A schedule of values (SOV) divides the contract sum, including the contractor’s markup, into billing lines that the owner approves and that every pay application reports progress against. A budget divides the contractor’s estimated cost into cost codes and cost types that actual and committed cost are tracked against. The SOV is revenue, organized for the owner. The budget is cost, organized for the contractor. They should map to each other, but they shouldn’t be the same list.
Both get built from the estimate in the weeks after award, often by the same person, so it is tempting to make one spreadsheet do both jobs. That works until month three, when billing is running ahead of cost on some lines and behind on others and nobody can see which.
Side by side
| Schedule of values | Budget | |
|---|---|---|
| Divides | The contract sum (price) | Estimated cost |
| Includes markup | Yes, in the lines or as a fee line | No; profit is the gap between price and budget |
| Includes contractor contingency | Not as a visible line on most lump-sum jobs | Usually, as its own line |
| Audience | Owner, architect, lender | PM, project accountant, executives |
| Approved by | The owner or architect | The contractor’s own management |
| Organized by | Whatever the owner wants to see: division, building, floor, phase | Cost code and cost type |
| Level of detail | Usually coarser | Usually finer |
| Used for | Monthly pay applications on the G703 | Job cost reports, cost to complete, WIP |
| Changes when | An owner change order is executed | Owner change orders, plus internal budget transfers |
| Progress measured as | Percent of each line billed | Cost to date and committed cost against each code |
What the schedule of values is for
The schedule of values exists so the owner can pay for progress without auditing your cost. Each month the contractor reports how much of each line is complete and how much material is stored, and the owner pays that share of the line’s value, less retainage. The architect or owner reviews the SOV at the start of the job, partly to check that the values are reasonable and not front-loaded.
Because it adds up to the contract sum, every line carries some of the contractor’s markup, either spread through the values or shown as a fee line. Many SOVs also carry general conditions, bonds and insurance, and mobilization as their own lines, which the contract may limit. How to fill out a pay application and the anatomy of a pay app explainer show how the lines are billed.
What the budget is for
The budget is the contractor’s cost plan. It starts from the estimate, reconciled to the signed contract, with the fee taken out and contingency set aside. Each line is a cost code plus a cost type, such as labor, materials, equipment or subcontract, because that is the level at which costs are committed and spent. How to set up a construction project budget covers the steps.
As the job runs, the budget is compared with committed cost (subcontracts and purchase orders) and actual cost to forecast the cost to complete. That forecast feeds percent complete on the WIP schedule, which is a cost-based measure, not a billing one.
How to connect them
- Build the budget first, from cost codes. It reflects how you’ll buy and track the work.
- Build the SOV from the budget, grouping cost codes into the lines the owner wants, and adding markup.
- Map every cost code to exactly one SOV line. Many-to-one is fine. One cost code split across two billing lines makes comparison impossible.
- Add change orders to both. An executed owner change order adds or adjusts an SOV line and adds budget to the cost codes it affects.
- Compare monthly by line. Billed percent on each SOV line against cost percent on the cost codes behind it.
A worked example
Illustrative: a $2,400,000 lump-sum job, with a budget of $2,200,000 including $49,000 of contractor contingency.
| SOV line | SOV value | Budget lines behind it | Budget |
|---|---|---|---|
| General conditions | $210,000 | 01 general conditions | $195,000 |
| Sitework | $180,000 | 31 sitework subcontract | $165,000 |
| Concrete | $420,000 | 03 concrete labor, 03 concrete materials | $370,000 |
| Framing | $360,000 | 06 framing subcontract | $330,000 |
| MEP | $780,000 | 22, 23, 26 subcontracts | $735,000 |
| Finishes | $350,000 | 09 finishes subcontracts | $320,000 |
| Bonds and insurance | $40,000 | 01 bonds and insurance | $36,000 |
| Fee | $60,000 | none | n/a |
| Contingency | n/a | 01 contractor contingency | $49,000 |
| Total | $2,400,000 | $2,200,000 |
Planned gross profit is $200,000. Only $60,000 of it is visible as the fee line; the rest sits inside the other SOV values.
At month four, the concrete line is billed at 80%, or $336,000. Concrete cost to date is $230,000 of a $370,000 budget, about 62%. That 18-point gap is the question to ask before the pay app goes out: are the concrete values front-loaded, is material stored but not yet in place, or is the cost forecast too low? Without the mapping, the gap disappears into a job-level total where other lines happen to offset it.
Common mistakes
- Using the SOV as the budget. Markup sits inside every line, so cost variances look smaller than they are and the fee gets spent before anyone notices.
- Splitting a cost code across SOV lines, so billed and cost progress can’t be compared.
- Front-loading the SOV beyond what the work supports. It invites a rejected pay app and can show up as over-billing on your WIP.
- Forgetting the change order on one side. An executed change that reaches the SOV but not the budget makes the job look more profitable than it is, and the reverse makes it look worse.
- Billing to the budget’s percent complete instead of to the work actually in place on each line.
- Moving money between SOV lines without approval. Internal budget transfers are your business; SOV reallocations usually need the owner’s or architect’s agreement.
Tools and related reading
Over-billing vs under-billing explains what the gap between billing and cost means on the WIP, the WIP calculator runs the numbers, and how to bill stored materials covers the most common reason a line bills ahead of cost. The budget, commitments and cost explainer shows how the cost side fills in, and the job cost report template gives you the layout.
In os.construction, Payment Applications build the G702/G703 from the contract’s schedule of values and its executed change orders, and the Budget tool tracks original, revised and projected budget against committed and direct cost by cost code and cost type. See construction WIP software for how billing and cost meet on the WIP.
FAQ
What is the difference between a schedule of values and a budget?
A schedule of values divides the contract sum, including the contractor's markup, into billing lines that the owner or architect approves and that each pay application reports progress against. A budget divides the contractor's estimated cost into cost codes and cost types that it tracks actual and committed cost against. One is revenue for the owner's eyes; the other is cost for the contractor's.
Should the schedule of values match the budget?
Not line for line. The SOV is organized the way the owner wants to see progress and pay, and it includes markup. The budget is organized the way the contractor controls cost, often in more detail. They should be reconcilable: every budget cost code should map to one SOV line, so billed progress and cost progress can be compared by area of work.
Does the schedule of values include profit?
Yes, because it adds up to the contract sum. Some contracts, especially cost-plus and GMP contracts, show the fee as its own SOV line. On many lump-sum jobs the markup is spread through the lines instead. Either way, the SOV total is the price, not the cost.
How does each one change during the job?
The schedule of values changes when an owner change order is executed, usually by adding a line or adjusting the affected one. The budget changes for the same approved change orders, and also through internal budget transfers between cost codes, which the owner doesn't see and which don't change the contract.
Can the owner see the contractor's budget?
On a lump-sum job, usually not; the owner sees the schedule of values and pays against it. On cost-plus and GMP jobs the owner often has audit rights over actual cost, and the contract may require cost reporting in a set format. What the owner is entitled to see is set by the contract.