A change order (CO) is a written amendment to a construction contract, signed by the owner and the contractor, that changes the scope of work, the contract sum, the contract time, or a mix of the three. On AIA contracts the standard form is G701. Once executed, the change becomes part of the contract and can be billed on the next pay application.
In the UK and most Commonwealth markets the same thing is called a variation or variation order. Under NEC4 contracts, a change to the Scope is handled as a compensation event. The mechanics differ, but the idea is the same: the contract is changed in writing, with price and time settled.
How it works
Most change orders follow the same path, whatever the contract form calls each step.
- Something changes. An RFI answer adds scope, the owner asks for an upgrade, a hidden condition turns up, or a drawing revision lands. The contractor logs it as a change event and gives any notice the contract requires.
- The contractor prices it. A potential change order collects sub quotes, self-performed labor, material, equipment and the markup the contract allows, plus any time impact in days.
- The proposal goes to the owner. Often called a change order request (COR) or change proposal, with backup attached.
- The parties agree and sign. Under AIA A201 Article 7, a change order is made when the owner, contractor and architect all agree. G701 records the description of the change, the adjustment to the contract sum (or GMP) and the adjustment to contract time.
- The contract value moves. The executed amount is added to the schedule of values as a new line and billed on the pay application as the work is done. The contractor issues matching subcontract change orders and budget changes on the cost side.
If the owner needs the work started before price is agreed, it issues a construction change directive (AIA G714) instead. If the change is minor and doesn’t touch price or time, the architect can issue it alone as an ASI (G710).
Change order vs CCD vs ASI vs field order
| Instrument | AIA form | Who signs | Price and time | Typical use |
|---|---|---|---|---|
| Change order | G701 | Owner, contractor, architect | Agreed and fixed | Any agreed change to scope, sum or time |
| Construction change directive | G714 | Owner and architect (contractor signs only if it agrees) | Not yet agreed; settled later | Work must start before pricing is settled |
| Architect’s supplemental instructions | G710 | Architect | No change | Minor changes consistent with the contract intent |
| Field order | None standard | Owner’s rep or architect, per contract | Usually none, or priced later | Quick field direction; converted to a CO if it costs money |
A constructive change is the informal version: direction or conduct that changes the work without a change order. Federal contracts deal with it in the Changes clause (FAR 52.243-4), which treats such an order as a change only if the contractor gives written notice, and bars recovery of costs incurred more than 20 days before that notice.
Why it matters
A change order is where extra work turns into revenue. Work done on verbal direction without an executed CO is unbilled, sometimes unbillable, and a common source of under-billing and margin fade. The CO also sets the time adjustment. A change order that shows zero days, or says nothing about time, can be read as giving up a later delay claim for the same change.
Change orders flow down. The owner CO usually drives subcontract change orders, purchase order changes and budget revisions. If those don’t move together, the job’s revenue and cost forecasts disagree, and the WIP schedule looks better or worse than the job really is.
To keep every change order visible from the first request to the pay app it is billed on, use the free change order log template for Excel. It keeps a running revised contract and flags approved changes that have not been billed or passed to the sub.
Worked example
Illustrative, using the Riverside Medical Center sample project:
| Line | Amount |
|---|---|
| Original contract sum | $48,200,000 |
| Net change by previous change orders (#1-13) | $1,013,600 |
| Contract sum before this change order | $49,213,600 |
| CO #14: add fire dampers per RFI-212 | $86,400 |
| New contract sum | $49,300,000 |
| Contract time change | +4 days |
The $86,400 is built from the mechanical sub’s quote, the GC’s own labor for access and patching, and the contract’s markup on each. The GC issues a matching subcontract change order to the mechanical sub, the budget for the fire protection cost code moves by the cost amount, and CO #14 becomes a new line on the G703. It is billed on Pay App #9 as the dampers go in. You can check the markup math with the change order calculator.
Common mistakes
- Starting work before anything is signed. If the owner won’t sign a CO yet, ask for a CCD or written direction, and give the contract’s notice.
- Leaving time off the CO. Price the schedule impact, or reserve the right to claim time in writing on the form.
- Missing notice deadlines. Many contracts bar claims not raised in writing within a set number of days. A201-2017 uses 21 days for claims; federal and owner forms vary.
- Thin backup. A lump number with no breakdown invites a long negotiation and a lower number.
- Forgetting the cost side. No matching sub CO or budget change means the forecast is wrong the day the CO is signed.
- Signing a CO that releases more than it should. Some owner forms add waiver language covering all impacts of the change, including cumulative delay. Read it before signing.
This is general information, not legal advice. Change rules and notice deadlines depend on the contract form and jurisdiction.
For a line-by-line pricing example from burdened labor to bond, see how to price a change order.
How os.construction handles it
In the app, a change event can name its origin RFI and carry line items by cost code. From it you create a potential change order against the prime contract or a subcontract or PO, submit it for review, then approve and execute it, alone or grouped into a change order package. A project can use one, two or three tiers. Approved owner changes appear in the budget’s approved changes, and executed ones flow into owner billing on pay apps. See Commitments and change orders, the explainer life of a change order and the change order software overview.
