Closeout package checklist generator

Tell it what the building has and what the contract requires, and get the closeout package for this project: TCO and CO readiness, commissioning, as-built and record documents, O&M manuals and warranties, attic stock and training, and financial closeout, each with an owner and a due date from substantial completion.

  • Free
  • No signup
  • Runs in your browser
  • Shareable link
Systems
Contract and owner

Your packageLive

TCO and CO readiness
0%
Items in this package
0
Overall done
0%

    Closeout checklistLive

    Tick items as they close; ticks are kept in this browser only. Due dates are substantial completion plus or minus the days shown.

    Sample: a project with fire alarm, sprinklers, elevators, controls and a roof warranty, commissioning, a phased TCO, bonds and retainage, reaching substantial completion on March 15, 2027.

    Method

    How this is calculated

    Every item has a section, a typical responsible party, an offset in days from substantial completion and, where it only applies to some projects, the conditions that switch it on. The generator keeps the items your answers switch on and sorts them by section and date.

    Included        = items with no condition + items whose condition you ticked
    Due date        = substantial completion + offset (negative = before)
    TCO readiness   = done ÷ items in "TCO and CO readiness"
    Excel           = same items, a Status drop-down (Open, In progress, Done, N/A),
                      due dates as formulas on the SC date, overdue items in red

    Offsets are starting points

    The offsets reflect a typical sequence: the pre-final meeting with the building department about 75 days out, life safety acceptance tests three weeks out, finals a week out, turnover documents within 30 days after, and retainage release and final waivers 45 to 60 days after substantial completion. Your contract’s closeout requirements, the building department and the commissioning plan set the real dates. Read our closeout to occupancy guide, the difference between a TCO and a certificate of occupancy, and what belongs in as-built drawings.

    How to build a closeout package checklist

    1. Set substantial completion. Enter the target date. Every item gets a due date relative to it, from the pre-final meeting about 75 days before to the warranty walk near the end of the first year.
    2. Tick what the project has. Systems such as fire alarm, sprinklers, elevators, generators and controls, and contract conditions such as commissioning, phased occupancy, bonds, a lender or retainage.
    3. Read the package. The checklist rebuilds instantly with only the items that apply, grouped from TCO and CO readiness to financial closeout, each with a responsible party.
    4. Track readiness. Tick items off as they close. The TCO and CO readiness score counts the readiness section.
    5. Export. Download the Excel checklist with a status drop-down, due dates that move with substantial completion and live counts, or the CSV, or print it.

    Closeout questions

    What is in a construction closeout package?

    Typically: final inspections and the certificate of occupancy, commissioning and test reports, as-built drawings and record documents, O&M manuals, warranties, attic stock and keys, owner training records, and the financial closeout: final change orders, lien waivers, consent of surety and the final pay app with retainage release. What applies depends on the building’s systems and the contract.

    What do you need for a temporary certificate of occupancy (TCO)?

    It depends on the building department, but usually life safety complete in the areas to be occupied: fire alarm and sprinklers accepted, exits, exit signs and emergency lighting working, fire department access, the required inspections passed for those areas, and separation from ongoing work. Ask the building department for its list at a pre-final meeting.

    When are as-built drawings due?

    At closeout, as part of the turnover documents, but they are only accurate if markups are collected from every trade throughout the job. The checklist puts monthly markup collection about two months before substantial completion as a reminder that it starts long before.

    When does the warranty period start?

    Usually at substantial completion for the work it covers, unless the contract says otherwise. Many contracts, including AIA A201, also include a one-year correction period; the checklist schedules a warranty walk before it ends.

    Who prepares the closeout package?

    The general contractor assembles it, usually the project engineer and project manager, with documents from every subcontractor and supplier, the commissioning authority and the architect. The owner and the architect review and accept it.

    Sources

    Checked Nov 21, 2026. Inspection, TCO and CO requirements are set by the local building department and fire marshal; closeout documents by your contract and specifications (Division 01).

    1. Temporary certificate of occupancy, NYC Department of Buildings (checked Nov 18, 2026).Used for: TCOs expire and are renewed while final CO items are open (one city’s practice).
    2. International Building Code 2021, Chapter 1 (Section 111, certificate of occupancy), International Code Council (checked Nov 18, 2026).Used for: the building official issues the certificate of occupancy and may issue a temporary one for a set period.
    3. Closeout to occupancy: punch, Cx, TCO and CO, os.construction (Nov 2026).Used for: the order of closeout steps and who does each.

