Esc

↑↓ move↵ openIndex · Pagefind
Accounting

Commitment

Definition

A contractual obligation to spend money, such as a subcontract or purchase order, tracked against the budget before any invoice arrives.

Part of: Construction cost reporting: accruals, earned revenue, EAC and WIP

Topic: Accounting & WIP

Updated

Budget, committed cost, invoiced cost and remaining commitmentA $2.30 million revised budget for the mechanical cost code. $2.15 million of it is committed: a $2.0 million subcontract plus $0.15 million of approved change orders, leaving $0.15 million uncommitted. Of the committed amount, $0.40 million has been invoiced and $1.75 million remains to be invoiced.REVISED BUDGET$2.30MCOMMITTED$2.0M + $0.15M COsINVOICED VS REMAINING$1.75M to comeInvoiced $0.40MRemaining commitment $1.75MUncommitted budget $0.15MLocked in: $2.15M, not $0.40M
Illustrative mechanical cost code: actuals show $400,000, but $2.15M is already committed and only $150,000 of budget is left to buy.

A commitment in construction is money you have agreed to spend on a job but haven’t been billed for yet. Subcontracts and purchase orders are the two common types. Committed cost is the original commitment plus approved commitment change orders; remaining commitment is committed cost minus what has been invoiced against it.

How it works

A commitment is born at buyout, when the estimate’s scope is turned into signed contracts with subs and suppliers. From then on it moves through four numbers, usually tracked by cost code:

  1. Original commitment. The signed value of the subcontract or purchase order, with its schedule of values or line items.
  2. Approved commitment changes. Commitment change orders (CCOs) add or deduct scope. Pending CCOs are tracked separately as exposure until they are approved.
  3. Invoiced to date. Each sub pay application or supplier invoice is billed against the commitment’s lines. Retainage withheld is still part of the invoiced amount.
  4. Remaining commitment. Committed cost − invoiced to date. This is cost you know is coming that isn’t in actuals yet.

On a cost report, commitments sit between the budget and actual columns. Revised budget − committed cost gives uncommitted budget: what is left to buy the rest of the scope. The forecast at completion should never be lower than actual cost plus remaining commitments, because those contracts are already signed.

Commitments also drive invoice control. When a bill arrives, it is checked against the commitment: does it exceed the remaining amount, does it match the received quantities on a PO (a three-way match), is the right retainage withheld?

Commitment vs actual cost vs accrual

These three numbers answer different questions, and a cost report usually shows all of them.

Commitment Actual cost Accrual
What it is Signed obligation to spend Cost invoiced, paid or posted Cost incurred but not yet invoiced
Source Subcontract or PO, plus approved changes Vendor invoices, payroll, direct costs Month-end estimate or PO receipt
In the general ledger? No, tracked in job cost Yes Yes, usually reversing next period
Main use Exposure and forecast Percent complete and WIP Getting cost into the right period

A commitment becomes actual cost as it is invoiced. If work is done before the invoice arrives, an accrual puts that cost in the right month, and the accrual reverses when the invoice posts. The commitment itself never hits the ledger; it is the ceiling the invoices are measured against.

Why it matters

Actual cost alone understates where a job is headed. If you’ve signed a $2M subcontract and only $400K has been billed, $1.6M or more of cost is already locked in. Tracking commitments is how you see an overrun at signing, not months later when the invoice shows up.

It also changes the cost-to-complete conversation. A PM forecasting from actuals has to guess at the rest. A PM forecasting from commitments only has to estimate what isn’t bought yet, plus any changes coming. That is why lenders and sureties trust a forecast more when the job is largely bought out.

Worked example

Illustrative: the mechanical cost code on Riverside Medical Center.

Line Amount
Revised budget, mechanical $2,300,000
Original subcontract $2,000,000
Approved commitment change orders $150,000
Committed cost $2,150,000
Uncommitted budget ($2,300,000 − $2,150,000) $150,000
Invoiced to date (three sub pay apps) $400,000
Remaining commitment ($2,150,000 − $400,000) $1,750,000

The actuals column shows $400,000, which looks like a job with $1.9M of room. The commitment view shows the truth: $2.15M is already locked in, and only $150,000 of budget is left for anything not yet bought, such as controls integration or test and balance.

Invoice control on the same job: PO-118 for medical gas fittings has a remaining commitment of $42,050. Invoice INV-4471 arrives for $48,200, exceeding the remaining commitment by $6,150. That gap is an unapproved change, a pricing error or an over-bill, and it should be resolved before the invoice is paid.

Common mistakes

  • Writing the PO after the invoice. Issuing work verbally and papering it later means the commitment never protects you.
  • Not updating for approved CCOs. Remaining commitment goes wrong, and so does every forecast that reads it.
  • Forecasting from actuals only. A cost-to-complete that ignores open commitments almost always understates the final cost.
  • Treating pending changes as zero. Pending CCOs are real exposure even before they are approved. Track them in their own column.
  • Coding a commitment to the wrong cost code. The budget line looks underspent while another overruns.
  • Leaving closed commitments open. A finished sub with a few dollars of remaining commitment keeps that amount in the forecast. Close it out once final billing and retainage are settled.

How os.construction handles it

The project Commitments tool holds subcontracts and purchase orders, each with a schedule of values, change orders and the invoices billed against it. Approved commitments and approved commitment change orders feed the Budget as Committed Costs; unapproved ones show as Pending Cost Changes. In company Accounting, Accounts Payable runs commitment and three-way matching when a bill is submitted, applies the over-commitment rule and re-matches at final approval. When a cost code has no PM forecast, the job cost forecast uses the greater of revised budget and actual plus remaining commitments. A commitment itself is not a posted expense. See Commitments and change orders.

FAQ

What is a commitment in construction?

A commitment is a signed contractual obligation to spend money on a job, usually a subcontract or a purchase order, tracked against the budget before the invoices arrive. It shows cost that is locked in even though it hasn't been billed.

How do you calculate remaining commitment?

Committed cost = original commitment + approved commitment change orders. Remaining commitment = committed cost − amount invoiced to date. Illustrative: a $2,000,000 subcontract with $150,000 of approved change orders is $2,150,000 committed; with $400,000 invoiced, $1,750,000 remains.

What is the difference between committed cost and actual cost?

Actual cost is what has been invoiced, paid or accrued so far. Committed cost is the full value of the subcontracts and purchase orders you've signed, billed or not. Forecasts that use only actual cost understate where a job will land.

Are commitments recorded in the general ledger?

Usually not as an expense. A commitment is tracked in job cost as an obligation against the budget. The cost reaches the ledger when the work is performed and invoiced or accrued, which is why commitments and actuals are reported in separate columns on a cost report.

What is uncommitted budget?

Uncommitted budget is the revised budget for a cost code minus its committed cost. It is the money still available to buy the remaining scope or self-perform it. A negative number means you have already signed more than the budget allows.

Sources

See it in the app

Commitment in os.construction

Track subcontracts and purchase orders as project commitments that feed committed cost in the budget (preview); a commitment is not itself a posted AP bill. Read the guide: Commitments.

  1. 1Subcontract or PO
  2. 2Commitment change order
  3. 3Committed cost
  4. 4Budget forecast

Try it on the sample project in a free trial.

Start free trial Sign in
Open file