General conditions calculator
Build a general conditions estimate line by line: supervision, field office, temporary utilities, dumpsters and the rest, priced per week, per month or as a lump sum. See the total, the share of the contract, the weekly burn, and what each extra week on site costs.
Example inputs: a 52-week, $12,000,000 job. The quantities and rates are placeholders, not market prices. Replace them with your own costs.
Prefer a spreadsheet? Get the free job cost report template for Excel
How this is calculated
Every line is quantity × rate × time. Weekly lines run for their weeks; monthly lines convert at 52 ÷ 12 = 4.33 weeks per month, so a monthly rental over a 52-week job costs exactly twelve months; lump sums do not depend on time. A time-related line with no weeks entered runs for the whole job, and those lines are what a delay extends.
Weekly cost of a line = quantity × rate (per week)
= quantity × rate ÷ (52 ÷ 12) (per month)
Line total = weekly cost × weeks on the job (weeks blank = whole duration)
= quantity × rate (lump sum)
Total general conditions = Σ line totals
% of contract = total ÷ contract value
Average weekly burn = total ÷ duration in weeks Monthly burn = weekly burn × 52 ÷ 12
Cost per extra week = Σ weekly cost of lines that run the whole job
Delay cost = cost per extra week × weeks of delayGeneral conditions example: the sample job
The sample is an illustrative 52-week, $12,000,000 job. Its rates are placeholders chosen to make the arithmetic easy to follow, not prices to copy.
| Item | Calculation | Total |
|---|---|---|
| Project manager (half time) | 0.5 × $3,200/week × 52 weeks | $83,200 |
| Superintendent | 1 × $3,000/week × 52 weeks | $156,000 |
| Assistant superintendent | 1 × $2,200/week × 30 weeks | $66,000 |
| Project engineer | 1 × $1,800/week × 52 weeks | $93,600 |
| Field office trailer rental | 1 × $900/month × 52 weeks ÷ (52 ÷ 12) | $10,800 |
| Trailer delivery, setup and removal | 1 × $6,000 lump sum | $6,000 |
| Temporary power and water | 1 × $1,500/month × 52 weeks ÷ (52 ÷ 12) | $18,000 |
| Dumpster swaps | 2 × $650/week × 52 weeks | $67,600 |
| Portable toilets | 4 × $180/month × 52 weeks ÷ (52 ÷ 12) | $8,640 |
| Temporary fencing | 1 × $9,500 lump sum | $9,500 |
| Total | Σ lines | $519,340 |
That is 4.33% of the contract and an average burn of $9,987 a week ($43,278 a month). The lines that run to completion (the project manager, superintendent, project engineer, trailer, temporary power and water, dumpsters and toilets) cost $8,420 a week together, so each extra week on site adds $8,420, about $1,203 per calendar day, and a 4-week slip adds $33,680. The assistant superintendent (30 weeks), the trailer setup and the fencing do not move with a delay, which is why the cost per extra week is lower than the average burn.
What to include, and where it goes
General conditions are job overhead: costs the project causes that no single trade carries. They belong in the estimate’s direct cost, not in the company overhead that markup recovers; mixing the two makes job margins impossible to compare, as how to calculate overhead and markup explains. Typical lines are project staff time charged to the job, the field office, temporary utilities and facilities, dumpsters and cleanup, small tools, safety and mobilization. On cost-plus and GMP contracts, the contract defines which of these are reimbursable, whether staff are billed at actual or fixed rates, and whether general conditions are a lump sum, so read it before you build the estimate.
Pricing extended general conditions
When a job runs long, the time-related lines keep billing. The cost per extra week here is the starting point for a time extension request or a delay claim: only the items that actually stay longer count, the slip has to be shown on the schedule, and the contract decides whether the delay is compensable at all. Watch for no-damages-for-delay clauses and notice deadlines, and compare the daily figure with any liquidated damages rate the owner can charge. Read extension-of-time preparation and delay analysis methods, and use the critical path calculator to check whether the delayed work actually drives completion.
Related: the markup vs margin calculator for the fee on top, the change order markup calculator and how to price a change order when a change adds time, the earned value calculator to track the job against budget, and the free job cost report template to track general conditions spend against this estimate. In the glossary: general conditions, overhead allocation, contingency and cost code.
