- Step 1: Publish the close calendar and the cutoff
- Step 2: Get every cost in
- Step 3: Get every billing in
- Step 4: Reconcile every bank account
- Step 5: Tie each subledger to the general ledger
- Step 6: Update cost-to-complete and run WIP
- Step 7: Book the remaining adjustments
- Step 8: Review, by someone who didn’t prepare it
- Step 9: Lock the period
- Worked example: what one late invoice does to WIP
- Common mistakes
- How os.construction handles it
- FAQ
To close the month in construction accounting, set the cutoff, get every cost and every billing into the period, reconcile cash and tie each subledger to the general ledger, update cost-to-complete with the project managers, compute and post WIP, book the remaining adjustments, have someone other than the preparer review it, and lock the period. Do it in the same order every month, because each step depends on the one before.
A month-end close in a contracting business has one feature most closes don’t: revenue rides on an estimate. On jobs measured by cost-to-cost, revenue follows cost incurred against estimated total cost, so a missing subcontractor invoice understates revenue as well as cost, and an old forecast puts the wrong margin on every dollar. That is why the WIP schedule sits in the middle of the step list, not at the end of it.
The steps below are a practical order, not an accounting standard. Your revenue method, accrual policy and cutoff rules should be agreed with your CPA.
Step 1: Publish the close calendar and the cutoff
Write down the cutoff date, the day each step is due and who owns it. Send it to project managers and superintendents as well as accounting, because half of the inputs come from the field.
An example calendar for a mid-sized contractor might look like this. Yours will differ.
| Business day | Step | Owner |
|---|---|---|
| 1 to 2 | Last bills, sub pay apps, payroll, equipment charges, accruals | AP, payroll, PMs |
| 1 to 3 | Owner billings and change orders posted | Project accountants |
| 3 | Bank reconciliations | Accounting |
| 3 to 4 | Subledger tie-outs | Accounting |
| 4 to 5 | Cost-to-complete and WIP | PMs, controller |
| 5 to 6 | Adjustments, review, lock | Controller, second reviewer |
Step 2: Get every cost in
Everything performed or received in the month belongs in the month. Work through each source:
- Supplier bills and subcontractor pay apps. Post what has arrived. For work you know was performed but haven’t been billed for, record an accrual from the subcontractor’s draft pay app or the project manager’s estimate, and set it to reverse when the invoice posts. A reversing entry keeps the cost from landing twice.
- Payroll and labor burden. Post every pay run that covers the month, and accrue the days between the last pay date and month end if your policy calls for it. Make sure taxes, insurance and benefits land on the jobs as labor burden, not in overhead.
- Equipment. Post internal equipment charges to jobs at the rates you use.
- Materials received but not invoiced. If purchase order receipts are recorded, accrue what was received and not billed.
The 3-way match for construction AP covers what to check before a bill posts. Code each cost to the right job and cost code now, because recoding after WIP is run means running it again.
Step 3: Get every billing in
Post every owner pay application, T&M billing and change order billing for the period. Record retainage receivable separately from current receivables, and record only executed change orders as contract value. A pending change belongs in the project manager’s forecast notes, not in the contract amount. How to fill out a pay application covers the billing side.
Step 4: Reconcile every bank account
Complete a bank reconciliation for every account, including payroll and any project or escrow accounts. List outstanding checks and deposits in transit, and investigate anything old. Cash is the one balance a third party can confirm, so reconcile it before you rely on anything else.
Step 5: Tie each subledger to the general ledger
Each subledger total should equal its control account in the general ledger at the same date:
- AP aging to accounts payable, with retainage payable shown separately.
- AR aging to accounts receivable, with retainage receivable shown separately.
- Payroll liabilities to the withholding and accrued payroll accounts.
- Total job cost by job to the job cost accounts in the ledger.
- Fixed asset register to fixed assets and accumulated depreciation.
When they don’t tie, find the cause: a manual entry posted straight to a control account, a cutoff difference, a bill coded to a closed job. Don’t plug the difference. A practical project-to-accounting reconciliation walks through the job-level version.
Step 6: Update cost-to-complete and run WIP
Once costs are complete, ask each project manager for a current cost-to-complete by job, with reasons for any material change. Then compute the WIP schedule: percent complete, earned revenue, over billing or under billing, and a loss provision for any job now forecast to lose money. Post the adjusting entry.
How to prepare a WIP schedule has the full procedure and how to run a cost-to-complete review covers the forecast meeting. The WIP calculator handles the arithmetic for a single job.
Step 7: Book the remaining adjustments
Post the recurring and period-end entries: depreciation, prepaid insurance and other amortization, accrued interest, overhead or equipment allocations, and any intercompany entries if you run more than one entity. Use journal entries with a description and support attached, so the reviewer can see why each one exists.
