General conditions calculator

Build a general conditions estimate line by line: supervision, field office, temporary utilities, dumpsters and the rest, priced per week, per month or as a lump sum. See the total, the share of the contract, the weekly burn, and what each extra week on site costs.

  • Free
  • No signup
  • Runs in your browser
  • Shareable link

Inputs

$
weeks
Planned, mobilization to completion.
weeks
General conditions line items

Example, replace with your own costs. These quantities and rates are placeholders so the tool works on load. They are not market prices or benchmarks.

$
$
$
$
$
$
$
$
$
$
$
$
$
$
Quantity is people, units or swaps (0.5 for a half-time role). Leave weeks blank (“all”) for items that run the whole job: those are the ones that extend if it runs long. Weeks are ignored for lump sums. Clear a line’s item, quantity and rate to remove it.

General conditionsLive

Total general conditions
$0
Average weekly burn
$0
Cost per extra week
$0
General conditions cost by line item
Runs to completion (extends with delay)Fixed number of weeksLump sum
    Line-by-line breakdown
    ItemPer weekWeeksTotal

    Example inputs: a 52-week, $12,000,000 job. The quantities and rates are placeholders, not market prices. Replace them with your own costs.

    Prefer a spreadsheet? Get the free job cost report template for Excel

    See it in the app

    Method

    How this is calculated

    Every line is quantity × rate × time. Weekly lines run for their weeks; monthly lines convert at 52 ÷ 12 = 4.33 weeks per month, so a monthly rental over a 52-week job costs exactly twelve months; lump sums do not depend on time. A time-related line with no weeks entered runs for the whole job, and those lines are what a delay extends.

    Weekly cost of a line   = quantity × rate                 (per week)
                            = quantity × rate ÷ (52 ÷ 12)     (per month)
    Line total              = weekly cost × weeks on the job  (weeks blank = whole duration)
                            = quantity × rate                 (lump sum)
    
    Total general conditions = Σ line totals
    % of contract            = total ÷ contract value
    Average weekly burn      = total ÷ duration in weeks       Monthly burn = weekly burn × 52 ÷ 12
    Cost per extra week      = Σ weekly cost of lines that run the whole job
    Delay cost               = cost per extra week × weeks of delay

    General conditions example: the sample job

    The sample is an illustrative 52-week, $12,000,000 job. Its rates are placeholders chosen to make the arithmetic easy to follow, not prices to copy.

    ItemCalculationTotal
    Project manager (half time)0.5 × $3,200/week × 52 weeks$83,200
    Superintendent1 × $3,000/week × 52 weeks$156,000
    Assistant superintendent1 × $2,200/week × 30 weeks$66,000
    Project engineer1 × $1,800/week × 52 weeks$93,600
    Field office trailer rental1 × $900/month × 52 weeks ÷ (52 ÷ 12)$10,800
    Trailer delivery, setup and removal1 × $6,000 lump sum$6,000
    Temporary power and water1 × $1,500/month × 52 weeks ÷ (52 ÷ 12)$18,000
    Dumpster swaps2 × $650/week × 52 weeks$67,600
    Portable toilets4 × $180/month × 52 weeks ÷ (52 ÷ 12)$8,640
    Temporary fencing1 × $9,500 lump sum$9,500
    TotalΣ lines$519,340

    That is 4.33% of the contract and an average burn of $9,987 a week ($43,278 a month). The lines that run to completion (the project manager, superintendent, project engineer, trailer, temporary power and water, dumpsters and toilets) cost $8,420 a week together, so each extra week on site adds $8,420, about $1,203 per calendar day, and a 4-week slip adds $33,680. The assistant superintendent (30 weeks), the trailer setup and the fencing do not move with a delay, which is why the cost per extra week is lower than the average burn.

    What to include, and where it goes

    General conditions are job overhead: costs the project causes that no single trade carries. They belong in the estimate’s direct cost, not in the company overhead that markup recovers; mixing the two makes job margins impossible to compare, as how to calculate overhead and markup explains. Typical lines are project staff time charged to the job, the field office, temporary utilities and facilities, dumpsters and cleanup, small tools, safety and mobilization. On cost-plus and GMP contracts, the contract defines which of these are reimbursable, whether staff are billed at actual or fixed rates, and whether general conditions are a lump sum, so read it before you build the estimate.

