How a change order is priced

Fifteen lines, from a carpenter’s base wage to the number the owner signs. Step through how burdened labor, material, equipment and sub quotes become direct cost, how overhead and profit, sub markup, insurance and bond stack on top, and why the same markup dollars read as a smaller margin.

Visual guide8 min read

The short answer

How is a change order priced?

A change order price is direct cost plus the markups the contract allows, applied in the order the contract sets. Direct cost is labor at the fully burdened rate, material with tax, equipment and subcontractor quotes. On top go overhead and profit on your own work, a smaller markup on sub work, then insurance and bond.

Owners review change orders line by line, so the price has to come apart the same way. Step through an illustrative storage-room change below, the same one priced in how to price a change order.

Step by step

From a base wage to a signed number

Step 8 of 8: Bond on everything before it

Change order price built as a waterfall from direct cost through each markup to the totalCarpenter labor, base wage: $1,520.00 (40 h × $38.00). Labor burden, 45%: $684.00 ($1,520.00 × 45%). Frame, door, hardware: $1,850.00 (quote). Sales tax on material, 7%: $129.50 ($1,850.00 × 7%). Scissor lift, 1 week: $425.00 (rental). Self-performed cost: $4,608.50. Drywall sub: $6,400.00 (quote). Electrical sub: $2,150.00 (quote). Direct cost: $13,158.50. Overhead, 10% of self-performed: $460.85 ($4,608.50 × 10%). Profit, 5% of self-performed: $230.43 ($4,608.50 × 5%). GC markup on subs, 5%: $427.50 ($8,550.00 × 5%). Insurance, 1%: $142.77 ($14,277.28 × 1%). Bond, 0.8%: $115.36 ($14,420.05 × 0.8%). Change order total: $14,535.41. Markups add $1,376.91: 10.46% of direct cost, a 9.47% margin on the price.LINERUNNING TOTAL, TO SCALEAMOUNTCarpenter labor, base wage$1,520.00Labor burden, 45%$684.00Frame, door, hardware$1,850.00Sales tax on material, 7%$129.50Scissor lift, 1 week$425.00Self-performed cost$4,608.50Drywall sub$6,400.00Electrical sub$2,150.00Direct cost$13,158.50Overhead, 10% of self-performed$460.85Profit, 5% of self-performed$230.43GC markup on subs, 5%$427.50Insurance, 1%$142.77Bond, 0.8%$115.36Change order total$14,535.41Markups $1,376.91 = 10.46% of direct cost (markup)9.47% of the price (margin)
Read the markup dollars as
Running total
$14,535.41
Markups so far
$1,376.91
Markup on $13,158.50 cost
10.46%
  1. 40 carpenter hours at a $38.00 base wage is $1,520.00. Labor burden of 45% (payroll taxes, workers’ compensation, insurance and benefits) adds $684.00, so the labor line is $2,204.00: 40 h × $38.00 × 1.45. Price at the base wage and that $684.00 is simply lost.

  2. The frame, door and hardware quote is $1,850.00. Sales tax at 7% adds $129.50, so material costs $1,979.50. Whether and how tax applies to material on a construction contract depends on the state and the contract, so check it.

  3. A scissor lift for a week adds $425.00. That completes the self-performed direct cost: $2,204.00 labor + $1,979.50 material + $425.00 equipment = $4,608.50.

  4. The drywall sub quotes $6,400.00 and the electrical sub $2,150.00, $8,550.00 in all. Each quote already includes the sub’s own overhead and profit. Direct cost for the change is $4,608.50 + $8,550.00 = $13,158.50.

  5. This contract allows 10% overhead and 5% profit on self-performed cost, each on cost and not compounded: $460.85 + $230.43 = $691.28, both figured on $4,608.50.

  6. The GC gets 5% on subcontract cost: $8,550.00 × 5% = $427.50. The rate is lower because the sub’s markup is already inside its quote. The running total is now $14,277.28.

  7. Insurance at 1% applies to everything so far: $14,277.28 × 1% = $142.77, for $14,420.05.

  8. Bond comes last because premiums are usually charged on total contract value: $14,420.05 × 0.8% = $115.36. The change order total is $14,535.41. Markups added $1,376.91 to $13,158.50 of direct cost.

Illustrative change. Choose a step, use Previous and Next, or press Play to stack the layers; switch between markup and margin to see the same $1,376.91 divided by cost or by price. Bars are to scale, so the small markups are thin. The rates are example contract terms, not industry standards.
Worked example

The markups, in the contract’s order

Each markup sits on the base the contract names, and the order matters for the last two. Here the contract allows 10% overhead and 5% profit on self-performed cost (not compounded), 5% on subcontract cost, 1% insurance and 0.8% bond.

