Closeout package checklist generator
Tell it what the building has and what the contract requires, and get the closeout package for this project: TCO and CO readiness, commissioning, as-built and record documents, O&M manuals and warranties, attic stock and training, and financial closeout, each with an owner and a due date from substantial completion.
Sample: a project with fire alarm, sprinklers, elevators, controls and a roof warranty, commissioning, a phased TCO, bonds and retainage, reaching substantial completion on March 15, 2027.
How this is calculated
Every item has a section, a typical responsible party, an offset in days from substantial completion and, where it only applies to some projects, the conditions that switch it on. The generator keeps the items your answers switch on and sorts them by section and date.
Included = items with no condition + items whose condition you ticked
Due date = substantial completion + offset (negative = before)
TCO readiness = done ÷ items in "TCO and CO readiness"
Excel = same items, a Status drop-down (Open, In progress, Done, N/A),
due dates as formulas on the SC date, overdue items in redOffsets are starting points
The offsets reflect a typical sequence: the pre-final meeting with the building department about 75 days out, life safety acceptance tests three weeks out, finals a week out, turnover documents within 30 days after, and retainage release and final waivers 45 to 60 days after substantial completion. Your contract’s closeout requirements, the building department and the commissioning plan set the real dates. Read our closeout to occupancy guide, the difference between a TCO and a certificate of occupancy, and what belongs in as-built drawings.
How to build a closeout package checklist
- Set substantial completion. Enter the target date. Every item gets a due date relative to it, from the pre-final meeting about 75 days before to the warranty walk near the end of the first year.
- Tick what the project has. Systems such as fire alarm, sprinklers, elevators, generators and controls, and contract conditions such as commissioning, phased occupancy, bonds, a lender or retainage.
- Read the package. The checklist rebuilds instantly with only the items that apply, grouped from TCO and CO readiness to financial closeout, each with a responsible party.
- Track readiness. Tick items off as they close. The TCO and CO readiness score counts the readiness section.
- Export. Download the Excel checklist with a status drop-down, due dates that move with substantial completion and live counts, or the CSV, or print it.
Closeout questions
What is in a construction closeout package?
Typically: final inspections and the certificate of occupancy, commissioning and test reports, as-built drawings and record documents, O&M manuals, warranties, attic stock and keys, owner training records, and the financial closeout: final change orders, lien waivers, consent of surety and the final pay app with retainage release. What applies depends on the building’s systems and the contract.
What do you need for a temporary certificate of occupancy (TCO)?
It depends on the building department, but usually life safety complete in the areas to be occupied: fire alarm and sprinklers accepted, exits, exit signs and emergency lighting working, fire department access, the required inspections passed for those areas, and separation from ongoing work. Ask the building department for its list at a pre-final meeting.
When are as-built drawings due?
At closeout, as part of the turnover documents, but they are only accurate if markups are collected from every trade throughout the job. The checklist puts monthly markup collection about two months before substantial completion as a reminder that it starts long before.
When does the warranty period start?
Usually at substantial completion for the work it covers, unless the contract says otherwise. Many contracts, including AIA A201, also include a one-year correction period; the checklist schedules a warranty walk before it ends.
Who prepares the closeout package?
The general contractor assembles it, usually the project engineer and project manager, with documents from every subcontractor and supplier, the commissioning authority and the architect. The owner and the architect review and accept it.
Sources
Checked Nov 21, 2026. Inspection, TCO and CO requirements are set by the local building department and fire marshal; closeout documents by your contract and specifications (Division 01).
- Temporary certificate of occupancy, NYC Department of Buildings (checked Nov 18, 2026).Used for: TCOs expire and are renewed while final CO items are open (one city’s practice).
- International Building Code 2021, Chapter 1 (Section 111, certificate of occupancy), International Code Council (checked Nov 18, 2026).Used for: the building official issues the certificate of occupancy and may issue a temporary one for a set period.
- Closeout to occupancy: punch, Cx, TCO and CO, os.construction (Nov 2026).Used for: the order of closeout steps and who does each.
When the spreadsheet version stops scaling
Closeout goes faster when the documents were collected all along.
In os.construction the Punch List tool takes each item to Closed with a manager and a final approver, Inspections record pass or fail with signatures, Permits tracks inspections and approvals, and Documents holds as-builts, O&M manuals and warranties in versioned folders. In Accounting, a final retainage release is refused until the contract’s required closeout documents are on file. A turnover package export is planned, not live.
- Punch list, inspections and permits on the project record (live).
- Versioned Documents for as-builts, O&M and warranties (live).
- Retainage release gated on required closeout documents (live).
Stop re-keying the numbers behind this math.
Project Financials tracks job costs and billing. The Accounting module includes reviewed WIP snapshots, posting and close. Learn the apps and review historical source coverage before a cutover.
Email gets you product updates: what shipped and what's next. Start a free trial → Founding program →
You're subscribed.
We'll email you when something ships. The live tools are open now: start a 14-day free trial →
Want a say in what ships? Finish your founding application (2 min) →