    Pricing extended general conditions

    When a job runs long, the time-related lines keep billing. The cost per extra week here is the starting point for a time extension request or a delay claim: only the items that actually stay longer count, the slip has to be shown on the schedule, and the contract decides whether the delay is compensable at all. Watch for no-damages-for-delay clauses and notice deadlines, and compare the daily figure with any liquidated damages rate the owner can charge. Read extension-of-time preparation and delay analysis methods, and use the critical path calculator to check whether the delayed work actually drives completion.

    Related: the markup vs margin calculator for the fee on top, the change order markup calculator and how to price a change order when a change adds time, the earned value calculator to track the job against budget, and the free job cost report template to track general conditions spend against this estimate. In the glossary: general conditions, overhead allocation, contingency and cost code.

    How to estimate general conditions with this calculator

    1. Set the job. Enter the contract value, the planned duration in weeks and, if you want to price a slip, the number of weeks of delay.
    2. Replace the example lines. For each general conditions item, enter a description, a quantity (people, units or swaps), your rate and whether that rate is per week, per month or a lump sum. The example rates are placeholders, not market prices.
    3. Set durations. Leave weeks blank for items that run the whole job, such as the superintendent and the trailer. Enter weeks for items that only run part of it, such as an assistant superintendent during peak trades. Clear a line to remove it.
    4. Read the totals. Read total general conditions, the share of the contract, the average weekly and monthly burn, and the cost of each extra week the job runs.
    5. Export. Download the CSV for the estimate, a change order request or a delay claim backup, or print the summary.

    General conditions questions

    What are general conditions costs in construction?

    They are the contractor’s job-specific costs of running the site that are not tied to one trade: the project manager, superintendent and project engineer time charged to the job, the field office trailer, temporary power, water, toilets and fencing, dumpsters and cleanup, and similar items. Company overhead such as the accounting department and office rent is not general conditions. The contract decides which items count, especially on cost-plus and GMP work.

    How do you calculate general conditions?

    List every item, then multiply quantity × rate × time. Staff and rentals are time-related: people × weekly cost × weeks on the job, or units × monthly rate × months. One-time items such as trailer delivery and setup, fencing or final cleaning are lump sums. Add them up for the total, divide by the duration for the weekly burn, and divide by the contract value for the share of the contract.

    What percentage of the contract should general conditions be?

    There is no reliable single figure. The share depends on duration, job size, staffing, site conditions, delivery method and what the contract counts as general conditions, so two well-run jobs can be far apart. Treat the percentage as a check against your own past jobs of similar size and length, not against a rule of thumb.

    How do you calculate extended general conditions for a delay?

    Add up the weekly cost of the time-related items that actually stay on site longer because of the delay, usually the staff and rentals that run to completion, and multiply by the weeks of delay. One-time costs and items already finished do not extend. Whether you can recover the cost is a contract question: notice requirements, excusable versus compensable delay and any no-damages-for-delay clause all matter, and claims are normally priced on actual costs, not the estimate.

    What is the difference between general conditions and general requirements?

    In CSI MasterFormat, Division 01 General Requirements covers administrative and temporary-facility requirements in the specifications, while the general conditions document, such as AIA A201, sits with the contract in Division 00. In cost terms many builders use general conditions for time-related staff and field office costs and general requirements for task-related Division 01 items. Usage varies, so the contract’s definitions control.

    Sources

    Checked Nov 18, 2026. The calculator applies your quantities and rates. This page does not publish or assume any market rate or typical general conditions percentage.

    1. AIA A201-2017 General Conditions of the Contract for Construction, American Institute of Architects (current).Used for: the contract meaning of “general conditions”, distinct from general conditions costs.
    2. AIA A102-2017 Owner-Contractor Agreement, Cost of the Work Plus a Fee with a GMP, American Institute of Architects (current).Used for: how a cost-plus or GMP agreement defines which site costs are reimbursable as cost of the work.
    3. MasterFormat, Construction Specifications Institute (current).Used for: Division 01 General Requirements versus the Division 00 contracting requirements.

    When the spreadsheet version stops scaling

    Track general conditions against the estimate, every week.

