Esc

↑↓ move↵ openIndex · Pagefind
Analytics

Cost-to-complete

Definition

The estimated remaining cost to finish a job, based on remaining commitments, remaining labor and known risks, not just budget minus actuals.

Part of: Construction cost reporting: accruals, earned revenue, EAC and WIP

Topic: Accounting & WIP

Updated

Cost-to-complete (CTC) is the PM’s forecast of what it will still cost to finish the job. Done properly, it’s built bottom-up by cost code: remaining subcontract and PO commitments, remaining self-performed labor and material at realistic productivity, pending changes and known risks. It is not simply the remaining budget.

How it works

  1. Start from posted cost. Cost to date by cost code, through the period cutoff, with late invoices and timecards accrued.
  2. Subcontracts and POs. Remaining commitment value (committed minus invoiced), plus any pending sub change orders and known back charges.
  3. Self-performed work. Remaining quantity or hours times a realistic unit rate. Use the productivity the crew is actually achieving, with labor burden included.
  4. Time-driven costs. General conditions for the remaining duration from the current schedule, not the original one.
  5. Changes and risk. Likely but unpriced change events, and specific risks the PM can name.
  6. Total it. CTC plus cost to date gives estimate at completion, which sets percent complete and projected margin on the WIP schedule.

Why it matters

CTC is the most important estimate a contractor makes after the bid. It sets estimated total cost, which sets percent complete, earned revenue and profit. A CTC that just assumes “the remaining budget will be enough” is how jobs fade quietly for months and then drop margin all at once near the end.

Worked example

Illustrative: Riverside Medical Center’s estimated total cost is $43.68M and cost to date is $31.7M, so CTC is $11.98M.

Now Volt Electric (26 Electrical) is trending 4% over budget. If that code’s remaining budget was $2.5M, a realistic CTC on that line is closer to $2.6M. That extra $100,000 raises total cost and lowers projected margin. Updating CTC now shows it; leaving it as remaining budget hides it.

A full bottom-up review goes through every line. With a sample split of the $11.98M remaining budget:

Cost group Remaining budget Bottom-up CTC Basis
Electrical subcontract $2.50M $2.60M Trending 4% over
Mechanical subcontract $3.10M $3.10M Open commitment, no changes
Other subcontracts $2.60M $2.65M $50,000 pending drywall change
Self-performed labor $1.20M $1.33M 14,000 hours × $95 burdened
Materials $0.90M $0.90M Remaining POs
General conditions $1.68M $1.82M 2 extra weeks × $70,000
Total $11.98M $12.40M

Estimate at completion becomes $31.7M + $12.40M = $44.10M. Projected gross profit falls to $49.3M − $44.10M = $5.20M, a 10.5% margin instead of 11.4%. The $420,000 difference existed either way; the review just moved its discovery forward.

Ways to estimate what’s left

Method Formula or basis When it fits
Remaining budget Budget − cost to date Only when the line is tracking to budget
Earned value, to plan Budget at completion − earned value Remaining work expected to go to plan
Earned value, current efficiency (BAC − EV) ÷ CPI Current cost performance expected to continue
Committed Committed − invoiced Fixed-price subcontracts and POs with no open changes
Bottom-up Fresh estimate of remaining quantities and rates Self-performed work, troubled lines, late-stage jobs

Most contractors mix them: committed values for subs, bottom-up for self-performed work, and a performance-based check on large lines to test whether the bottom-up number is believable.

Common mistakes

  • Setting CTC equal to remaining budget on every line.
  • Forgetting open commitments that haven’t been invoiced yet.
  • Not including costs for pending change events that are likely but unpriced.
  • Forecasting general conditions from the original duration after the schedule has slipped.
  • Using bid productivity for self-performed labor when the crew has been running below it for months.
  • Leaving a negative CTC on a line that’s already over budget, which quietly assumes money will come back.
  • Letting the person whose bonus depends on the margin set CTC with no review.

When the forecast moves, the effect on margin is margin fade or gain, and it should be explained line by line.

For the full review, line by line with a margin bridge, see how to run a cost-to-complete review.

How os.construction handles it

On the Budget’s Forecast tab, the PM can override forecast to complete on any cost code line. In Accounting, the Job Cost Forecast app takes a dated forecast per cost code (manual cost to complete, physical percent complete, unit rate or budget), and a different person approves it before it feeds the WIP. AI suggestions are planned, as part of the agents work.