Step 8: Review, by someone who didn’t prepare it
Run the trial balance and compare it with last month and the budget. Look for:
- Accounts that moved more than you can explain in a sentence.
- Jobs whose projected margin changed since last month, and why.
- Over and under billings that grew without a reason.
- Negative balances where there shouldn’t be any, such as negative AP for a vendor.
The review is a control, so it should be done by someone other than the person who prepared the entries. That’s segregation of duties applied to the close.
Step 9: Lock the period
Close the period so nothing else posts to it. If an error turns up later, the usual fix is a correcting entry in the current open month with a note explaining it. Reopening a closed month should take a reason and a second approver, and your CPA can tell you when an error is large enough that prior statements need revisiting.
Worked example: what one late invoice does to WIP
A $2,400,000 job has an estimated total cost of $2,040,000. By October 31 it has billed $1,150,000. On business day 2, posted cost to date is $867,000. The project manager reports that the drywall subcontractor finished $51,000 of October work and its pay app will arrive next week.
Without the accrual:
percent complete = $867,000 ÷ $2,040,000 = 42.5%
earned revenue = 42.5% × $2,400,000 = $1,020,000
over billing = $1,150,000 − $1,020,000 = $130,000
gross profit to date = $1,020,000 − $867,000 = $153,000
With the $51,000 accrued:
cost to date = $867,000 + $51,000 = $918,000
percent complete = $918,000 ÷ $2,040,000 = 45.0%
earned revenue = 45.0% × $2,400,000 = $1,080,000
over billing = $1,150,000 − $1,080,000 = $70,000
gross profit to date = $1,080,000 − $918,000 = $162,000
The $51,000 accrual raises revenue by $60,000, because each dollar of cost carries $2,400,000 ÷ $2,040,000 of revenue, and raises gross profit by $9,000. It also cuts the over billing liability on the balance sheet from $130,000 to $70,000. Leave the invoice out and the statements show a smaller job with a bigger liability than the one you actually have. That matters to anyone reading your WIP, including your surety. What sureties look for in your WIP explains why.
The accrual is dated October 31 and set to reverse on November 1. When the subcontractor’s pay app posts in November, the reversal offsets it and the cost isn’t counted twice.
Common mistakes
- Running WIP before costs are complete, then running it again, and again.
- Using last month’s cost-to-complete because the project managers weren’t asked in time.
- Plugging subledger differences instead of finding the entry that caused them.
- Accruals with no reversal, so the cost is counted once as an accrual and again when the invoice posts.
- Counting pending change orders as contract value in WIP.
- The preparer approving their own close.
- Reopening closed months to fix errors quietly instead of correcting them in the open month with a note.
How os.construction handles it
In the Accounting module, a controller configures the close checklist; one person prepares the evidence and a different authorized user approves it before the period closes. A hard close waits for the period’s open work, such as AP bills awaiting approval, draft payment runs, bank reconciliations not yet reviewed by a second person, due recurring journals and the period’s depreciation run, and each blocker links to where you clear it. Integrity checks and subledger tie-outs run every night, and reopening a hard-closed period takes two people. See Close the month and the month-end overview. WIP is computed from the job cost forecast and posted as an approved snapshot, as described in job cost and WIP. For more on the ledger side, see construction accounting software and construction WIP software.
FAQ
What are the steps of a construction month-end close?
Set the cutoff, get every cost in (bills, subcontractor pay apps, payroll, equipment and accruals for work received but not invoiced), get every billing in, reconcile the bank accounts, tie AP, AR, retainage and job cost to the general ledger, update cost-to-complete and the WIP schedule, book the remaining adjustments, have a second person review the results, and lock the period.
How is a construction close different from a general business close?
Revenue on most construction contracts depends on an estimate. Under a cost-to-cost method, revenue follows cost incurred against the estimated total cost, so a missing invoice or a stale cost-to-complete changes revenue, gross profit and the over or under billing on the balance sheet, not just expenses. The WIP schedule and the project managers' forecasts are part of the close.
How long should a construction month-end close take?
There is no standard. It depends on the number of jobs and entities, how quickly subcontractor invoices arrive, and how much of the work is manual. What matters more is that the close follows a calendar, that each step has an owner, and that the same steps happen in the same order every month.
Should I accrue subcontractor invoices that arrive after month end?
If the work was performed in the month, the cost generally belongs in that month. Many contractors accrue it from the project manager's estimate or the subcontractor's pay app draft and reverse the accrual when the invoice is posted. Agree the cutoff and accrual policy with your CPA, and apply it the same way every month.
What happens if I find an error after the month is closed?
Usually you correct it in the current open period with an entry that explains what it fixes, rather than reopening the closed month. Reopening may be appropriate for a material error before statements go out, but it should take a reason and a second approver. Your CPA can advise on when a prior-period correction is needed.