Esc

↑↓ move↵ openIndex · Pagefind
Analytics

Cost report

Definition

A job report showing, by cost code, the original and revised budget, committed cost, actual cost, cost-to-complete, forecast and variance.

Part of: Construction cost reporting: accruals, earned revenue, EAC and WIP

Topic: Accounting & WIP

Updated

Reading one cost report lineCost code 26 Electrical. Revised budget $4.78M. Committed $4.971M, already past the budget line. Actual cost to date $2.69M plus cost to complete $2.281M gives a projected final cost of $4.971M, so the variance is $191k over, about 4 percent, visible in the committed column before actual cost shows it. Illustrative numbers.26 Electrical$ millionsbudget lineRevised budget4.780Committed4.971Actual + to complete4.971actual 2.690CTC 2.281Variance−$191krevised budget − projected finalCommitted is the early warning:the overrun is locked in before it's spent.
One line of a job cost report. Committed cost already exceeds the revised budget, so the PM can act before actual cost catches up. Illustrative.

A cost report (job cost report) shows a construction job’s financial position by cost code: original budget, approved changes, revised budget, committed cost, actual cost to date, cost to complete, projected final cost and variance. Project managers use it monthly to forecast the job, spot overruns early and feed the WIP schedule.

Good cost reports also show pending changes separately, so potential risk is visible without being booked. Cost reporting is where operations and accounting meet: accounting supplies actual cost, the PM supplies the forecast, and the report is only as good as both.

In plain English

A cost report is a job’s budget-versus-reality sheet, one row per type of work. Illustrative: the electrical line was budgeted at $4.78 million. The electrical subcontract plus its change orders already total $4.97 million. Nothing has gone wrong on the invoices yet, but the cost report shows the $191,200 overrun today, months before the last invoice would have revealed it. That early warning is the whole point of the report.

Types of construction cost reports

Report Who uses it What it answers
Job cost report (budget vs actual by cost code) PM, project accountant Where is this job over or under?
Cost-to-complete or forecast report PM, operations leader What will this job finally cost?
Committed cost report PM, purchasing How much of the budget is already contracted?
Anticipated cost report (anticipated final cost) Owner’s cost consultant, quantity surveyor What will the owner end up paying?
Cost value reconciliation (CVR) UK contractors Is value earned keeping up with cost?
WIP schedule Controller, CFO, surety Across all jobs, how much revenue and profit is earned?

Cost report columns explained

Column What it shows Source
Original budget The estimate as awarded Estimate / budget setup
Approved changes Approved budget changes and change orders Change orders, budget changes
Revised budget Original + approved changes Calculated
Pending changes Unapproved changes, shown but not booked Change events, PCOs
Committed Subcontracts and POs plus their approved changes Commitments
Actual to date Posted cost: AP, payroll, equipment, accruals Accounting
Cost to complete PM’s forecast of remaining cost PM
Projected final (EAC) Actual + cost to complete Calculated
Variance Revised budget − projected final Calculated

How to run a monthly cost review

  1. Close cost. Post the month’s invoices, payroll and accruals.
  2. Check commitments. Make sure every signed subcontract, PO and change is entered; a missing commitment hides an overrun.
  3. Forecast each line. Update cost to complete from remaining scope, not remaining budget.
  4. Explain variances. Any line that moved materially since last month gets a note: cause, recovery, owner.
  5. Review pending changes. Decide which will be recovered from the owner and which the job will absorb.
  6. Roll up. Projected final cost goes to the estimate at completion and the WIP report.

The free job cost report template for Excel is laid out for this review: budget, committed, cost to date, cost to complete, EAC and variance by cost code, with a flag on any line whose cost to complete is below its open commitments.

Formulas

  • Revised budget = original budget + approved changes
  • Projected final cost = actual to date + cost to complete, and for a bought-out line it’s normally no less than the committed amount plus uncommitted remaining cost
  • Variance = revised budget − projected final (negative is an overrun)
  • Uncommitted budget = revised budget − committed, a quick check on how much is still exposed

Worked example

Illustrative rows from a cost report on a $45M building:

Cost code Revised budget Committed Actual Cost to complete Projected final Variance
03 Concrete $2,460,000 $2,395,000 $2,250,000 $145,000 $2,395,000 +$65,000
09 Finishes $3,100,000 $2,650,000 $410,000 $2,690,000 $3,100,000 $0
26 Electrical $4,780,000 $4,971,200 $2,690,000 $2,281,200 $4,971,200 −$191,200
01 General conditions $2,050,000 $310,000 $1,420,000 $760,000 $2,180,000 −$130,000

Electrical: committed cost is already above the revised budget, so the $191,200 overrun (4% over) is locked in before actual cost shows it. The PM digs in now: is there a pending change to recover from the owner? General conditions: the job is running longer than planned, so remaining months of staff and site costs push the forecast $130,000 over even though most of it isn’t committed. Finishes: $450,000 is still uncommitted, so its zero variance is only as good as the remaining buyout.

