Contingency drawdown tracker
Track the owner’s and the contractor’s contingency month by month against percent complete. See what is left, how fast it is burning against the work, where the current rate lands at completion and what pending items would take, then download it as Excel with the formulas live.
Example inputs: a job at 48% complete with a $600,000 owner contingency and a $300,000 contractor contingency, six months of draws and $125,000 of pending exposure.
How this is calculated
Each contingency is tracked on its own, against the same percent complete. The straight line is a reference for comparison, not a target: contingency risk is usually front-loaded.
Remaining = starting contingency − Σ drawn to date Straight line = starting contingency × (1 − % complete) Burn index = (drawn ÷ starting) ÷ % complete 1.0 = in step with the work Used at current rate = drawn ÷ % complete linear projection to 100% Left at current rate = starting − used at current rate Free after pending = remaining − pending exposure
Worked example
At 48% complete the owner has drawn $210,000 of $600,000 (35%), a burn index of 0.73, and the contractor $127,000 of $300,000 (42%), an index of 0.88. At those rates the owner would use $437,500 and the contractor about $264,600 by completion, leaving $162,500 and $35,400. After pending items, $305,000 of the owner’s and $133,000 of the contractor’s contingency is free to spend.
Owner and contractor contingency are different money
Owner contingency covers the owner’s decisions and unknowns; contractor contingency covers the contractor’s own risk inside a GMP or price. Mixing them hides who is spending what. Buyout results feed straight into this: savings often move into contingency and overruns come out of it, so keep the buyout log alongside. For the whole-job forecast, the estimate at completion calculator shows the EAC trend month by month.
How to track contingency drawdown
- Enter both contingencies. The owner’s contingency and the contractor’s contingency as they stood at the start (or at GMP), kept separate because they belong to different parties under different rules.
- Log each period. For every month: cumulative percent complete and how much each contingency was drawn that month. Paste rows from a spreadsheet if you have them.
- Add pending exposure. Known draws that are coming but not approved yet: open change events, pending buyout overruns, unresolved claims.
- Read the burn index and chart. A burn index over 1 means contingency is going faster than the work. The chart compares what is left with a straight-line drawdown.
- Export. Download the Excel tracker with live formulas and a chart, or the CSV, for the monthly cost review or the owner report.
Contingency questions
What is the difference between owner and contractor contingency?
Owner contingency is money the owner holds for changes it decides on, such as scope additions, unforeseen conditions or design changes, and it usually sits outside the construction contract. Contractor contingency sits inside the contractor’s price or GMP for the contractor’s own risks, such as buyout gaps, estimating errors and coordination issues. The contract says who can use each, for what, and who keeps what is left.
How fast should contingency be used?
Most risk is front-loaded: unknown conditions show up in sitework and demolition, and buyout surprises appear early. A straight line against percent complete is a simple reference, not a rule. A burn index well above 1 early in the job is normal for some work types; well above 1 past mid-job deserves a hard look at the remaining risk.
What is a contingency burn index?
The share of contingency used divided by the share of work complete. If 42% of the contingency is gone at 48% complete, the index is 0.88: contingency is being used a little slower than the work is progressing.
What happens to unused contingency?
The contract decides. On many GMP contracts unused contractor contingency returns to the owner as savings or is split under a shared-savings clause; owner contingency stays with the owner. On lump-sum work the contractor’s contingency is just part of its price.
Should pending items count against contingency?
Track them separately but show them. Remaining after pending tells you what is really free to spend; counting pending items as spent before they are approved can hide real savings.
Sources
Checked Nov 21, 2026. Who may use each contingency, and who keeps what is left, are contract terms. This tool tracks the numbers; it does not interpret your contract.
- Integrated Project Delivery: A Guide (2007), AIA and AIA California Council (checked Nov 21, 2026).Used for: contingency and shared savings under target-cost arrangements.
- GSAM Subpart 536.71: Construction-Manager-as-Constructor Contracting, Acquisition.gov (checked Nov 21, 2026).Used for: guaranteed maximum price construction options on federal CMc work.
When the spreadsheet version stops scaling
Contingency moves belong in the budget, with a reason.
In os.construction a contingency draw is a budget modification from the contingency line to the line that needs it, with a note, and change events can be typed as Contingency or Allowance from the start, so the budget shows what was drawn and why.
- Budget modifications that move money between lines and list every transfer (live).
- Change events typed as Contingency, Allowance, Owner Change or Transfer (live).
- Buyout review against a captured budget snapshot (live).
Stop re-keying the numbers behind this math.
Project Financials tracks job costs and billing. The Accounting module includes reviewed WIP snapshots, posting and close. Learn the apps and review historical source coverage before a cutover.
Email gets you product updates: what shipped and what's next. Start a free trial → Founding program →
You're subscribed.
We'll email you when something ships. The live tools are open now: start a 14-day free trial →
Want a say in what ships? Finish your founding application (2 min) →