Overhead allocation spreads indirect costs that support many jobs but belong to none, such as the fab shop, the equipment yard, small tools or supervision shared across jobs, to individual jobs on a measurable base. Common bases are labor hours, labor dollars or total direct cost. The jobs are charged, an “overhead applied” account is credited, and the overhead pool empties as it is absorbed.
For GAAP financial statements, only costs that relate to contract performance belong in contract costs. General and administrative costs, such as the main office and executive salaries, generally don’t, and are recovered through markup instead.
How it works
- Define the pools. Group indirect costs by what drives them: shop overhead, yard and equipment overhead, field supervision shared across jobs.
- Choose a base for each pool. The base should move with the cost. Shop overhead usually follows shop labor hours. Equipment overhead may follow equipment hours. Shared supervision may follow field labor hours or job count.
- Set a rate. Actual rate = actual pool ÷ actual base, computed at period end. Predetermined rate = budgeted pool ÷ budgeted base, set at the start of the year so jobs can be costed as work happens.
- Apply it. Each period, multiply each job’s actual base by the rate. Entry: Dr Job cost (overhead cost type), Cr Overhead applied.
- True up. Compare overhead applied with actual overhead incurred. The difference is over- or under-applied overhead, cleared at period or year end.
Field costs that belong to one job, such as its own trailer, superintendent and temporary utilities, are general conditions charged directly to that job, not allocated. Allocation is for shared costs only.
Worked example
Actual-rate allocation. A $30,000 shop overhead pool for the month is allocated by labor hours across three jobs with 600, 300 and 100 shop hours:
| Job | Shop hours | Share | Allocated |
|---|---|---|---|
| A | 600 | 60% | $18,000 |
| B | 300 | 30% | $9,000 |
| C | 100 | 10% | $3,000 |
| Total | 1,000 | $30,000 |
Predetermined rate. Illustrative: at the start of the year, shop overhead is budgeted at $360,000 and shop labor at 24,000 hours, so the rate is $15 per hour. During the year, jobs log 26,000 actual hours, so $390,000 is applied. Actual shop overhead is $372,000. Overhead is over-applied by $18,000, because the shop was busier than budgeted and the fixed part of the overhead was spread over more hours. The $18,000 is cleared at year end, usually as a reduction of cost of revenue, or prorated to jobs and inventory if material.
Rounding. A $100 pool over three equal jobs allocates $33.34, $33.33 and $33.33 by the largest-remainder method, so the parts add back to $100 exactly.
Choosing a base
| Base | Good for | Weakness |
|---|---|---|
| Labor hours | Shops and self-perform crews | Ignores equipment-heavy work |
| Labor dollars | Simple, already in payroll | Higher-wage crews absorb more overhead for the same time |
| Equipment hours | Yard and fleet overhead | Needs reliable equipment time capture |
| Total direct cost | Quick, works for mixed work | Subcontract-heavy jobs absorb overhead they didn’t use |
The wrong base is worse than none. A GC that allocates shop overhead by total direct cost charges a subcontracted job that never touched the shop.
Overhead in delay claims
When a project is delayed or suspended, a contractor may claim home office overhead that the job would otherwise have absorbed. On US federal contracts, boards and courts use the Eichleay formula, and they generally limit it to situations where the government suspended or delayed the work and kept the contractor on standby. The formula:
- Contract billings ÷ total company billings for the contract period × total home office overhead for that period = overhead allocable to the contract.
- Allocable overhead ÷ days of contract performance = daily overhead rate.
- Daily rate × days of compensable delay = claimed unabsorbed overhead.
Illustrative: $2 million of contract billings out of $10 million company billings, with $1.5 million of home office overhead, gives $300,000 allocable. Over 400 days of performance that is $750 a day. Thirty compensable days gives $22,500. UK claims use comparable formulas, such as Hudson and Emden. Whether any formula is accepted depends on the contract, the forum and the facts. See delay claim.
Why it matters
Without allocation, job margins look better than they are, and bids don’t recover the shop. With a careless allocation, profitable jobs subsidize bad ones and estimators lose trust in the historical costs they bid from. On federal cost-reimbursement work, FAR Part 31 governs how indirect costs may be allocated, so the method also has to survive an audit.
Common mistakes
- Allocating G&A into contract costs on GAAP statements.
- Rounding each share and leaving a few cents in the pool.
- Never truing up a predetermined rate, so a large over- or under-applied balance builds up.
- Choosing a base that doesn’t drive the cost, such as direct cost for shop overhead.
- Allocating job-specific costs that should have been charged directly.
- Changing the method mid-year without explaining it, which breaks job-to-job comparisons.
Company overhead that isn’t allocated to jobs is recovered through markup instead; how to calculate overhead and markup for a bid shows the method. The labor burden calculator handles the payroll side, which is a separate calculation.
This is general information, not accounting or tax advice.
How os.construction handles it
The Accounting close workflows support allocation runs with journal postings and linked reversal. Review the allocation basis and resulting job-cost lines before posting; a reversal is made from the resulting journal entry. See the accounting guide.
FAQ
What is overhead allocation in construction?
Overhead allocation is the process of charging indirect costs that support several jobs, such as a fabrication shop, equipment yard, small tools or shared supervision, to individual jobs using a measurable base like labor hours, labor dollars or direct cost. It makes job costs reflect what the work really costs to perform.
How do you calculate an overhead allocation rate?
Divide the overhead cost pool by the allocation base for the same period. A predetermined rate uses budgeted figures: for example, $360,000 of budgeted shop overhead divided by 24,000 budgeted labor hours gives $15 per labor hour, which is then applied to each job's actual hours.
What is over-applied and under-applied overhead?
When overhead is applied with a predetermined rate, the amount charged to jobs rarely matches actual overhead. If applied is more than actual, overhead is over-applied; if less, it is under-applied. The difference is cleared at period or year end, usually to cost of revenue, or prorated when it is material.
Should general and administrative costs be allocated to jobs?
For GAAP financial statements, generally no. Costs that relate directly to contract performance, such as field supervision, shop and equipment costs, can be included in contract costs. General and administrative costs like the main office, executive salaries and marketing are usually expensed as incurred. Tax rules for long-term contracts have their own allocation requirements, so ask your CPA.
What is the Eichleay formula?
The Eichleay formula is a method used in US federal contract claims to calculate unabsorbed home office overhead when the government suspends work and the contractor is left on standby. It allocates overhead to the contract by its share of total company billings, converts that to a daily rate, and multiplies by the days of delay. UK claims use comparable formulas such as Hudson and Emden.