Esc

↑↓ move↵ openIndex · Pagefind

Change order markup calculator and log

Price a change order the way owners review it: burdened direct cost by type, overhead and profit on self-performed work, a lower tiered markup on subs, then insurance, fee and bond. Export the summary, and keep pending exposure in a log.

  • Free
  • No signup
  • Runs in your browser
  • Shareable link

Inputs

Direct cost
Labor, entered as
$
$
%
$
$

Sub amount is the sub's own quote, its markup included.

Markups
%
%
GC markup on subcontract (tiered)
%
on the first
$
%
above that
No tiers in your contract? Set both rates the same.
%
%
%

Fee is for cost-plus and GMP contracts that add a fee on cost; leave it at 0 on lump-sum work.

ResultsLive

Change order total
$0
Direct cost
$0
Total markup
$0
Waterfall from direct cost to change order total
Direct costMarkupCO total
Markup is not margin
Pricing summary

CO log

Change order log: what's approved, what's exposure

Track every change from submitted to decided. Pending dollars are cost you may already be carrying without a signature. Saved in this browser only.

Approved
$0
Pending exposure
$0
Rejected
$0
Oldest pending
0 days
CO #DescriptionAmountStatusSubmittedAgeDelete

No change orders yet. Price one above and press Add to CO log, add one here, or load the sample.

When the spreadsheet stops scaling

Approve it once. It updates the budget, the subcontract and the pay app.

  • An RFI can open a change event, so the exposure shows on the forecast before anything is signed.
  • Potential change orders carry cost, markup and sub quotes, in one, two or three tiers per project.
  • Executed change orders update the contract sum and budget; the sub's side updates the commitment.
  • Approved changes reach owner billing on the next pay app without being retyped.

See change order software Start a free trial

Change order pricing questions

What is a typical overhead and profit markup on a change order?

Whatever the contract allows. Many contracts state overhead and profit as a percentage of cost for self-performed work, with a lower percentage for the general contractor on subcontracted work, and the sub's own markup inside its quote. Check the changes clause and any markup schedule before pricing; reviewers will apply it line by line.

Why do subcontracted changes get a lower markup?

A sub's quote already includes the sub's overhead and profit. A full GC markup on top double-charges the owner, so contracts often set a lower rate on sub work, sometimes tiered so large sub changes carry a smaller percentage. The tier here applies the first rate up to the limit and the second above it.

Should insurance and bond be applied before or after markup?

Usually after, because premiums are charged on the final contract value. This calculator applies insurance on the subtotal, an optional fee on subtotal plus insurance, and bond on everything before it. Some contracts fold insurance into overhead or pass bond through at actual cost. Match yours.

Is a 15% markup a 15% margin?

No. Markup divides profit by cost; margin divides it by price. A 15% markup is a 13.0% margin. On CO #14 the 10.6% total markup on cost is a 9.6% margin. The markup vs margin calculator converts both ways.

How should labor be priced on a change order?

At fully burdened cost: hours × base wage × (1 + burden), where burden covers payroll taxes, workers' comp, insurance and benefits or fringes. Enter hours, wage and burden here, or a burdened lump sum. The labor burden calculator works out the burden percentage.

What should a change order log track?

Every change from first notice to decision: number, description, amount, status (pending, approved, rejected, void) and the date it was submitted. Pending dollars are your exposure: cost you may already be carrying without a signed change. Age matters too: changes pending more than 30 days are the ones to chase.

What happens to the change order after approval?

It changes the contract sum, gets its own line on the schedule of values, and is billed on the next pay application. Only approved change orders belong on the bill. Try it in the free pay application builder.

Sample inputs (sample data): CO #14, fire dampers found behind a hidden condition (RFI-212) on Riverside Medical Center: $78,100 of cost (Summit Mechanical $68,000, GC supervision $6,500, firestopping $3,600) plus $8,300 of markup lands at $86,400.

Prefer a spreadsheet? Get the free change order log template for Excel

See it in the app

Method

How this is calculated

Most contracts spell out allowable markups. This tool applies them in the order owners usually expect to see them on a change order proposal.

Labor             = hours × base wage × (1 + burden %)   (or a burdened lump sum)
Self-performed    = labor + material + sales tax + equipment
Overhead          = self-performed × overhead %
Profit            = self-performed × profit %             (or × (self-performed + overhead) if compounded)
Sub markup        = min(sub, tier limit) × tier 1 % + max(0, sub − tier limit) × tier 2 %
Subtotal          = self-performed + overhead + profit + sub + sub markup
Insurance         = subtotal × insurance %
Fee               = (subtotal + insurance) × fee %
Bond              = (subtotal + insurance + fee) × bond %
CO total          = subtotal + insurance + fee + bond
Markup on cost    = (CO total − direct cost) ÷ direct cost
Margin on price   = (CO total − direct cost) ÷ CO total

Overhead and profit: separate or compounded?

