How to close the month in construction accounting: a step list from cutoff to lock

A construction month-end close gets every cost and every billing into the right month, proves cash and the subledgers against the ledger, updates the WIP schedule from current cost-to-complete, has someone else review it, and then locks the period. Here is the step list, an example close calendar and a worked example of what one late invoice does to WIP.

Charley Forey7 min readAccountingMonth-end closeWIP
On this page
  1. Step 1: Publish the close calendar and the cutoff
  2. Step 2: Get every cost in
  3. Step 3: Get every billing in
  4. Step 4: Reconcile every bank account
  5. Step 5: Tie each subledger to the general ledger
  6. Step 6: Update cost-to-complete and run WIP
  7. Step 7: Book the remaining adjustments
  8. Step 8: Review, by someone who didn’t prepare it
  9. Step 9: Lock the period
  10. Worked example: what one late invoice does to WIP
  11. Common mistakes
  12. How os.construction handles it
  13. FAQ

To close the month in construction accounting, set the cutoff, get every cost and every billing into the period, reconcile cash and tie each subledger to the general ledger, update cost-to-complete with the project managers, compute and post WIP, book the remaining adjustments, have someone other than the preparer review it, and lock the period. Do it in the same order every month, because each step depends on the one before.

A month-end close in a contracting business has one feature most closes don’t: revenue rides on an estimate. On jobs measured by cost-to-cost, revenue follows cost incurred against estimated total cost, so a missing subcontractor invoice understates revenue as well as cost, and an old forecast puts the wrong margin on every dollar. That is why the WIP schedule sits in the middle of the step list, not at the end of it.

The steps below are a practical order, not an accounting standard. Your revenue method, accrual policy and cutoff rules should be agreed with your CPA.

Step 1: Publish the close calendar and the cutoff

Write down the cutoff date, the day each step is due and who owns it. Send it to project managers and superintendents as well as accounting, because half of the inputs come from the field.

An example calendar for a mid-sized contractor might look like this. Yours will differ.

Business day Step Owner
1 to 2 Last bills, sub pay apps, payroll, equipment charges, accruals AP, payroll, PMs
1 to 3 Owner billings and change orders posted Project accountants
3 Bank reconciliations Accounting
3 to 4 Subledger tie-outs Accounting
4 to 5 Cost-to-complete and WIP PMs, controller
5 to 6 Adjustments, review, lock Controller, second reviewer

Step 2: Get every cost in

Everything performed or received in the month belongs in the month. Work through each source:

  • Supplier bills and subcontractor pay apps. Post what has arrived. For work you know was performed but haven’t been billed for, record an accrual from the subcontractor’s draft pay app or the project manager’s estimate, and set it to reverse when the invoice posts. A reversing entry keeps the cost from landing twice.
  • Payroll and labor burden. Post every pay run that covers the month, and accrue the days between the last pay date and month end if your policy calls for it. Make sure taxes, insurance and benefits land on the jobs as labor burden, not in overhead.
  • Equipment. Post internal equipment charges to jobs at the rates you use.
  • Materials received but not invoiced. If purchase order receipts are recorded, accrue what was received and not billed.

The 3-way match for construction AP covers what to check before a bill posts. Code each cost to the right job and cost code now, because recoding after WIP is run means running it again.

Step 3: Get every billing in

Post every owner pay application, T&M billing and change order billing for the period. Record retainage receivable separately from current receivables, and record only executed change orders as contract value. A pending change belongs in the project manager’s forecast notes, not in the contract amount. How to fill out a pay application covers the billing side.

Step 4: Reconcile every bank account

Complete a bank reconciliation for every account, including payroll and any project or escrow accounts. List outstanding checks and deposits in transit, and investigate anything old. Cash is the one balance a third party can confirm, so reconcile it before you rely on anything else.

Step 5: Tie each subledger to the general ledger

Each subledger total should equal its control account in the general ledger at the same date:

  • AP aging to accounts payable, with retainage payable shown separately.
  • AR aging to accounts receivable, with retainage receivable shown separately.
  • Payroll liabilities to the withholding and accrued payroll accounts.
  • Total job cost by job to the job cost accounts in the ledger.
  • Fixed asset register to fixed assets and accumulated depreciation.

When they don’t tie, find the cause: a manual entry posted straight to a control account, a cutoff difference, a bill coded to a closed job. Don’t plug the difference. A practical project-to-accounting reconciliation walks through the job-level version.

Step 6: Update cost-to-complete and run WIP

Once costs are complete, ask each project manager for a current cost-to-complete by job, with reasons for any material change. Then compute the WIP schedule: percent complete, earned revenue, over billing or under billing, and a loss provision for any job now forecast to lose money. Post the adjusting entry.

How to prepare a WIP schedule has the full procedure and how to run a cost-to-complete review covers the forecast meeting. The WIP calculator handles the arithmetic for a single job.

Step 7: Book the remaining adjustments

Post the recurring and period-end entries: depreciation, prepaid insurance and other amortization, accrued interest, overhead or equipment allocations, and any intercompany entries if you run more than one entity. Use journal entries with a description and support attached, so the reviewer can see why each one exists.

Step 8: Review, by someone who didn’t prepare it

Run the trial balance and compare it with last month and the budget. Look for:

  • Accounts that moved more than you can explain in a sentence.
  • Jobs whose projected margin changed since last month, and why.
  • Over and under billings that grew without a reason.
  • Negative balances where there shouldn’t be any, such as negative AP for a vendor.