Watch the explainer · 1:57

How to read a construction cost report

  1. 0:00One row per cost code
  2. 0:14Budget and committed cost
  3. 0:32Cost to date and accruals
  4. 0:48Cost to complete and EAC
  5. 1:11From EAC to earned revenue
  6. 1:34The cost report in os.construction
Read the transcript

A construction cost report tells you what a job will cost when it's done. It has one row per cost code, and its bottom line, the estimate at completion, drives almost every other number in construction finance.

Read it left to right. Original budget plus approved changes is the revised budget. Committed cost is signed subcontracts and purchase orders, and it's the early warning column. On this illustrative job, HVAC commitments already run above the HVAC budget, months before cost to date showed it.

Cost to date means cost incurred, not just invoiced: posted invoices, payroll and equipment, plus accruals for work in place that hasn't been billed yet. Without the accrual, cost to date is understated until the invoice lands.

Cost to complete is the project manager's forecast of what's left. Cost to date plus cost to complete is the estimate at completion. Here, eight point three million spent, plus three point five million to go, is an EAC of eleven point eight million. Against an eleven point three four million revised budget, that's a four hundred sixty thousand dollar overrun.

The EAC then drives revenue. Percent complete is cost to date divided by EAC, about seventy percent. Times the twelve point six million dollar contract, that's about eight point eight six million earned. With nine point one five million billed, the job is over billed by about two hundred eighty-seven thousand. A stale cost to complete changes all of it.

In os.construction, the Budget tool is the cost report: budget, commitments, cost and forecast to complete by cost code, with month-end snapshots. Accounting builds a WIP snapshot from posted job cost, billings and approved forecasts, reviewed before it posts.

Watch the explainer · 1:55

Cost-to-cost percent complete: when it lies

  1. 0:00One formula, one assumption
  2. 0:21An illustrative job
  3. 0:37Material bought, not installed
  4. 0:56A stale cost to complete
  5. 1:16Get a second opinion
  6. 1:37Percent complete in os.construction
Read the transcript

Most contractors measure percent complete with the cost-to-cost method: cost to date divided by estimated total cost. It's simple, and auditors know it. It also assumes every dollar spent is the same amount of progress. When that isn't true, earned revenue and over and under billing are wrong too.

Take an illustrative job: a ten million dollar contract with nine million dollars of estimated cost, a ten percent margin. With three point six million dollars spent, the job is forty percent complete, and you've earned four million dollars of revenue.

Now the mechanical sub buys six hundred thousand dollars of rooftop units early. The invoice posts, and cost to date jumps to four point two million. Percent complete jumps to about forty-seven percent, and about six hundred sixty-seven thousand dollars more revenue is recognized for equipment sitting in a warehouse.

The bigger risk is the forecast. Later, five point four million is spent. If the cost to complete still says three point six million, the job looks sixty percent complete with a ten percent margin. An honest forecast of four point three million makes it about fifty-six percent, with a three percent margin.

Unaccrued costs, rework and miscoded invoices distort it too. The fix is a cross-check. Compare cost-to-cost with the field's physical percent complete and with billing, and ask why when they spread apart. Uninstalled materials can be tracked separately, and your accountant sets the policy for leaving them out.

In os.construction, the WIP app computes each job's snapshot from posted job costs, the approved cost-to-complete forecast and billings, so you can review the evidence before you post it.

FAQ

How do you calculate cost to complete?

Build it by cost code. For subcontracts and purchase orders, take the remaining committed value plus expected changes. For self-performed work, multiply remaining quantities or hours by realistic rates. Add general conditions for the remaining duration and an allowance for known risks and likely changes. The total is cost to complete.

What's the difference between cost to complete and estimate at completion?

Cost to complete is what's left to spend. Estimate at completion is the forecast total: cost to date plus cost to complete. A change in cost to complete changes estimate at completion by the same amount.

Is cost to complete the same as remaining budget?

Only if the job is performing exactly to budget. Remaining budget is budget minus cost to date. Cost to complete is a fresh forecast of what the remaining work will cost, and it should differ from remaining budget whenever productivity, prices, scope or schedule have moved.

What are the earned value formulas for estimate to complete?

In earned value management, a simple estimate to complete is budget at completion minus earned value, which assumes remaining work goes to plan. A performance-based version divides that by the cost performance index, assuming current efficiency continues. Bottom-up estimates replace the formula with a fresh estimate of the remaining work.

How often should cost to complete be updated?

At least monthly, before the WIP schedule is prepared, because it sets percent complete and earned revenue. Large jobs and jobs with known problems are often reviewed more often, and any major change event should trigger an update.

Sources

Open file