    When the spreadsheet version stops scaling

    Closeout goes faster when the documents were collected all along.

    In os.construction the Punch List tool takes each item to Closed with a manager and a final approver, Inspections record pass or fail with signatures, Permits tracks inspections and approvals, and Documents holds as-builts, O&M manuals and warranties in versioned folders. In Accounting, a final retainage release is refused until the contract’s required closeout documents are on file. A turnover package export is planned, not live.

    • Punch list, inspections and permits on the project record (live).
    • Versioned Documents for as-builts, O&M and warranties (live).
    • Retainage release gated on required closeout documents (live).

    Stop re-keying the numbers behind this math.

    Project Financials tracks job costs and billing. The Accounting module includes reviewed WIP snapshots, posting and close. Learn the apps and review historical source coverage before a cutover.

    Your role (optional)

    Email gets you product updates: what shipped and what's next. Start a free trial → Founding program →

    More free tools

    Pay app builderG702/G703-style pay app: SOV, stored materials, retainage reductions, change orders, error checks, roll-forward, print and Excel export.RetainageRetainage this period, a ledger over the life of the job with reductions and release, carrying cost, and state retainage rules.Over/under billingSingle-job over/under billing: cost-to-cost, units or physical %, pending COs, uninstalled materials and loss provision.Change order markupPrice a CO with burdened labor, tax, OH&P, tiered sub markup, insurance and bond, then track it in a CO log with exposure and aging.Estimate at completionFive EAC methods side by side (CPI, CPI×SPI, budget-rate, weighted, PM ETC) with TCPI, sensitivity and a monthly trend.Markup vs marginConvert markup to margin and back, price from a target margin, and see why 20% markup is not 20% margin.Labor burdenFully burdened hourly cost: payroll taxes with wage caps, workers' comp, GL, benefits, fringe and PTO.Bonding capacityUnderwriter-style adjusted working capital and net worth, single-job and aggregate ranges, backlog utilization and what-if levers.Bond premiumPerformance, payment and bid bond cost from your own surety’s tiered rate per $1,000: gross the premium into a bid and price change orders.Cash flow curveJob and portfolio cash curves: billing lag, retainage, pay-when-paid, peak financing need, interest cost and scenario compare.Punch list closeoutImport your punch log: open items by trade and age, a burn-down forecast with a confidence band, close rates each milestone needs, closeout checklist and Excel export.RFI response timeImport your RFI log: median and P90 turnaround in calendar or business days, on-time rate by party, ball-in-court aging, late RFIs with impact and an OAC report.Critical pathEnter activities with FS, SS, FF and SF logic and lags: forward and backward pass, total and free float, the critical path, a Gantt and a network diagram, with the math shown.Earned valuePV, EV and AC from budget and percent complete: CV, SV, CPI, SPI, three EAC formulas side by side, ETC, VAC and TCPI, with the math shown.General conditionsStaff, trailer, temp utilities and dumpsters by week, month or lump sum: total, weekly burn, share of contract and cost per extra week of delay.Delivery methodEleven questions, transparent scoring: design-bid-build, CM at risk, design-build or IPD, with the points behind every answer, a comparison table and a decision memo to download.Bid bondPenal sum from a percentage, a fixed amount or the federal 20% rule, what you owe if you win and walk, and a withdrawal-risk check by stage, mistake type and state.NTP generatorFull or limited NTP letter: commencement, contract time in calendar or working days (federal holidays skipped), completion dates, early-work caps and an acknowledgment. Word, text or print.Back chargeBurdened labor, material, equipment and other trades, markup only where the subcontract allows it, the notice and cure timeline, and how much comes off the next payment.ContingencyOwner and contractor contingency against percent complete: burn index, straight-line chart, projection to completion, pending exposure and an Excel tracker with live formulas.WIP schedule workbenchMulti-job WIP schedule: over/under billing, fade vs prior, loss provisions, pending COs and surety ratios. Printable report and Excel with formulas.Bring your own jobFive numbers from one of your jobs, or your whole pasted WIP schedule, rendered on the os.construction dashboard: over/under billing, margin, fade risk. Runs in your browser.Migration plannerPhased plan to move onto one system: cutover off year-end and peak season, risks and exports.Stack assessment10 questions, 3 minutes. Score your systems across five dimensions and get concrete next steps.