Labor burden: the number behind every bid

A carpenter who earns $36 an hour costs you a lot more than $36 an hour. Labor burden is the gap, and if your estimate, your job cost and your T&M rates each use a different version of it, you're losing money in at least one of them. Here's how to build the number.

Charley Forey5 min readEstimatingJob costAccounting
On this page
  1. What goes into it
  2. A worked example
  3. Where the number has to agree
  4. What ships today

Every self-performing contractor has a number like this somewhere: “Our burden is 35%.” It’s in the estimating template. It’s in the T&M rate sheet. It may or may not be in the job cost system. Ask when it was last calculated and you’ll often get a shrug.

Labor burden is the cost of employing someone beyond their base wage: payroll taxes, workers’ comp, insurance, benefits and paid time that isn’t spent working. It’s one of the largest numbers in a labor-heavy estimate, and it changes every year whether you update it or not.

What goes into it

Burden has three layers.

Statutory costs. You pay these by law, on wages.

  • Social Security and Medicare (FICA). 7.65% of wages for the employer share: 6.2% Social Security up to an annual wage base, plus 1.45% Medicare with no cap.
  • Federal unemployment (FUTA). Charged on the first $7,000 of each employee’s wages per year. With the standard state credit, the effective rate is usually 0.6%, though it can be higher in states with outstanding federal loans.
  • State unemployment (SUTA). Rates and wage bases vary by state and by your own claims history.
  • Workers’ compensation. Priced per $100 of payroll by class code, then adjusted by your experience modification rate. In construction it’s often the largest single statutory item, and it varies enormously between a finish carpenter and an ironworker.

Insurance tied to payroll. General liability is frequently rated on payroll for contractors, and some umbrella and other policies follow. If your premiums move with payroll, they belong in burden.

Benefits and paid non-productive time. Health insurance, retirement contributions, and union fringes if you’re signatory. Plus holidays, vacation and sick time: hours you pay for that never hit a cost code. A worker paid for 2,080 hours who takes 80 hours of holiday and vacation costs you 2,080 hours of wages for 2,000 productive hours.

Rates changeWage bases, unemployment rates, workers’ comp rates and your experience mod change at least annually. Check current figures with your payroll provider, insurance broker and CPA. Nothing here is tax advice.

A worked example

Illustrative numbersOne carpenter, made-up rates chosen to show the method. Your rates will differ.
Component Basis Per hour
Base wage $36.00
FICA 7.65% of wage $2.75
FUTA and SUTA ~3.0% of wage, averaged over the year $1.08
Workers’ comp $6.00 per $100 of payroll $2.16
General liability 2.0% of payroll $0.72
Health insurance $9,360 a year ÷ 2,080 hours $4.50
Retirement 3% match $1.08
Paid holidays and vacation 80 hours off ÷ 2,000 productive hours = 4% $1.44
Burdened cost $49.73

That’s $13.73 of burden on $36.00 of wage, or 38.1%. Price this carpenter at $36 plus a 25% burden from an old template and every estimated hour is $4.73 short. On a job with 10,000 self-performed hours, that’s $47,300 that was never in the bid.

ONE BURDENED HOUR · ILLUSTRATIVEBASE WAGE $36.00STATUTORY $5.99BENEFITS + PTO $7.02INS $0.72= $49.73 / HR
Statutory: FICA, FUTA/SUTA, workers’ comp. Benefits and PTO: health, retirement, paid holidays and vacation.

Two subtleties catch people.

Burden isn’t flat across the year. FUTA, SUTA and the Social Security portion of FICA stop once wages pass their annual caps. Early in the year your real burden is higher; late in the year it’s lower. If job cost applies the actual payroll tax as it happens, a January job looks more expensive than an identical October job. Most contractors use an annualized burden rate in job cost to avoid that distortion, then true up the difference to overhead.

Burden is per trade, sometimes per person. Workers’ comp class codes vary by trade, union fringes vary by local, and benefits vary by employee. One company-wide percentage averages over all of that. If your crew mix changes, say more ironworkers and fewer laborers, the average is wrong even if every rate is right.

Overtime changes the math. An overtime hour pays 1.5 times the wage, and FICA applies to all of it. But many benefits are paid per hour worked, not per dollar, so they don’t grow with the premium. And in many states, workers’ comp premium is calculated on straight-time payroll, with the overtime premium excluded if your payroll records separate it. The result: burden as a percentage is usually lower on overtime hours, even though the hour costs more. If your job cost applies the straight-time burden percentage to overtime pay, it overstates the cost of the premium hours, and if your crew runs heavy overtime, your bid rates should reflect the mix.

Where the number has to agree

Burden shows up in three places, and they should use the same rates:

  1. The estimate. Burdened labor rates by trade or crew, current for the year the work will happen.
  2. Job cost. Labor posted to cost codes at burdened cost, so the job cost report compares like with like. If the estimate is burdened and job cost is raw wages, every labor line looks under budget until the burden true-up lands at month-end or year-end, and then it all fades at once.
  3. T&M and change order rates. A T&M rate sheet built on last year’s burden undercharges for every hour of extra work. The same goes for the labor portion of every change order you price.
Annual tune-upEvery January, rebuild burden by trade from actual prior-year payroll, current workers’ comp rates and your new experience mod, and current benefit costs. Update the estimating template, the job cost rate table and the T&M sheet the same day. Then check it at midyear.

Our labor burden calculator does this build-up in your browser with your own rates. For how burden flows into a priced change, see the change order calculator. Related glossary terms: job costing, certified payroll and prevailing wage, where fringe rules add their own layer; certified payroll and the WH-347 shows those rules in a worked week. Burden covers the direct cost of labor; company overhead is recovered separately, through the markup in how to calculate overhead and markup for a bid.

What ships today

In os.construction, approved timesheets flow into Accounting Payroll, which models union locals, prevailing wage rates and workers’ comp classes. Before a run is approved, you preview the labor and burden job cost lines it will post; posting the run puts labor and burden on the job by cost code. Month-end accruals and a standard-rate burden true-up keep job labor accurate between pay dates, and a voided check reverses its burden at the rate captured when the run was approved. One burden rate table shared by the estimate, T&M and change order pricing is still planned. If your burden number lives in three spreadsheets, start a free trial and run a pay period through it.

For where labor sits in an electrical subcontractor’s money flow today, from crew hours to union or prevailing wage payroll and job cost, see electrical contractor software.

Share this article

Written by

Charley Forey

Founder of os.construction. We're building the operating system for construction. Project Financials follows job money, and company Accounting covers the books and controls. AI agents remain planned. We write about how money and data actually move on a job, and we build in public.

Apply to the founding program →Start a free trial →
Keep readingAll articles →
Job cost

Direct vs indirect costs in construction: job cost, general conditions and overhead

Direct costs can be traced to a specific job or piece of work. Indirect costs support the work without belonging to one item: the job's general conditions and the company's overhead. Here is how to draw the line, how each gets recovered, a worked estimate and the coding mistakes that distort margins.

5 min read

Estimating

How to calculate construction overhead and markup for a bid

Your markup has one job: recover company overhead and leave the profit you planned. To set it, you need an annual overhead budget, a realistic revenue volume, a profit target, and the margin-to-markup conversion most estimators get wrong. Here's the method step by step, with a worked bid and what happens to the number when volume drops.

5 min read

Job cost

Construction job costing: how to set up cost codes

A cost code list decides what your job cost report can tell you. Too coarse and overruns hide; too fine and the field codes everything to the first line on the list. Here's how to structure codes and cost types, when to follow CSI MasterFormat and when to build your own, a worked tenant improvement budget, and the rules that keep coding clean.