How to estimate general conditions with this calculator
- Set the job. Enter the contract value, the planned duration in weeks and, if you want to price a slip, the number of weeks of delay.
- Replace the example lines. For each general conditions item, enter a description, a quantity (people, units or swaps), your rate and whether that rate is per week, per month or a lump sum. The example rates are placeholders, not market prices.
- Set durations. Leave weeks blank for items that run the whole job, such as the superintendent and the trailer. Enter weeks for items that only run part of it, such as an assistant superintendent during peak trades. Clear a line to remove it.
- Read the totals. Read total general conditions, the share of the contract, the average weekly and monthly burn, and the cost of each extra week the job runs.
- Export. Download the CSV for the estimate, a change order request or a delay claim backup, or print the summary.
General conditions questions
What are general conditions costs in construction?
They are the contractor’s job-specific costs of running the site that are not tied to one trade: the project manager, superintendent and project engineer time charged to the job, the field office trailer, temporary power, water, toilets and fencing, dumpsters and cleanup, and similar items. Company overhead such as the accounting department and office rent is not general conditions. The contract decides which items count, especially on cost-plus and GMP work.
How do you calculate general conditions?
List every item, then multiply quantity × rate × time. Staff and rentals are time-related: people × weekly cost × weeks on the job, or units × monthly rate × months. One-time items such as trailer delivery and setup, fencing or final cleaning are lump sums. Add them up for the total, divide by the duration for the weekly burn, and divide by the contract value for the share of the contract.
What percentage of the contract should general conditions be?
There is no reliable single figure. The share depends on duration, job size, staffing, site conditions, delivery method and what the contract counts as general conditions, so two well-run jobs can be far apart. Treat the percentage as a check against your own past jobs of similar size and length, not against a rule of thumb.
How do you calculate extended general conditions for a delay?
Add up the weekly cost of the time-related items that actually stay on site longer because of the delay, usually the staff and rentals that run to completion, and multiply by the weeks of delay. One-time costs and items already finished do not extend. Whether you can recover the cost is a contract question: notice requirements, excusable versus compensable delay and any no-damages-for-delay clause all matter, and claims are normally priced on actual costs, not the estimate.
What is the difference between general conditions and general requirements?
In CSI MasterFormat, Division 01 General Requirements covers administrative and temporary-facility requirements in the specifications, while the general conditions document, such as AIA A201, sits with the contract in Division 00. In cost terms many builders use general conditions for time-related staff and field office costs and general requirements for task-related Division 01 items. Usage varies, so the contract’s definitions control.
Sources
Checked Nov 18, 2026. The calculator applies your quantities and rates. This page does not publish or assume any market rate or typical general conditions percentage.
- AIA A201-2017 General Conditions of the Contract for Construction, American Institute of Architects (current).Used for: the contract meaning of “general conditions”, distinct from general conditions costs.
- AIA A102-2017 Owner-Contractor Agreement, Cost of the Work Plus a Fee with a GMP, American Institute of Architects (current).Used for: how a cost-plus or GMP agreement defines which site costs are reimbursable as cost of the work.
- MasterFormat, Construction Specifications Institute (current).Used for: Division 01 General Requirements versus the Division 00 contracting requirements.
When the spreadsheet version stops scaling
Track general conditions against the estimate, every week.
An estimate is only half the job. In os.construction, general conditions are cost codes like any other, so staff time, rentals and site costs land against the budget line they were estimated on.
- Commitments, direct costs and approved change orders land on the cost code they belong to (live).
- PM cost-to-complete inputs are dated and freeze for the period once approved or soft-closed (live).
- WIP snapshots show a calculation trace on every job and link to the forecast and job cost (live).
Stop re-keying the numbers behind this math.
Project Financials tracks job costs and billing. The Accounting module includes reviewed WIP snapshots, posting and close. Learn the apps and review historical source coverage before a cutover.
Email gets you product updates: what shipped and what's next. Start a free trial → Founding program →
You're subscribed.
We'll email you when something ships. The live tools are open now: start a 14-day free trial →
Want a say in what ships? Finish your founding application (2 min) →