The review is a control, so it should be done by someone other than the person who prepared the entries. That’s segregation of duties applied to the close.

Step 9: Lock the period

Close the period so nothing else posts to it. If an error turns up later, the usual fix is a correcting entry in the current open month with a note explaining it. Reopening a closed month should take a reason and a second approver, and your CPA can tell you when an error is large enough that prior statements need revisiting.

Worked example: what one late invoice does to WIP

Illustrative numbersA made-up job, using a cost-to-cost method. Your revenue method and accrual policy may differ.

A $2,400,000 job has an estimated total cost of $2,040,000. By October 31 it has billed $1,150,000. On business day 2, posted cost to date is $867,000. The project manager reports that the drywall subcontractor finished $51,000 of October work and its pay app will arrive next week.

Without the accrual:

percent complete = $867,000 ÷ $2,040,000 = 42.5%

earned revenue = 42.5% × $2,400,000 = $1,020,000

over billing = $1,150,000 − $1,020,000 = $130,000

gross profit to date = $1,020,000 − $867,000 = $153,000

With the $51,000 accrued:

cost to date = $867,000 + $51,000 = $918,000

percent complete = $918,000 ÷ $2,040,000 = 45.0%

earned revenue = 45.0% × $2,400,000 = $1,080,000

over billing = $1,150,000 − $1,080,000 = $70,000

gross profit to date = $1,080,000 − $918,000 = $162,000

Effect of accruing a late subcontractor invoiceWithout the accrual, cost to date is 867,000 dollars, earned revenue 1,020,000 and over billing 130,000. With the 51,000 dollar accrual, cost is 918,000, earned revenue 1,080,000 and over billing 70,000. Revenue moves by 60,000 and gross profit by 9,000.WITHOUT ACCRUALWITH $51,000 ACCRUEDCOST$867,000EARNED$1,020,000OVER BILLED$130,000COST$918,000EARNED$1,080,000OVER BILLED$70,000ONE MISSING INVOICE MOVES COST, REVENUE AND THE BALANCE SHEET
Under cost-to-cost, a missing cost understates revenue too. Illustrative.

The $51,000 accrual raises revenue by $60,000, because each dollar of cost carries $2,400,000 ÷ $2,040,000 of revenue, and raises gross profit by $9,000. It also cuts the over billing liability on the balance sheet from $130,000 to $70,000. Leave the invoice out and the statements show a smaller job with a bigger liability than the one you actually have. That matters to anyone reading your WIP, including your surety. What sureties look for in your WIP explains why.

The accrual is dated October 31 and set to reverse on November 1. When the subcontractor’s pay app posts in November, the reversal offsets it and the cost isn’t counted twice.

Common mistakes

  • Running WIP before costs are complete, then running it again, and again.
  • Using last month’s cost-to-complete because the project managers weren’t asked in time.
  • Plugging subledger differences instead of finding the entry that caused them.
  • Accruals with no reversal, so the cost is counted once as an accrual and again when the invoice posts.
  • Counting pending change orders as contract value in WIP.
  • The preparer approving their own close.
  • Reopening closed months to fix errors quietly instead of correcting them in the open month with a note.

How os.construction handles it

In the Accounting module, a controller configures the close checklist; one person prepares the evidence and a different authorized user approves it before the period closes. A hard close waits for the period’s open work, such as AP bills awaiting approval, draft payment runs, bank reconciliations not yet reviewed by a second person, due recurring journals and the period’s depreciation run, and each blocker links to where you clear it. Integrity checks and subledger tie-outs run every night, and reopening a hard-closed period takes two people. See Close the month and the month-end overview. WIP is computed from the job cost forecast and posted as an approved snapshot, as described in job cost and WIP. For more on the ledger side, see construction accounting software and construction WIP software.

FAQ

What are the steps of a construction month-end close?

Set the cutoff, get every cost in (bills, subcontractor pay apps, payroll, equipment and accruals for work received but not invoiced), get every billing in, reconcile the bank accounts, tie AP, AR, retainage and job cost to the general ledger, update cost-to-complete and the WIP schedule, book the remaining adjustments, have a second person review the results, and lock the period.

How is a construction close different from a general business close?

Revenue on most construction contracts depends on an estimate. Under a cost-to-cost method, revenue follows cost incurred against the estimated total cost, so a missing invoice or a stale cost-to-complete changes revenue, gross profit and the over or under billing on the balance sheet, not just expenses. The WIP schedule and the project managers' forecasts are part of the close.

How long should a construction month-end close take?

There is no standard. It depends on the number of jobs and entities, how quickly subcontractor invoices arrive, and how much of the work is manual. What matters more is that the close follows a calendar, that each step has an owner, and that the same steps happen in the same order every month.

Should I accrue subcontractor invoices that arrive after month end?

If the work was performed in the month, the cost generally belongs in that month. Many contractors accrue it from the project manager's estimate or the subcontractor's pay app draft and reverse the accrual when the invoice is posted. Agree the cutoff and accrual policy with your CPA, and apply it the same way every month.

What happens if I find an error after the month is closed?

Usually you correct it in the current open period with an entry that explains what it fixes, rather than reopening the closed month. Reopening may be appropriate for a material error before statements go out, but it should take a reason and a second approver. Your CPA can advise on when a prior-period correction is needed.

Share this article

Written by

Charley Forey

Founder of os.construction. We're building the operating system for construction. Project Financials follows job money, and company Accounting covers the books and controls. AI agents remain planned. We write about how money and data actually move on a job, and we build in public.