Esc

↑↓ move↵ openIndex · Pagefind
Topic · 23 terms

Getting paid: pay applications, retainage and lien rights

Contractors are paid in arrears, monthly, against a schedule of values, with part of every payment held back as retainage. The pay application is the request; lien waivers and notices are how each tier protects its right to be paid.

The terms below follow the money: billing the work (SOV, G702/G703, stored materials), what gets held back (retainage and its release), and the paperwork that preserves or gives up lien rights (preliminary notices, conditional and unconditional waivers, stop payment notices, mechanics liens).

Read the guide: Getting paid: pay apps, retainage, lien waivers and notices

Payment & liens: terms defined

Billing

Pay Application (Pay App)

A contractor's periodic, itemized request for payment based on work completed and materials stored against the schedule of values.

Billing

AIA G702

The AIA Application and Certificate for Payment: the one-page summary of a pay application, signed by the contractor and certified by the architect.

Billing

AIA G703

The AIA Continuation Sheet: the line-by-line detail of a pay application, showing progress and retainage for each schedule of values item.

Billing

Schedule of Values (SOV)

The breakdown of the contract sum into line items with assigned values, used as the basis for progress billing.

Billing

Mobilization

The work and cost of getting people, equipment, temporary facilities and permits in place on site so construction can start, often billed as its own line on the schedule of values.

Billing

Stored Materials

Materials delivered and stored on site or in an approved off-site location but not yet installed, which may be billed if the contract allows.

Billing

Retainage

A percentage of each progress payment that the owner (or GC) holds back until the work is substantially or finally complete.

Billing

Retainage Release

Billing and paying out the retainage held on a contract, usually at substantial or final completion, once the contractual conditions are met.

Accounting

Retainage receivable

Retainage the owner has withheld from your pay applications: billed and earned, but not collectible until release.

Accounting

Retainage payable

Retainage you have withheld from subcontractors' pay apps, owed to them once release conditions are met.

Contracts

Pay-When-Paid

A subcontract clause that sets the timing of sub payment to follow the GC's receipt of payment from the owner.

Billing

Joint Check

A check made payable to two parties, typically a subcontractor and its supplier, so the supplier gets paid and lien risk is reduced.

Billing

Lien Waiver

A document in which a contractor, sub or supplier gives up its right to file a mechanics lien for a stated amount or period, usually in exchange for payment.

Billing

Conditional Lien Waiver

A lien waiver that only takes effect once the stated payment is actually received and clears.

Billing

Unconditional Lien Waiver

A lien waiver that takes effect immediately on signing, confirming payment has already been received for the stated amount.

Billing

Preliminary Notice

A notice a sub or supplier sends early in a job to preserve its lien rights, telling the owner and GC it is furnishing labor or materials.

Contracts

Notice of Commencement (NOC)

A recorded public notice that identifies a private construction project, its owner, contractor and lender, and anchors lien deadlines and priority in states that use it.

Contracts

Notice of Nonpayment

A written notice an unpaid subcontractor or supplier sends to preserve a payment bond claim or warn the owner and GC that it hasn't been paid; deadlines are set by state law.

Contracts

Stop Payment Notice

A claim served on an owner or construction lender that requires them to withhold enough undisbursed project funds to cover an unpaid sub or supplier.

Billing

Mechanics Lien

A legal claim against a property filed by an unpaid contractor, subcontractor or supplier who improved it.

Contracts

Notice of Completion

A recorded notice that a private project is complete, which in many states shortens the deadline for contractors, subs and suppliers to record mechanics liens.

Billing

Over billing

When billings to date exceed revenue earned to date on a job; recorded as a liability called billings in excess of costs and estimated earnings.

Billing

Under billing

When revenue earned to date exceeds billings to date; recorded as an asset called costs and estimated earnings in excess of billings.

Open file