Retainage is calculated on the cumulative amount earned, not just this period: retainage held = (work completed to date × the work rate) + (stored materials × the stored-materials rate), and this period’s retainage is that total minus what was already held. With one flat rate, it’s simply this period’s billing times the rate. Release comes later, as its own billing, usually at substantial completion less a punch list holdback and the rest at final completion.
That’s the whole formula. What makes retainage hard in practice is a reduction partway through the job, a different rate on stored materials, getting the release billed and collected, and making sure subcontractors are held and paid on the terms their subcontracts and the statute allow. The free retainage calculator runs all of this in your browser, with a ledger for the whole job and a table of state rules.
The formula, on one pay app
On a G702/G703-style pay application, retainage sits on line 5 of the summary:
retainage held = (columns D + E) × work rate + column F × stored rate
payment due = (completed and stored − retainage held) − previous certificates
So if a job has $1,950,000 of work completed to date, nothing stored, and a flat 10% rate, retainage held is $195,000. If $195,000 minus last month’s $135,000 is $60,000, that’s the retainage taken from this month’s $600,000 billing, and the payment due is $540,000. Our pay application how-to walks through every line of the form.
Worked example: 10% reduced to 5% at 50% complete
| Pay app | Billed this period | Cumulative billed | Rate applied | Retainage this period | Retainage held | Net paid |
|---|---|---|---|---|---|---|
| 1 | 300,000 | 300,000 | 10% | 30,000 | 30,000 | 270,000 |
| 2 | 450,000 | 750,000 | 10% | 45,000 | 75,000 | 405,000 |
| 3 | 600,000 | 1,350,000 | 10% | 60,000 | 135,000 | 540,000 |
| 4 | 600,000 | 1,950,000 | 10% on 150,000, 5% on 450,000 | 37,500 | 172,500 | 562,500 |
| 5 | 600,000 | 2,550,000 | 5% | 30,000 | 202,500 | 570,000 |
| 6 | 450,000 | 3,000,000 | 5% | 22,500 | 225,000 | 427,500 |
| Total | 3,000,000 | 225,000 | 2,775,000 |
Pay app 4 is the one people get wrong. The first $150,000 of that month’s work takes the job to 50% ($1,350,000 + $150,000 = $1,500,000) and is held at 10%; only the $450,000 above the milestone drops to 5%. Total retainage ends at $225,000, which is 7.5% of the contract.
Under the other common reading, where the rate on all completed work drops to 5% at 50%, pay app 4 would hold 5% of $1,950,000, or $97,500, and release $37,500 of what was already held ($135,000 − $97,500). By the end that method holds $150,000, 5% of the contract. Same contract language, a $75,000 difference in cash at completion. Read the clause and the statute before the first pay app, not at the milestone.
To step through the same six pay apps with the subcontractor tier added, and drag a slider to read the owner’s and the GC’s balances after any pay app or release, see how retainage moves through a job.
How to bill and collect the release
Retainage doesn’t arrive on its own. You bill for it, usually on a separate application or a dedicated release line, once the contract’s conditions are met.
- Reach substantial completion and get it certified the way the contract requires.
- Price the punch list. Owners typically keep back a multiple of the value of incomplete work; 150% is common in contracts and in several state statutes. In the example, a $20,000 punch list means $30,000 stays held.
- Bill the release. $225,000 held less $30,000 kept = $195,000 released, with whatever the contract asks for: consent of surety, lien waivers for the release amount, and closeout items that are already complete.
- Finish closeout (closeout documents, warranties, as-builts, O&M manuals, final waivers) and bill the last $30,000 at final completion.
- Watch the clock. Many public statutes set a deadline to release retainage after completion or acceptance, sometimes with interest when it’s late. California public works, for example, require release within 60 days after completion (Public Contract Code §7107). Our retainage release entry covers the sequence in more depth.