Watch the explainer · 2:00
ASI vs field order vs CCD vs change order
- 0:00Four change documents
- 0:14ASI (AIA G710)
- 0:35Field order (EJCDC)
- 0:53CCD (AIA G714)
- 1:13Change order (AIA G701)
- 1:30Recap
- 1:41One change chain
Read the transcript
Four documents can change what gets built on a job: the ASI, the field order, the construction change directive and the change order. They differ in who issues them, and whether the price or the schedule moves.
An architect's supplemental instruction, or ASI, comes from the architect. On AIA contracts it's form G710. It clarifies the documents or orders a minor change, with no change to the contract sum or time. If you think it does cost money or time, say so in writing before you proceed.
A field order plays the same role on many engineering contracts. Under EJCDC general conditions, the engineer issues it for a minor change with no change in price or times. Some owners use the term loosely, for work directed now and priced later, so read how your contract defines it.
A construction change directive, or CCD, is for real changes when the price isn't agreed yet. The owner and architect sign it, AIA form G714, and the contractor proceeds. The price is settled later, often from documented time and materials, so track that cost on its own code.
A change order is the agreement itself. The owner, contractor and architect sign it, AIA form G701, and it adjusts the contract sum, the contract time, or both. A CCD usually ends up as a change order once the price is settled.
So, ASI and field order: minor, with no price or time change. CCD: do the work now, settle the price later. Change order: the signed change to price or time.
In os.construction, a potential change starts as a change event, linked to the RFI behind it, gathers pricing and T&M tickets, and carries through to a change order on the same project record.
Video page with chaptersMore in Construction concepts explained
Watch the explainer · 1:54
Change event vs change order
- 0:00A maybe vs a contract
- 0:18Log the event early
- 0:37Protect the notice clock
- 0:54Price it on one contract
- 1:11One change, several numbers
- 1:31Changes in os.construction
Read the transcript
A change event is a maybe. A change order is a contract. The change event records that something may change cost, scope or time. The change order is the signed amendment that fixes the price and time. Many events never become change orders.
Log the change event the day it shows up: an RFI answer that adds work, an owner request, a hidden condition. Mark the scope as in, out, or to be determined, and enter a rough order of magnitude, or ROM, by cost code. It's an early estimate, not a price.
If it may be a change or a claim, give written notice within the contract's deadline. The AIA A201-2017 general conditions use twenty-one days for claims, and your contract may be shorter. Logging the event early keeps you inside that window, while the record is fresh.
Next, get quotes from the subs, then create a potential change order, or PCO, against one contract. A PCO on the prime contract carries the revenue side. One on the subcontract carries the cost side. The PCO is where markup is added.
Here's an illustrative change. The event's ROM is four thousand eight hundred fifty dollars. The awarded quote comes in at five thousand three hundred. The PCO adds ten percent markup, for five thousand eight hundred thirty. Only once it's approved and executed does the contract change, and only then can you bill it.
In os.construction, quotes and PCOs made from a change event link back to it, and approved PCOs are executed in packages. Pending prime PCOs show as pending changes in the budget, approved ones as approved changes, and executed ones land on line two of the pay app.
Video page with chaptersMore in Construction concepts explained
FAQ
What is a change order in construction?
A change order is a written amendment to a construction contract, signed by the owner and contractor (and the architect on AIA contracts), that changes the scope of work, the contract sum, the contract time, or any combination. Once it is executed, the new amount becomes part of the contract and can be billed.
What is the difference between a change order and a construction change directive?
A change order records a change that the owner and contractor have both agreed to, including price and time. A construction change directive (AIA G714) is an owner order to proceed with a change before price or time is agreed. The contractor must do the work, and the adjustment is settled later. If the contractor signs a CCD agreeing to its terms, it becomes a change order.
Who signs a change order?
Under the AIA family, the G701 Change Order form has signature lines for the owner, the architect and the contractor, and A201 treats a change order as agreed only when all three sign. Other contract forms may need only owner and contractor signatures. The contract says who has authority, and a signature from someone without that authority can be challenged.
What is a variation order?
Variation, or variation order, is the UK and Commonwealth term for a change order. Under JCT contracts a variation is instructed in writing by the architect or contract administrator. Under the NEC4 Engineering and Construction Contract, an instruction changing the Scope is one of the compensation events listed in clause 60.1, which also handles time and money.
Can a contractor refuse to do change order work?
Under most US contracts the owner can order changes within the general scope of the contract and the contractor must proceed, often through a construction change directive while the price is disputed. The contractor keeps its right to an adjustment by giving the notice the contract requires. Work well outside the general scope is a different matter. Check the contract and get legal advice for disputes.
How much markup is allowed on a change order?
Whatever the contract says. Many contracts set overhead and profit percentages for self-performed work and for subcontracted work, sometimes with limits on tiers of subs. Some reduce or drop markup on deductive changes. If the contract is silent, markup is negotiated, and the backup should show labor, material, equipment, subcontract and markup separately.


