Under billing happens when you’ve earned more revenue than you’ve billed, based on percent complete. On the balance sheet it’s a current asset, commonly labeled “costs and estimated earnings in excess of billings” (a contract asset under ASC 606). Formula: earned revenue minus billed to date. A positive result is under billing.
How it works
- Measure progress. Percent complete is cost to date divided by estimated total cost (cost to date plus cost to complete).
- Earned revenue. Percent complete times the current contract value gives earned revenue.
- Billed to date. Total the pay applications through the same cutoff, gross of retainage.
- Compare. Earned revenue minus billed to date. A positive result is under billing; a negative one is over billing.
- Book it. The WIP schedule adjustment records the under billing as a contract asset and adds the same amount to revenue.
- Explain it. Every under billed job should carry a reason: timing, pending change, missed billing or forecast. The reason decides whether the asset is real.
Why it matters
Under billing means you’ve financed the owner’s project with your own cash. Sometimes the reason is timing: work happened after the pay app cutoff. Often it’s worse: unapproved change order work that hasn’t been billed, a cost overrun inflating percent complete, or a missed billing. Sureties and lenders look hard at under billings because they’re the asset most likely to turn out not to be real.
Worked example
Illustrative: Riverside Medical Center, $49.3M contract, $43.68M estimated total cost, $31.7M cost to date. Percent complete is 72.6% and earned revenue is $35,778,781. Billed to date through Pay App #9 is $33,000,000.
Under billing = $35,778,781 minus $33,000,000 = $2,778,781 (about $2.78M).
Some of that gap is cost booked after the pay app cutoff. Some is change work: until CO #14 was approved, the $78,100 of fire damper cost already in cost to date couldn’t be billed at all.
Now test the forecast. Suppose the PM’s review finds $1.0M of cost that the estimate hasn’t picked up, so estimated total cost is really about $44.68M:
| Line | Current forecast | Corrected forecast |
|---|---|---|
| Estimated total cost | $43.68M | $44.68M |
| Percent complete ($31.7M ÷ total) | 72.6% | 71.0% |
| Earned revenue | $35.78M | $34.98M |
| Billed to date | $33.00M | $33.00M |
| Under billing | $2.78M | $1.98M |
| Gross profit earned to date | $4.08M | $3.28M |
About $0.80M of the under billing came from the stale forecast, not from work the owner owes for. Correcting it cuts the asset and earned profit by the same amount. That’s the pattern lenders look for: an under billing that grows while the margin stays flat.
Under billing vs over billing
| Under billing | Over billing | |
|---|---|---|
| Formula | Earned − billed > 0 | Billed − earned > 0 |
| Balance sheet | Contract asset | Contract liability |
| Common label | Costs and estimated earnings in excess of billings | Billings in excess of costs and estimated earnings |
| Cash position | Contractor financing the work | Cash ahead of work |
| What makes it risky | Depends on forecasts and unapproved changes | Cash may be spent before the work is done |
Sorting the causes
- Timing. Cost posted after the pay app cutoff. This should clear with the next billing. If it doesn’t, it isn’t timing.
- Pending changes. Work on an unapproved change order sits in cost to date with no billable value. Track the amount by change and push for approval.
- Billing rules. Retainage, stored materials and line-item caps on the schedule of values can hold back billing even when the work is done.
- Missed billing. Line items left off a pay app. Reconcile the SOV against the cost record.
- Overrun. A cost-to-complete that hasn’t been updated. This is the one that turns into a write-down.
Common mistakes
- Assuming under billing will “catch up” next month without checking why it exists.
- Letting change order work sit unbilled for months while the paperwork waits.
- Ignoring that a cost overrun increases percent complete, which inflates earned revenue and under billing at the same time.
- Netting under billed jobs against over billed ones so the portfolio looks balanced.
- Reporting under billings to a surety without a job-by-job explanation; it can hurt bonding capacity more than the number itself.
For how sureties read both balances, see what sureties look for in your WIP.
How os.construction handles it
WIP compares supported earned revenue with billings on a dated snapshot. Posting an approved revision books the contract asset; inspect source links and pending changes to understand why it arose. See the accounting guide.
Watch the explainer · 1:45
Over billing vs under billing on a WIP schedule
- 0:00Earned vs billed
- 0:13Percent complete and earned revenue
- 0:36Over billing
- 0:54Under billing
- 1:10Reading the trend
- 1:26WIP from the posted record
Read the transcript
A WIP schedule compares what you've earned on each job with what you've billed. The gap between those two numbers is over billing or under billing, and it's one of the first things a banker or surety reads.
Start with percent complete. With the cost-to-cost method, it's cost to date divided by total estimated cost. Take an illustrative job: a one million dollar contract with eight hundred thousand dollars of estimated cost. You've spent four hundred thousand, so the job is fifty percent complete, and you've earned half the contract: five hundred thousand dollars.
Now look at billing. If you've billed six hundred thousand, you've billed one hundred thousand more than you've earned. That's over billing. It shows up as a liability, often called billings in excess of costs and estimated earnings, because you still owe the customer that work.
If you've billed only four hundred twenty thousand, you've earned eighty thousand more than you've billed. That's under billing. It's an asset, costs and estimated earnings in excess of billings: revenue you've earned but haven't invoiced yet.
Neither one is automatically good or bad. Some over billing can mean healthy cash flow. Under billing that keeps growing can mean you're slow to bill, or that costs are running ahead of the estimate and profit is fading. Watch the trend, job by job, month by month.
In os.construction, the WIP app computes each job's snapshot from posted job costs, the approved cost-to-complete forecast and billings, so you can review the evidence before you post it.
Video page with chaptersMore in Construction concepts explained
FAQ
How do you calculate under billing?
Take earned revenue to date and subtract billed to date. Earned revenue is percent complete times the current contract value, with percent complete usually measured as cost to date divided by estimated total cost. A positive result is under billing.
Is under billing an asset or a liability?
An asset. It's commonly labeled costs and estimated earnings in excess of billings, and under ASC 606 it's presented as a contract asset. It's revenue the contractor has recognized but doesn't yet have the right to invoice.
What causes under billing?
Timing is the harmless cause: work done after the pay app cutoff. The others need attention: change order work performed before the change is approved, missed or late billings, retainage or stored material rules that delay billing, and cost overruns that inflate percent complete because the estimated total cost hasn't been updated.
Why do sureties and banks worry about under billings?
Because under billings depend on the cost forecast and on getting paid for work the owner hasn't yet agreed to pay for. If the forecast is low or the change orders are rejected, the asset shrinks or disappears, taking reported profit and working capital with it.
How do you reduce under billing?
Find the cause job by job. Bill all eligible work through the cutoff, push pending change orders to approval and bill them, check stored material billing, and update the cost-to-complete so percent complete reflects the real total cost.
