Construction concepts explained · 1:57

How to read a construction cost report

Revised budget, committed cost, cost to date, cost to complete and EAC on one illustrative job, and how the EAC drives earned revenue.

Published · Illustrative examples · Watch on YouTube

Diagram from this explainer

8.30 million cost to date plus 3.50 million cost to complete is an 11.80 million estimate at completion, 460,000 over the 11.34 million revised budget
Cost to date + to complete = EAC. Free to share with a link to this page: 1200×630 · 1080×1350

Chapters

  1. 0:00 One row per cost code
  2. 0:14 Budget and committed cost
  3. 0:32 Cost to date and accruals
  4. 0:48 Cost to complete and EAC
  5. 1:11 From EAC to earned revenue
  6. 1:34 The cost report in os.construction

Video transcript

A construction cost report tells you what a job will cost when it's done. It has one row per cost code, and its bottom line, the estimate at completion, drives almost every other number in construction finance.

Read it left to right. Original budget plus approved changes is the revised budget. Committed cost is signed subcontracts and purchase orders, and it's the early warning column. On this illustrative job, HVAC commitments already run above the HVAC budget, months before cost to date showed it.

Cost to date means cost incurred, not just invoiced: posted invoices, payroll and equipment, plus accruals for work in place that hasn't been billed yet. Without the accrual, cost to date is understated until the invoice lands.

Cost to complete is the project manager's forecast of what's left. Cost to date plus cost to complete is the estimate at completion. Here, eight point three million spent, plus three point five million to go, is an EAC of eleven point eight million. Against an eleven point three four million revised budget, that's a four hundred sixty thousand dollar overrun.

The EAC then drives revenue. Percent complete is cost to date divided by EAC, about seventy percent. Times the twelve point six million dollar contract, that's about eight point eight six million earned. With nine point one five million billed, the job is over billed by about two hundred eighty-seven thousand. A stale cost to complete changes all of it.

In os.construction, the Budget tool is the cost report: budget, commitments, cost and forecast to complete by cost code, with month-end snapshots. Accounting builds a WIP snapshot from posted job cost, billings and approved forecasts, reviewed before it posts.