Contingency drawdown tracker

Track the owner’s and the contractor’s contingency month by month against percent complete. See what is left, how fast it is burning against the work, where the current rate lands at completion and what pending items would take, then download it as Excel with the formulas live.

  • Free
  • No signup
  • Runs in your browser
  • Shareable link
$
At the start
$
In the price or GMP
$
$

Pending: draws you expect but that are not approved yet (open change events, buyout gaps, claims).

Where contingency standsLive

Owner

$0

Burn index
—
At current rate
—
Free after pending
—

Contractor

$0

Burn index
—
At current rate
—
Free after pending
—

Bars show the share used; the tick marks the share of work complete.

    Drawdown vs straight lineLive

    Owner and contractor contingency remaining by period, with straight-line references
    Owner remainingOwner straight lineContractor remainingContractor straight line

    Periods

    Cumulative % complete at the end of each period and the amount drawn from each contingency during it. Paste rows as period, % complete, owner drawn, contractor drawn.

    Period% completeOwner drawn $Contractor drawn $Owner leftContractor leftRemove

    Example inputs: a job at 48% complete with a $600,000 owner contingency and a $300,000 contractor contingency, six months of draws and $125,000 of pending exposure.

    See it in the app

    Method

    How this is calculated

    Each contingency is tracked on its own, against the same percent complete. The straight line is a reference for comparison, not a target: contingency risk is usually front-loaded.

    Remaining             = starting contingency − Σ drawn to date
    Straight line         = starting contingency × (1 − % complete)
    Burn index            = (drawn ÷ starting) ÷ % complete          1.0 = in step with the work
    Used at current rate  = drawn ÷ % complete                       linear projection to 100%
    Left at current rate  = starting − used at current rate
    Free after pending    = remaining − pending exposure

    Worked example

    At 48% complete the owner has drawn $210,000 of $600,000 (35%), a burn index of 0.73, and the contractor $127,000 of $300,000 (42%), an index of 0.88. At those rates the owner would use $437,500 and the contractor about $264,600 by completion, leaving $162,500 and $35,400. After pending items, $305,000 of the owner’s and $133,000 of the contractor’s contingency is free to spend.

    Owner and contractor contingency are different money

    Owner contingency covers the owner’s decisions and unknowns; contractor contingency covers the contractor’s own risk inside a GMP or price. Mixing them hides who is spending what. Buyout results feed straight into this: savings often move into contingency and overruns come out of it, so keep the buyout log alongside. For the whole-job forecast, the estimate at completion calculator shows the EAC trend month by month.

    How to track contingency drawdown

    1. Enter both contingencies. The owner’s contingency and the contractor’s contingency as they stood at the start (or at GMP), kept separate because they belong to different parties under different rules.
    2. Log each period. For every month: cumulative percent complete and how much each contingency was drawn that month. Paste rows from a spreadsheet if you have them.
    3. Add pending exposure. Known draws that are coming but not approved yet: open change events, pending buyout overruns, unresolved claims.
    4. Read the burn index and chart. A burn index over 1 means contingency is going faster than the work. The chart compares what is left with a straight-line drawdown.
    5. Export. Download the Excel tracker with live formulas and a chart, or the CSV, for the monthly cost review or the owner report.

    Contingency questions

    What is the difference between owner and contractor contingency?

    Owner contingency is money the owner holds for changes it decides on, such as scope additions, unforeseen conditions or design changes, and it usually sits outside the construction contract. Contractor contingency sits inside the contractor’s price or GMP for the contractor’s own risks, such as buyout gaps, estimating errors and coordination issues. The contract says who can use each, for what, and who keeps what is left.

    How fast should contingency be used?

    Most risk is front-loaded: unknown conditions show up in sitework and demolition, and buyout surprises appear early. A straight line against percent complete is a simple reference, not a rule. A burn index well above 1 early in the job is normal for some work types; well above 1 past mid-job deserves a hard look at the remaining risk.

    What is a contingency burn index?

    The share of contingency used divided by the share of work complete. If 42% of the contingency is gone at 48% complete, the index is 0.88: contingency is being used a little slower than the work is progressing.

    What happens to unused contingency?

    The contract decides. On many GMP contracts unused contractor contingency returns to the owner as savings or is split under a shared-savings clause; owner contingency stays with the owner. On lump-sum work the contractor’s contingency is just part of its price.

    Should pending items count against contingency?

    Track them separately but show them. Remaining after pending tells you what is really free to spend; counting pending items as spent before they are approved can hide real savings.

    Sources

    Checked Nov 21, 2026. Who may use each contingency, and who keeps what is left, are contract terms. This tool tracks the numbers; it does not interpret your contract.

