as a fixed-price contract?

In practice, yes. The AIA calls it a stipulated sum, Canadian CCDC documents call it a stipulated price, and US federal contracts use firm-fixed-price. The details of risk sharing and change pricing depend on the contract's terms rather than the label.

What are the advantages and disadvantages of a lump sum contract?

For the owner, the price is known at award and administration is simpler. For the contractor, efficient work and good buyout increase margin. The downsides are that the contractor carries cost risk, bids need complete design documents, and disputes concentrate on what is and isn't in the scope.

How is a lump sum contract billed?

Usually by monthly progress billing against a schedule of values. The contractor splits the price into line items, the owner approves the breakdown, and each pay application bills the percentage complete on each line, less retainage. The owner normally doesn't see the contractor's actual costs.

What is the difference between a lump sum and a GMP contract?

A lump sum is one fixed price and the owner doesn't see costs. A GMP contract is cost-plus-fee up to a guaranteed maximum: the owner pays actual cost plus fee, sees the books, and savings below the maximum are often shared. Overruns above the GMP fall on the contractor in both cases, unless the contract allows a change.

Sources

Open file