    An estimate is only half the job. In os.construction, general conditions are cost codes like any other, so staff time, rentals and site costs land against the budget line they were estimated on.

    • Commitments, direct costs and approved change orders land on the cost code they belong to (live).
    • PM cost-to-complete inputs are dated and freeze for the period once approved or soft-closed (live).
    • WIP snapshots show a calculation trace on every job and link to the forecast and job cost (live).

    Stop re-keying the numbers behind this math.

    Project Financials tracks job costs and billing. The Accounting module includes reviewed WIP snapshots, posting and close. Learn the apps and review historical source coverage before a cutover.

    Your role (optional)

    Email gets you product updates: what shipped and what's next. Start a free trial → Founding program →

    More free tools

    Pay app builderG702/G703-style pay app: SOV, stored materials, retainage reductions, change orders, error checks, roll-forward, print and Excel export.RetainageRetainage this period, a ledger over the life of the job with reductions and release, carrying cost, and state retainage rules.Over/under billingSingle-job over/under billing: cost-to-cost, units or physical %, pending COs, uninstalled materials and loss provision.Change order markupPrice a CO with burdened labor, tax, OH&P, tiered sub markup, insurance and bond, then track it in a CO log with exposure and aging.Estimate at completionFive EAC methods side by side (CPI, CPI×SPI, budget-rate, weighted, PM ETC) with TCPI, sensitivity and a monthly trend.Markup vs marginConvert markup to margin and back, price from a target margin, and see why 20% markup is not 20% margin.Labor burdenFully burdened hourly cost: payroll taxes with wage caps, workers' comp, GL, benefits, fringe and PTO.Bonding capacityUnderwriter-style adjusted working capital and net worth, single-job and aggregate ranges, backlog utilization and what-if levers.Bond premiumPerformance, payment and bid bond cost from your own surety’s tiered rate per $1,000: gross the premium into a bid and price change orders.Cash flow curveJob and portfolio cash curves: billing lag, retainage, pay-when-paid, peak financing need, interest cost and scenario compare.Punch list closeoutImport your punch log: open items by trade and age, a burn-down forecast with a confidence band, close rates each milestone needs, closeout checklist and Excel export.RFI response timeImport your RFI log: median and P90 turnaround in calendar or business days, on-time rate by party, ball-in-court aging, late RFIs with impact and an OAC report.Critical pathEnter activities with FS, SS, FF and SF logic and lags: forward and backward pass, total and free float, the critical path, a Gantt and a network diagram, with the math shown.Earned valuePV, EV and AC from budget and percent complete: CV, SV, CPI, SPI, three EAC formulas side by side, ETC, VAC and TCPI, with the math shown.Delivery methodEleven questions, transparent scoring: design-bid-build, CM at risk, design-build or IPD, with the points behind every answer, a comparison table and a decision memo to download.Bid bondPenal sum from a percentage, a fixed amount or the federal 20% rule, what you owe if you win and walk, and a withdrawal-risk check by stage, mistake type and state.NTP generatorFull or limited NTP letter: commencement, contract time in calendar or working days (federal holidays skipped), completion dates, early-work caps and an acknowledgment. Word, text or print.Back chargeBurdened labor, material, equipment and other trades, markup only where the subcontract allows it, the notice and cure timeline, and how much comes off the next payment.ContingencyOwner and contractor contingency against percent complete: burn index, straight-line chart, projection to completion, pending exposure and an Excel tracker with live formulas.Closeout packagePick the building’s systems and contract terms and get its closeout package: TCO and CO readiness, Cx, as-builts, O&M, warranties and final payment, with due dates and an Excel checklist.WIP schedule workbenchMulti-job WIP schedule: over/under billing, fade vs prior, loss provisions, pending COs and surety ratios. Printable report and Excel with formulas.Bring your own jobFive numbers from one of your jobs, or your whole pasted WIP schedule, rendered on the os.construction dashboard: over/under billing, margin, fade risk. Runs in your browser.Migration plannerPhased plan to move onto one system: cutover off year-end and peak season, risks and exports.Stack assessment10 questions, 3 minutes. Score your systems across five dimensions and get concrete next steps.

    Ask the OS

    Reading this page

    Ask anything about this page. Answers use what you're reading as context.

    Suggested

      AI · may be imperfect · sample data where shown

      Open file