How to calculate construction overhead and markup for a bid

Your markup has one job: recover company overhead and leave the profit you planned. To set it, you need an annual overhead budget, a realistic revenue volume, a profit target, and the margin-to-markup conversion most estimators get wrong. Here's the method step by step, with a worked bid and what happens to the number when volume drops.

Charley Forey5 min readEstimatingAccountingJob cost
On this page
  1. Step 1: Separate job costs from company overhead
  2. Step 2: Build a 12-month overhead budget
  3. Step 3: Forecast revenue honestly
  4. Step 4: Add the profit target and convert to markup
  5. Worked example: a $500,000 bid
  6. What happens when volume drops
  7. Step 5: Adjust per job, then check recovery monthly
  8. How os.construction handles it
  9. FAQ

To calculate the markup for a construction bid, divide next year’s company overhead by the revenue you expect to bill to get an overhead rate, add your target profit to get the gross margin you need, and convert that margin to a markup with markup = margin ÷ (1 − margin). With $720,000 of overhead on $8,000,000 of revenue and a 5% profit target, you need a 14% margin, which is a 16.28% markup on direct cost, not 14%.

Most bids that “covered overhead” on paper and didn’t in the bank went wrong in one of two places: overhead and profit percentages were added to cost as if they were margins, or the overhead rate assumed more volume than the company won. This post walks through both.

Step 1: Separate job costs from company overhead

Direct cost is everything the job causes: labor with its labor burden, material, equipment, subcontracts, and general conditions like the superintendent, trailer, temporary utilities, dumpsters and project insurance. All of that belongs in the estimate line by line.

Company overhead is what you spend to stay in business whether or not you win this job: office rent and utilities, office and executive salaries and their burden, accounting and legal, software, insurance that isn’t charged to jobs, marketing, and vehicles that aren’t costed to projects. That’s what markup has to recover. If a cost is in both places, you’ll double-charge it; if it’s in neither, you’ll never recover it.

Step 2: Build a 12-month overhead budget

Start from last year’s general ledger, not from memory. Take actual overhead by account, remove one-offs, add known changes (a new estimator, a rent increase, a software contract), and you have next year’s overhead budget. In the example below it’s $720,000.

Step 3: Forecast revenue honestly

The overhead rate divides by volume, so volume is the number to be careful with. Use backlog that will be earned next year plus a realistic share of the pipeline, not your best-ever year. The example uses $8,000,000.

overhead rate = annual overhead ÷ annual revenue = $720,000 ÷ $8,000,000 = 9%

Revenue is the most common base because it’s how you’ll check recovery later, but it isn’t the only one. Contractors with a large self-perform crew often allocate shop or field overhead on labor hours or labor cost instead (see overhead allocation). The federal cost principles make the same point for government contractors: pick a base that spreads each pool of indirect cost in proportion to the benefit it provides, and apply it consistently (FAR 31.203).

Step 4: Add the profit target and convert to markup

Overhead and profit are both shares of the selling price, so they add as margins:

required gross margin = overhead rate + profit target = 9% + 5% = 14%

Then convert margin to markup, because you’ll apply it to cost:

markup = margin ÷ (1 − margin) = 0.14 ÷ 0.86 = 16.28%

bid price = direct cost ÷ (1 − margin)

The shortcut that sinks people is adding 9% + 5% to cost. A 14% markup is a 12.28% margin, so the job recovers its overhead and leaves 3.28% profit, not 5%. Our post on markup vs margin shows the same trap on change orders, and the markup and margin calculator does the conversion both ways.

Worked example: a $500,000 bid

Illustrative numbersA made-up contractor with $720,000 of annual overhead, an $8,000,000 revenue forecast and a 5% profit target. Direct cost includes burdened labor, material, equipment, subcontracts and general conditions.
Right: price = cost ÷ (1 − 14%) Wrong: cost × 1.14
Direct cost $500,000 $500,000
Markup $81,395 (16.28%) $70,000 (14%)
Bid price $581,395 $570,000
Overhead recovered (9% of price) $52,326 $51,300
Profit left $29,069 (5.0%) $18,700 (3.28%)

On one bid the gap is $10,369. On $8,000,000 of work it’s about $140,000 a year of profit you planned and never earned.

Two things often sit on top of the price rather than in the markup, because they’re charged on the contract value: bond premium and any insurance or fee your contract prices as a percentage of the total. Calculate them on the final price, after markup.

