Construction concepts explained · 1:54

Change event vs change order

A change event is a maybe and a change order is a contract: log the event early, price it as a PCO, and bill it only once executed.

Published · Illustrative examples · Watch on YouTube

Diagram from this explainer

A change event records that cost, scope or time may change, with a rough estimate and no signature. A change order is the signed contract amendment that fixes price and time.
A maybe vs a contract. Free to share with a link to this page: 1200×630 · 1080×1350

Chapters

  1. 0:00 A maybe vs a contract
  2. 0:18 Log the event early
  3. 0:37 Protect the notice clock
  4. 0:54 Price it on one contract
  5. 1:11 One change, several numbers
  6. 1:31 Changes in os.construction

Video transcript

A change event is a maybe. A change order is a contract. The change event records that something may change cost, scope or time. The change order is the signed amendment that fixes the price and time. Many events never become change orders.

Log the change event the day it shows up: an RFI answer that adds work, an owner request, a hidden condition. Mark the scope as in, out, or to be determined, and enter a rough order of magnitude, or ROM, by cost code. It's an early estimate, not a price.

If it may be a change or a claim, give written notice within the contract's deadline. The AIA A201-2017 general conditions use twenty-one days for claims, and your contract may be shorter. Logging the event early keeps you inside that window, while the record is fresh.

Next, get quotes from the subs, then create a potential change order, or PCO, against one contract. A PCO on the prime contract carries the revenue side. One on the subcontract carries the cost side. The PCO is where markup is added.

Here's an illustrative change. The event's ROM is four thousand eight hundred fifty dollars. The awarded quote comes in at five thousand three hundred. The PCO adds ten percent markup, for five thousand eight hundred thirty. Only once it's approved and executed does the contract change, and only then can you bill it.

In os.construction, quotes and PCOs made from a change event link back to it, and approved PCOs are executed in packages. Pending prime PCOs show as pending changes in the budget, approved ones as approved changes, and executed ones land on line two of the pay app.