Labor          = hours × base wage × (1 + burden %)  = 40 × $38.00 × 1.45 = $2,204.00
Direct cost    = self-performed + subcontracts        = $4,608.50 + $8,550.00 = $13,158.50
OH&P           = self-performed × (10% + 5%)          = $460.85 + $230.43
Insurance      = running total × 1%                   = $14,277.28 × 1% = $142.77
Bond           = running total × 0.8%                 = $14,420.05 × 0.8% = $115.36
Illustrative storage-room change · markups in order
LineCalculationAmountRunning total
Self-performed cost$2,204.00 + $1,979.50 + $425.00$4,608.50$4,608.50
Overhead, 10%$4,608.50 × 10%$460.85$5,069.35
Profit, 5%$4,608.50 × 5%$230.43$5,299.78
Subcontract cost$6,400.00 + $2,150.00$8,550.00$13,849.78
GC markup on subs, 5%$8,550.00 × 5%$427.50$14,277.28
Insurance, 1%$14,277.28 × 1%$142.77$14,420.05
Bond, 0.8%$14,420.05 × 0.8%$115.36$14,535.41
Change order totaldirect $13,158.50 + markups $1,376.91$14,535.41

Read the result the way a reviewer would. The labor line carries its burden, so nothing is missing from cost. The sub quotes get 5%, not 15%, because their own markup is already inside. And superintendent time and general conditions are not separate lines, because on this contract the overhead percentage covers them. If your contract lets you price supervision on changes, it goes in as its own line with hours and a rate.

The change order markup calculator runs the same stack on your own lines, and the labor burden calculator works out the burden percentage from your payroll costs.

Markup vs margin

Same dollars, two percentages

Markup divides the added dollars by cost; margin divides them by price. The $1,376.91 of markups in the example is 10.46% of the $13,158.50 direct cost, and 9.47% of the $14,535.41 price. Neither is wrong; they answer different questions.

Markup          = added dollars ÷ cost
Margin          = added dollars ÷ price
Margin          = markup ÷ (1 + markup)
10% markup     = 9.09% margin
15% markup     = 13.04% margin
20% markup     = 16.67% margin
  • Contracts state change order markups on cost. “10% overhead and 5% profit” means percentages of the cost base, so price the change with markup.
  • Your company reads results as margin. The income statement, the WIP schedule and your surety all read gross profit as a share of revenue. The 15% overhead and profit on self-performed work here is only a 13.04% margin on that work.
  • Compounding is a contract question. If the contract allowed profit on cost plus overhead, profit would be $5,069.35 × 5% = $253.47, $23.04 more. Small on one change, real across a job’s worth of them. Match the contract’s wording.

The markup vs margin calculator converts either way, and the pricing mistake hiding in your change orders shows what using one in place of the other costs.

In os.construction change order software, a change event records the change and its rough cost by cost code. A potential change order created from it copies the line items (cost code, quantity, unit cost and amount) against the prime contract or a subcontract, with a grand total that includes any markup and tax on the lines, and a schedule impact in days. See change orders in the docs.

FAQ

Common questions

How is a change order priced?

Price the direct cost line by line: labor at the fully burdened rate, material with tax and delivery, equipment, and subcontractor quotes. Then apply the markups the contract allows, in the order it sets: commonly overhead and profit on self-performed cost, a lower markup on subcontract cost, then insurance and bond on the running total. Add any time impact and attach the backup.

What markup is allowed on a change order?

Whatever the contract’s changes clause says. Many contracts state a percentage for overhead and profit on the contractor’s own work and a lower percentage on subcontracted work, sometimes tiered by the size of the change. The rates on this page (10% overhead, 5% profit, 5% on subs, 1% insurance, 0.8% bond) are illustrative, not industry standards.

What is the difference between markup and margin on a change order?

Markup is profit divided by cost; margin is profit divided by price. The same dollars give a smaller percentage as margin, because price is the bigger number. In the example, $1,376.91 of markups is 10.46% of the $13,158.50 direct cost but 9.47% of the $14,535.41 price. Contracts state change order markups on cost, so apply them as markups.

Why does a GC get a lower markup on subcontractor work?

A subcontractor’s quote already includes its own overhead and profit, so a second full markup would charge the owner twice for the same kind of cost. The GC’s markup on sub work covers its coordination, supervision and risk, which is why contracts usually allow a smaller percentage on it.

Are insurance and bond added before or after markup?

The contract decides. A common order adds them last: insurance on the subtotal including markups, then bond on everything before it, because bond premiums are usually charged on total contract value. Some contracts fold insurance and bond into the overhead percentage instead, in which case adding them again would be double counting.

Keep going

Sources and further reading

  • AIA contract documents: A201 General Conditions, Article 7, sets out how changes in the work are made and priced, including allowances for overhead and profit.
  • FAR 52.243-4: the changes clause in federal construction contracts, and how equitable adjustments are requested.
  • How to price a change order: the same worked example as a step-by-step guide, with common mistakes.

General information only. Every figure on this page is illustrative.

Want this on live job data?

In os.construction, a change event records the change by cost code, and a potential change order copies its line items with a grand total that includes markup and tax on the lines, plus the schedule impact in days.

Your role (optional)

14-day free trial. Pricing for paid plans isn't set yet. Talk to us. Already have an account? Sign in →

General information, not legal or estimating advice. The change and every figure on this page are illustrative. Your contract’s changes clause decides what counts as cost, which markups apply, in what order, and what backup is required.