A bond is not insurance for the contractor. When a surety issues a performance and payment bond, it’s guaranteeing the owner that you’ll finish the work and pay your subs and suppliers, and it expects you, and usually your owners personally through an indemnity agreement, to repay any loss. So an underwriter reads your financials the way a lender would, with one extra focus: the work you haven’t finished yet.
That work lives in one place. The WIP schedule.
Why the WIP matters more than the income statement
Your income statement tells the surety what happened. Your WIP tells it what’s about to happen. Every open job carries an estimate of cost to complete, and every estimate is a forecast that can be wrong. A contractor with a strong year on paper and three jobs quietly fading is a bigger risk than one with a flat year and honest forecasts.
Underwriters generally want a WIP that ties to the year-end financial statements prepared by a CPA, and for larger programs they ask for interim WIPs during the year, often quarterly. They’ll also ask for a completed-jobs schedule: what each closed job was bid at and what it actually earned. That’s where they check whether your forecasts can be trusted.
The six things an underwriter checks
1. Gross profit fade. The first comparison is the margin you bid against the margin you’re projecting now, job by job. A job that was bid at 13% and now projects 11% has faded two points. One fading job is normal. A pattern of fade across most jobs says the estimating, the field, or the forecasting is optimistic. On the completed-jobs schedule, the question is whether jobs finished at, above or below the margin your WIP showed midway through.
2. Underbillings. Underbillings are an asset on the balance sheet, but sureties treat them with suspicion. An underbilling can be legitimate (approved change orders not yet billed), or it can be unrecognized fade: costs running ahead of the estimate while the forecast stays put. Many underwriters discount underbillings, or remove them entirely, when they calculate the working capital your bonding capacity is built on.
3. Overbillings against cash. Overbillings are a liability. You’ve been paid for work you owe. A common check compares total overbillings to cash and near-cash. If overbillings are bigger, the cash from those jobs has already been spent somewhere else, often funding overhead or other jobs. That’s a warning sign even when every job is profitable.
4. Estimate discipline. Underwriters look for evidence that cost to complete is updated, not inherited. Signs of a stale forecast: estimated total cost that never changes month to month, percent complete that jumps when costs come in, and jobs whose margin holds perfectly steady right up until a large loss at the end.
5. Concentration and backlog. How much of the work on hand is one job, one owner, or one type of work outside your usual range? A job much larger than anything you’ve completed is a capacity question, even if the margin looks fine. Backlog with no gross profit left in it is also worth a sentence.
6. Retainage and receivables. Retainage receivable is real money, but it’s slow money. Underwriters look at how old it is and whether closed jobs are still carrying it. Old receivables and old retainage on finished jobs suggest a closeout or collection problem.
Reading one job the way a surety would
| Column | Riverside |
|---|---|
| Contract (with $1.1M approved COs) | $49,300,000 |
| Estimated total cost | $43,679,800 |
| Cost to date | $31,700,000 |
| Percent complete (cost-to-cost) | 72.6% |
| Earned revenue | $35,778,781 |
| Billed to date | $33,000,000 |
| Over / (under) billed | ($2,778,781) |
| Margin at bid / projected | 13.2% / 11.4% |
An underwriter sees two things. First, 1.8 points of fade from bid. Not alarming on its own, but they’ll want the story: is it change order pricing, a buyout miss, or field productivity? Second, a $2.78M underbilling on a job that’s 72.6% complete. They’ll ask what explains it. If the answer is unbilled approved change orders and a billing cutoff, show the list. If the answer is “costs came in faster than the schedule of values,” the next question is whether cost to complete is still right. The anatomy of a WIP schedule walks through every column.
How to hand over a WIP that builds trust
- Tie it to the financials. Total earned revenue, over and underbillings on the WIP should match the balance sheet and income statement exactly. A WIP that doesn’t tie raises questions about everything else.
- Explain every big move. A one-line note on any job whose margin moved more than a point or whose under/over billing swung materially. Underwriters prefer bad news with an explanation to good news without one.
- Show forecast history. Estimated total cost by quarter for each open job. Steady, explained revisions look like discipline. A flat line followed by a cliff looks like the opposite.
- Reconcile underbillings to the change order log. If approved-but-unbilled changes explain the underbilling, prove it.
- Keep the completed-jobs schedule honest. It’s your track record. It’s the strongest evidence that today’s forecasts mean something.
Want a rough sense of how capacity is sized? Our bonding capacity estimator shows the common working-capital and net-worth approaches, with transparent assumptions, and the WIP calculator runs a single job. See also bonding capacity and margin fade in the glossary.
Build a reviewable surety packet
The Accounting module’s WIP app combines supported contract, billing, posted job-cost and forecast sources in dated snapshots. Review exceptions, explain estimate changes and obtain independent approval before posting. WIP, completed-contract and backlog reports read posted rows, so the packet can identify the revision and cutoff behind each number.
Confirm the format and evidence your underwriter requires. Signed work outside a posted snapshot is not included in the backlog roll-forward, and historical source completeness needs review. See Job cost and WIP, financial reports, and your first accounting cycle.