What happens when volume drops

Overhead is mostly fixed over a year, so the overhead rate moves with volume. If the $720,000 is spread over less work, every job has to carry more of it:

Required markup at different annual revenue volumesWith 720,000 dollars of fixed annual overhead and a 5 percent profit target, the markup needed on direct cost is 20.5 percent at 6 million dollars of revenue, 18.0 percent at 7 million, 16.3 percent at 8 million, 14.9 percent at 9 million and 13.9 percent at 10 million.20.5%18.0%16.3%14.9%13.9%$6M$7M$8M PLAN$9M$10MMARKUP NEEDED · $720K OVERHEAD · 5% PROFITANNUAL REVENUE VOLUME
The same overhead over less work needs a bigger markup. Illustrative.
Revenue Overhead rate Margin needed (+5% profit) Markup on cost
$6,000,000 12.0% 17.0% 20.5%
$7,000,000 10.3% 15.3% 18.0%
$8,000,000 9.0% 14.0% 16.3%
$9,000,000 8.0% 13.0% 14.9%
$10,000,000 7.2% 12.2% 13.9%

That table is the argument for checking overhead recovery every month. If you’re tracking to $6,000,000 while bidding at a markup built for $8,000,000, you’re under-recovering overhead by about 3 points of revenue, roughly $180,000 over the year, on top of any job that fades. The fix is one of three things: win more work at the same markup, raise markup where the market will bear it, or cut overhead.

Step 5: Adjust per job, then check recovery monthly

The calculated markup is a floor for a typical job, not a rule for every bid. Small jobs consume more estimating and office time per dollar; large, simple jobs less. Risky scopes, tough owners and long durations deserve more. A deliberately thin markup to keep crews busy can make sense, but call it what it is: a job that won’t cover its share of overhead, which the rest of the year has to make up.

Then measure it. Each month compare overhead recovered (gross profit earned on jobs, from your WIP schedule) with actual overhead spent. If gross profit earned year to date doesn’t cover overhead year to date, the markup, the volume or the overhead is off, and you want to know in March, not December.

How os.construction handles it

The labor burden calculator builds the burdened labor rate that goes into direct cost, and the markup and margin calculator converts between the two. In the product, job budgets, committed cost and actual cost sit on the same cost codes (cost codes and budgets), labor posts with its burden (labor and burden in job cost), and Accounting’s financial reports show company overhead from the general ledger, so you can compare gross profit earned on jobs with what overhead actually cost. For how cost flows from estimate to WIP, see the construction cost reporting guide.

General information, not accounting or tax advice. Overhead budgets, allocation bases and pricing are business decisions; your CPA can help with allocation on government work. Sources: FAR 31.203, Indirect costs, FAR Part 31 contract cost principles.

FAQ

What is a good overhead and profit markup for construction?

There isn't a universal number, and a figure borrowed from someone else's company is a guess. The right markup is the one that recovers your overhead at the volume you can realistically win and leaves your target profit. Work it out from your own overhead budget and revenue forecast, then adjust for job size, risk and competition.

How do you calculate an overhead rate for a construction company?

Total the company overhead you expect for the year (office rent, office and executive salaries and burden, insurance not charged to jobs, accounting, IT, vehicles and other general and administrative costs) and divide by the revenue you expect to bill that year. $720,000 of overhead on $8,000,000 of revenue is a 9% overhead rate. Some contractors divide by direct cost or labor hours instead; whatever base you pick, apply it consistently.

What's the difference between markup and margin?

Markup is a percentage of cost; margin is a percentage of price. A 20% markup on $100 of cost gives a $120 price and $20 of gross profit, which is a 16.7% margin. To hit a target margin, divide cost by (1 − margin); to convert, markup = margin ÷ (1 − margin).

Should general conditions be in overhead or in direct cost?

Job-site costs that exist because of the project, such as the superintendent, site trailer, temporary utilities and project-specific insurance, are general conditions and belong in the estimate's direct cost. Company overhead is what you'd spend whether or not you won this job, and it's recovered through markup.

Do you mark up subcontractor costs the same as self-performed work?

Many contractors use a lower markup on subcontracts than on self-performed labor because the risk is different, but the overhead still has to be recovered somewhere. If you discount markup on subs, the remaining work has to carry more. Track realized markup by cost type so you can see whether the blend actually covers overhead.

Share this article

Written by

Charley Forey