Some contracts allow "10% overhead and 5% profit" as two markups on cost (15% total). Others allow profit on cost plus overhead, which compounds: 1.10 × 1.05 = 15.5%. The difference is small per change and real across a year of them. Use the checkbox to match the contract's wording.

Insurance and bond

Bond premiums are typically charged on the total contract value, so bond is applied last. Some contracts fold insurance into overhead or treat bond as a pass-through at actual cost. Match your contract.

Before you send it

  • Back up labor with hours × burdened rate by craft, and attach quotes for material and subs.
  • Price time impact (extended general conditions) separately if the change moves the schedule.
  • Reference the RFI or directive that triggered the change.

Further reading: the pricing mistake hiding in your change orders, change events vs change orders and the real cost of re-keying a change order. To see each layer stack up on a worked example, read how a change order is priced.

Stop re-keying the numbers behind this math.

Project Financials tracks job costs and billing. The Accounting module includes reviewed WIP snapshots, posting and close. Learn the apps and review historical source coverage before a cutover.

Your role (optional)

Email gets you product updates: what shipped and what's next. Start a free trial → Founding program →

More free tools

Pay app builderG702/G703-style pay app: SOV, stored materials, retainage reductions, change orders, error checks, roll-forward, print and Excel export.RetainageRetainage this period, a ledger over the life of the job with reductions and release, carrying cost, and state retainage rules.Over/under billingSingle-job over/under billing: cost-to-cost, units or physical %, pending COs, uninstalled materials and loss provision.Estimate at completionFive EAC methods side by side (CPI, CPI×SPI, budget-rate, weighted, PM ETC) with TCPI, sensitivity and a monthly trend.Markup vs marginConvert markup to margin and back, price from a target margin, and see why 20% markup is not 20% margin.Labor burdenFully burdened hourly cost: payroll taxes with wage caps, workers' comp, GL, benefits, fringe and PTO.Bonding capacityUnderwriter-style adjusted working capital and net worth, single-job and aggregate ranges, backlog utilization and what-if levers.Bond premiumPerformance, payment and bid bond cost from your own surety’s tiered rate per $1,000: gross the premium into a bid and price change orders.Cash flow curveJob and portfolio cash curves: billing lag, retainage, pay-when-paid, peak financing need, interest cost and scenario compare.Punch list closeoutImport your punch log: open items by trade and age, a burn-down forecast with a confidence band, close rates each milestone needs, closeout checklist and Excel export.RFI response timeImport your RFI log: median and P90 turnaround in calendar or business days, on-time rate by party, ball-in-court aging, late RFIs with impact and an OAC report.Critical pathEnter activities with FS, SS, FF and SF logic and lags: forward and backward pass, total and free float, the critical path, a Gantt and a network diagram, with the math shown.Earned valuePV, EV and AC from budget and percent complete: CV, SV, CPI, SPI, three EAC formulas side by side, ETC, VAC and TCPI, with the math shown.General conditionsStaff, trailer, temp utilities and dumpsters by week, month or lump sum: total, weekly burn, share of contract and cost per extra week of delay.Delivery methodEleven questions, transparent scoring: design-bid-build, CM at risk, design-build or IPD, with the points behind every answer, a comparison table and a decision memo to download.Bid bondPenal sum from a percentage, a fixed amount or the federal 20% rule, what you owe if you win and walk, and a withdrawal-risk check by stage, mistake type and state.NTP generatorFull or limited NTP letter: commencement, contract time in calendar or working days (federal holidays skipped), completion dates, early-work caps and an acknowledgment. Word, text or print.Back chargeBurdened labor, material, equipment and other trades, markup only where the subcontract allows it, the notice and cure timeline, and how much comes off the next payment.ContingencyOwner and contractor contingency against percent complete: burn index, straight-line chart, projection to completion, pending exposure and an Excel tracker with live formulas.Closeout packagePick the building’s systems and contract terms and get its closeout package: TCO and CO readiness, Cx, as-builts, O&M, warranties and final payment, with due dates and an Excel checklist.WIP schedule workbenchMulti-job WIP schedule: over/under billing, fade vs prior, loss provisions, pending COs and surety ratios. Printable report and Excel with formulas.Bring your own jobFive numbers from one of your jobs, or your whole pasted WIP schedule, rendered on the os.construction dashboard: over/under billing, margin, fade risk. Runs in your browser.Migration plannerPhased plan to move onto one system: cutover off year-end and peak season, risks and exports.Stack assessment10 questions, 3 minutes. Score your systems across five dimensions and get concrete next steps.

Ask the OS

Reading this page

Ask anything about this page. Answers use what you're reading as context.

Suggested

    AI · may be imperfect · sample data where shown

    Open file