Retainage: a controller's monthly follow-up

Track retainage receivable and payable separately, reconcile changes, and make release dates visible in the cash plan.

Charley Forey2 min readAccountingBillingRetainage
On this page
  1. Build a useful register
  2. Review each billing cycle
  3. Know the evidence limit

Retainage is easy to lose in a total invoice balance. The owner may hold money from your billing while you hold a different amount from a subcontractor. Those balances have different counterparties, terms and release conditions. Review both sides separately each month.

Build a useful register

For each contract or subcontract, record the counterparty, job, billed or invoiced amount, retainage held to date, releases and the remaining balance. Add the contract’s release conditions, supporting documents, an expected date, the person responsible and the next follow-up. Keep the contract and pay application available for review; the expected date is a forecast, not a promise of payment.

A simple illustration: an owner pay application bills $100,000 with $10,000 withheld. The current amount is $90,000 and the retainage balance is $10,000 before any later adjustments or release. A subcontractor’s separate $40,000 invoice with $4,000 withheld leaves $36,000 current and $4,000 retained. Do not net the two retainage balances just because they belong to the same job.

Review each billing cycle

  1. Compare the current pay application and subcontract invoices with their agreements and approved changes. Check the applicable retainage calculation and any change in rate against the actual terms.
  2. Reconcile the opening balance plus new retainage, less releases and corrections, to the ending balance. Investigate differences by counterparty and job.
  3. Check what remains for release: for example, completion evidence, a required document or an owner review. Assign the next action and date rather than assuming the balance will clear at completion.
  4. Put expected receipts and payments in the cash forecast separately. Update the dates when the release conditions or review schedule change.

Use the retainage calculator for an illustration, how to calculate retainage for a worked reduction and release, and the closeout and retainage release guide for the handoff. Contract language and circumstances vary; confirm the applicable terms and obtain professional advice where needed.

Know the evidence limit

Accounting AR aging and reconciliation use effective posting dates, including supported retainage activity. A current open balance alone is not an as-of reconciliation, and historical source completeness still needs review. Preserve dated pay applications, releases and ledger evidence for your cutoff; do not treat an unavailable check as a zero difference. See Accounts receivable and the billing-to-cash workflow.

See how a pay app is built from the contract, with retainage and executed change orders: pay application software.

Share this article

Written by

Charley Forey

Founder of os.construction. We're building the operating system for construction. Project Financials follows job money, and company Accounting covers the books and controls. AI agents remain planned. We write about how money and data actually move on a job, and we build in public.

Apply to the founding program →Start a free trial →
Open file