    1. Integrated Project Delivery: A Guide (2007), AIA and AIA California Council (checked Nov 21, 2026).Used for: contingency and shared savings under target-cost arrangements.
    2. GSAM Subpart 536.71: Construction-Manager-as-Constructor Contracting, Acquisition.gov (checked Nov 21, 2026).Used for: guaranteed maximum price construction options on federal CMc work.

    When the spreadsheet version stops scaling

    Contingency moves belong in the budget, with a reason.

    In os.construction a contingency draw is a budget modification from the contingency line to the line that needs it, with a note, and change events can be typed as Contingency or Allowance from the start, so the budget shows what was drawn and why.

    • Budget modifications that move money between lines and list every transfer (live).
    • Change events typed as Contingency, Allowance, Owner Change or Transfer (live).
    • Buyout review against a captured budget snapshot (live).

    Stop re-keying the numbers behind this math.

    Project Financials tracks job costs and billing. The Accounting module includes reviewed WIP snapshots, posting and close. Learn the apps and review historical source coverage before a cutover.

    Your role (optional)

    Email gets you product updates: what shipped and what's next. Start a free trial → Founding program →

    More free tools

    Pay app builderG702/G703-style pay app: SOV, stored materials, retainage reductions, change orders, error checks, roll-forward, print and Excel export.RetainageRetainage this period, a ledger over the life of the job with reductions and release, carrying cost, and state retainage rules.Over/under billingSingle-job over/under billing: cost-to-cost, units or physical %, pending COs, uninstalled materials and loss provision.Change order markupPrice a CO with burdened labor, tax, OH&P, tiered sub markup, insurance and bond, then track it in a CO log with exposure and aging.Estimate at completionFive EAC methods side by side (CPI, CPI×SPI, budget-rate, weighted, PM ETC) with TCPI, sensitivity and a monthly trend.Markup vs marginConvert markup to margin and back, price from a target margin, and see why 20% markup is not 20% margin.Labor burdenFully burdened hourly cost: payroll taxes with wage caps, workers' comp, GL, benefits, fringe and PTO.Bonding capacityUnderwriter-style adjusted working capital and net worth, single-job and aggregate ranges, backlog utilization and what-if levers.Bond premiumPerformance, payment and bid bond cost from your own surety’s tiered rate per $1,000: gross the premium into a bid and price change orders.Cash flow curveJob and portfolio cash curves: billing lag, retainage, pay-when-paid, peak financing need, interest cost and scenario compare.Punch list closeoutImport your punch log: open items by trade and age, a burn-down forecast with a confidence band, close rates each milestone needs, closeout checklist and Excel export.RFI response timeImport your RFI log: median and P90 turnaround in calendar or business days, on-time rate by party, ball-in-court aging, late RFIs with impact and an OAC report.Critical pathEnter activities with FS, SS, FF and SF logic and lags: forward and backward pass, total and free float, the critical path, a Gantt and a network diagram, with the math shown.Earned valuePV, EV and AC from budget and percent complete: CV, SV, CPI, SPI, three EAC formulas side by side, ETC, VAC and TCPI, with the math shown.General conditionsStaff, trailer, temp utilities and dumpsters by week, month or lump sum: total, weekly burn, share of contract and cost per extra week of delay.Delivery methodEleven questions, transparent scoring: design-bid-build, CM at risk, design-build or IPD, with the points behind every answer, a comparison table and a decision memo to download.Bid bondPenal sum from a percentage, a fixed amount or the federal 20% rule, what you owe if you win and walk, and a withdrawal-risk check by stage, mistake type and state.NTP generatorFull or limited NTP letter: commencement, contract time in calendar or working days (federal holidays skipped), completion dates, early-work caps and an acknowledgment. Word, text or print.Back chargeBurdened labor, material, equipment and other trades, markup only where the subcontract allows it, the notice and cure timeline, and how much comes off the next payment.Closeout packagePick the building’s systems and contract terms and get its closeout package: TCO and CO readiness, Cx, as-builts, O&M, warranties and final payment, with due dates and an Excel checklist.WIP schedule workbenchMulti-job WIP schedule: over/under billing, fade vs prior, loss provisions, pending COs and surety ratios. Printable report and Excel with formulas.Bring your own jobFive numbers from one of your jobs, or your whole pasted WIP schedule, rendered on the os.construction dashboard: over/under billing, margin, fade risk. Runs in your browser.Migration plannerPhased plan to move onto one system: cutover off year-end and peak season, risks and exports.Stack assessment10 questions, 3 minutes. Score your systems across five dimensions and get concrete next steps.

    Ask the OS

    Reading this page

    Ask anything about this page. Answers use what you're reading as context.

    Suggested

      AI · may be imperfect · sample data where shown

      Open file