Markup vs margin calculator
Markup is profit as a share of cost. Margin is profit as a share of price. Same dollars, different denominators, and mixing them up quietly costs you points on every job.
Sample inputs (illustrative): $100,000 of cost at a 20% target margin.
How this is calculated
Both numbers describe the same profit dollars. They divide by different things.
Profit = price − cost Margin = profit ÷ price Markup = profit ÷ cost Price from a target margin = cost ÷ (1 − margin) Price from a markup = cost × (1 + markup) Margin from markup = markup ÷ (1 + markup) Markup from margin = margin ÷ (1 − margin)
Why 20% markup is not 20% margin
On $100 of cost, a 20% markup gives a $120 price and $20 of profit. $20 is 16.7% of $120. To keep 20% of the price you need a $125 price, which is a 25% markup. The gap grows as the rate grows: a 50% markup is a 33.3% margin.
Which one to use where
- Estimating and bidding: set your target as a margin, because your income statement, WIP schedule and bonding agent all read gross profit as a share of revenue.
- Change orders and T&M: contracts almost always state allowed overhead and profit as a markup on cost. Apply it as a markup.
- Overhead recovery: if company overhead runs 10% of revenue, a 10% markup does not cover it. You need 11.1%.
Margin here is gross margin on the cost you enter. If that cost leaves out job overhead or burden, the real margin is lower.
Stop re-keying the numbers behind this math.
Project Financials tracks job costs and billing. Company Accounting is available for evaluation; certified WIP posting and close are not yet available.
Email gets you product updates: what shipped and what's next. Start a free trial → Founding program →
You're subscribed.
We'll email you when something ships. The live tools are open now: start a 14-day free trial →
Want a say in what ships? Finish your founding application (2 min) →