Flowing it down to subcontractors
The same math runs on every subcontract, usually at the rate in the subcontract, and that’s where statutes bite hardest. Say your electrical subcontractor’s $600,000 subcontract holds 10% with no reduction. When their work is done, you’re holding $60,000 of retainage payable, even though the owner’s rate on your contract dropped to 5%. Whether that’s allowed depends on the subcontract and the law where the job is:
- Federal jobs. Retainage from the government is limited to cases where progress isn’t satisfactory, capped at 10% (FAR 52.232-5(e)). Primes must pay subs within 7 days of receiving payment for their work, and the Prompt Payment Act lets primes and subs agree to retainage in the subcontract (31 U.S.C. §3905).
- California public works. Retention is capped at 5% of each payment and of the contract price, and the cap applies at every tier (Public Contract Code §7201).
- California private works. For contracts entered into on or after January 1, 2026, retention is capped at 5% of each payment and of the contract price, with exceptions (Civil Code §8811, added by SB 61). The direct contractor then has 10 days after receiving retention to pay each sub its share (Civil Code §8814).
- New York private projects of $150,000 or more cap retainage at 5% and flow that down to subcontractors (General Business Law §756-c).
Rules vary a lot by state and between public and private work. The state retainage rules table on the calculator page lists more, each with its statute.
Recording it in the books
On the receivable side, the full billing is earned, but the retained part goes to retainage receivable, aged separately from current receivables because it isn’t collectible until release. In the example, pay app 4 records $562,500 to accounts receivable and $37,500 to retainage receivable. The release billing moves $195,000 from retainage receivable to accounts receivable. On the payable side, retainage you hold from subs is retainage payable on each subcontract, released when its conditions are met. Both balances belong in the cash forecast with expected release dates; see the controller’s monthly retainage follow-up.
How os.construction handles it
Project pay applications carry retainage by rate on work and stored materials and roll it forward from application to application (pay apps, SOV and retainage). In Accounting, a certified owner pay app can draft an AR invoice through the billing bridge after rechecking the G702 math and retainage, and retainage releases and final-release closeout controls follow the AR workflow (progress billing and accounting). The getting paid in construction guide connects retainage to pay apps, lien waivers and notices.
General information, not legal or accounting advice. Retainage rates, reductions, release deadlines and flow-down rules depend on your contract and the law where the project is; rules vary by state and between public and private work. Sources: FAR 52.232-5 and FAR 32.103, 31 U.S.C. §3905, Cal. Public Contract Code §7201 and §7107, Cal. Civil Code §8811 and §8814, N.Y. General Business Law §756-c.
FAQ
How do you calculate retainage on a progress payment?
Multiply the cumulative amount of work completed to date by the retainage rate, add stored materials times their rate, and subtract the retainage already held. That difference is this period's retainage. For a single rate it is simply this period's billing times the rate: $600,000 billed at 10% retainage means $60,000 held and $540,000 paid, before any other deductions.
What does 10% retainage reduced to 5% at 50% complete mean?
Usually one of two things, and the contract decides which. Either work billed up to the 50% point is held at 10% and work after it at 5%, so total retainage ends around 7.5% of the contract, or the rate on all completed work drops to 5% at the milestone and the excess already held is released. Public statutes in some states prescribe the method, and owners often require satisfactory progress or surety consent first.
When is retainage released?
Typically in a release billing at substantial completion, less a holdback for punch list and closeout items, with the balance at final completion once closeout documents and final lien waivers are in. Many public statutes and some private prompt payment laws set deadlines for release after completion and for passing subcontractors their share once the contractor is paid.
Is retainage revenue when it is billed?
For a contractor using percentage of completion, retainage is part of the contract revenue earned as the work is done; holding it back affects when cash arrives, not when revenue is earned. It's tracked as retainage receivable, separately from regular receivables, and the balance-sheet presentation depends on whether the right to it is still conditional. Check presentation with your CPA.
Can a general contractor hold more retainage from a subcontractor than the owner holds from the GC?
It depends on the subcontract and the law where the project is. Several states cap subcontract retainage at the rate the owner withholds from the prime, or apply the same public-work cap at every tier; California's public works cap, for example, applies from the owner down through each subcontract tier. Where there's no statute, the subcontract governs.