Why it matters

The cost report is where the PM sees problems early enough to act. It’s the basis for the monthly forecast, which feeds the WIP schedule and the financial statements, and margin fade usually shows up here first. When cost reports are built by exporting accounting data to a spreadsheet and adding the PM’s notes by hand, they’re stale by the time they’re reviewed, and nobody fully trusts them.

Common mistakes

  • Reporting variance against original budget instead of revised budget.
  • Leaving cost-to-complete as remaining budget, which hides every overrun until it’s spent.
  • Missing commitments, so the committed column understates exposure.
  • Netting pending changes into the forecast without saying so.
  • Running cost reports quarterly on jobs that change weekly.

How os.construction handles it

In the project app, the Budget tool is the job cost report: per cost code and cost type it shows original budget, modifications, approved and pending budget changes, revised budget, committed costs, direct costs, pending cost changes, projected costs and projected over/under, with pending changes kept apart from approved numbers. The Forecast tab adds forecast to complete, which the PM can override per line, and estimated cost at completion. Monthly budget snapshots and the Variance tab give the trend. The project report uses project financial records such as direct costs and commitments; not all project activity posts to the company ledger automatically. In the Accounting module, the Job Cost app holds posted job cost. See Job cost reports and cost to complete, Budget and Job cost. The Budget, commitments and cost explainer shows how the columns connect.

Watch the explainer · 1:57

How to read a construction cost report

  1. 0:00One row per cost code
  2. 0:14Budget and committed cost
  3. 0:32Cost to date and accruals
  4. 0:48Cost to complete and EAC
  5. 1:11From EAC to earned revenue
  6. 1:34The cost report in os.construction
Read the transcript

A construction cost report tells you what a job will cost when it's done. It has one row per cost code, and its bottom line, the estimate at completion, drives almost every other number in construction finance.

Read it left to right. Original budget plus approved changes is the revised budget. Committed cost is signed subcontracts and purchase orders, and it's the early warning column. On this illustrative job, HVAC commitments already run above the HVAC budget, months before cost to date showed it.

Cost to date means cost incurred, not just invoiced: posted invoices, payroll and equipment, plus accruals for work in place that hasn't been billed yet. Without the accrual, cost to date is understated until the invoice lands.

Cost to complete is the project manager's forecast of what's left. Cost to date plus cost to complete is the estimate at completion. Here, eight point three million spent, plus three point five million to go, is an EAC of eleven point eight million. Against an eleven point three four million revised budget, that's a four hundred sixty thousand dollar overrun.

The EAC then drives revenue. Percent complete is cost to date divided by EAC, about seventy percent. Times the twelve point six million dollar contract, that's about eight point eight six million earned. With nine point one five million billed, the job is over billed by about two hundred eighty-seven thousand. A stale cost to complete changes all of it.

In os.construction, the Budget tool is the cost report: budget, commitments, cost and forecast to complete by cost code, with month-end snapshots. Accounting builds a WIP snapshot from posted job cost, billings and approved forecasts, reviewed before it posts.

FAQ

What is a cost report in construction?

A construction cost report, or job cost report, is the project manager's main financial view of a job. Each row is a cost code, and the columns show original budget, approved changes, revised budget, committed cost, actual cost to date, cost to complete, projected final cost and variance. It answers whether the job will finish on budget and where it won't.

What is the difference between committed cost and actual cost?

Committed cost is what you have contractually agreed to spend, through signed subcontracts and purchase orders plus their approved change orders. Actual cost is what has been incurred and recorded to date, such as posted invoices, payroll and accruals. Committed cost shows an overrun early; actual cost only shows it once the money is spent.

How often should a job cost report be reviewed?

At least monthly as part of the month-end close and WIP review, with the project manager updating cost to complete and explaining variances. On fast-moving jobs, many teams look at committed and actual cost weekly. Reviewing quarterly is usually too slow to act on what the report shows.

Should variance be measured against the original or revised budget?

Against the revised budget, which is the original budget plus approved changes. Measuring against the original budget mixes owner-approved scope changes with real overruns. Many reports show both, but decisions about performance should be based on revised budget versus projected final cost.

What is the difference between a cost report and a WIP report?

A cost report looks at one job by cost code: budget, committed, actual and forecast cost. A WIP report looks at every open job at the contract level: contract value, estimated total cost, percent complete, earned revenue, billings and over or under billing. The cost report's projected final cost feeds the WIP report's estimated total cost.

What is an anticipated cost report?

An anticipated cost report, common in UK, Commonwealth and Asian practice, is a cost report built around the anticipated final cost (AFC): cost to date plus the anticipated cost to complete, compared with the budget or the contract sum. It answers the same question as a US job cost report's projected final cost column. Owners' quantity surveyors often prepare one monthly for the client.

Sources

Open file