Estimate at completion (EAC) is the forecast total cost of a job when finished: cost to date plus estimated cost to complete. Compared with the revised budget, it shows the projected overrun or underrun; compared with the contract value, it shows projected gross profit. Under cost-to-cost, it also sets percent complete and earned revenue.
EAC is the number that ties field operations to the financial statements. Cost to date is fact (once accruals are in); cost to complete is judgment, and it should come from the project manager’s view of the remaining work, not from what’s left in the budget.
In plain English
Illustrative: you budgeted $1,000,000 to build a job you sold for $1,200,000. You have spent $600,000, and the PM walks the job and says it will take $500,000 more to finish. Your estimate at completion is $1,100,000: $100,000 over budget, and your expected profit has shrunk from $200,000 to $100,000. Note that “budget left” ($400,000) is not the answer; the remaining work is.
Formula
EAC = actual cost to date + estimate to complete (ETC)
From there:
- Projected gross profit = contract value (including approved change orders) − EAC
- Projected margin % = projected gross profit ÷ contract value
- Variance at completion = revised budget − EAC (negative is an overrun)
- Percent complete (cost-to-cost) = cost to date ÷ EAC
Earned value practice adds index-based cross-checks, useful when a bottom-up forecast looks optimistic:
| Method | Formula | Assumes |
|---|---|---|
| Bottom-up | AC + ETC (PM forecast by line) | The PM’s forecast of remaining work is right |
| Budget rate | AC + (BAC − EV) | Remaining work will go to budget |
| CPI-based | BAC ÷ CPI | Past cost efficiency continues |
| CPI × SPI | AC + (BAC − EV) ÷ (CPI × SPI) | Cost and schedule pressure both persist |
Here AC is actual cost, BAC is budget at completion, EV is earned value (physical percent complete × BAC) and CPI = EV ÷ AC.
How to build an EAC
- Close the month properly. Post costs and accruals so cost to date is complete.
- Start from commitments. For bought-out lines, remaining cost is at least the open commitment plus known pending changes.
- Forecast self-performed work. Remaining quantity × current unit cost (from actual productivity), not budget unit cost.
- Add risk. Pending changes the job will absorb, open risks, and a view on remaining contingency.
- Sum to EAC and compare with last month’s EAC; explain every material move.
- Sign off. The PM owns the forecast; the controller reviews it before the WIP report.
Worked example
Illustrative job:
| Item | Amount |
|---|---|
| Cost to date | $31,700,000 |
| Cost to complete (PM forecast) | $11,980,000 |
| EAC | $43,680,000 |
| Contract, including $1.1M approved change orders | $49,300,000 |
| Projected gross profit | $5,620,000 |
| Projected margin | 11.4% |
| Percent complete (31.7 ÷ 43.68) | 72.6% |
A change order is already in those numbers: it added $86,400 to the contract and $78,100 of cost to EAC, so it added $8,300 of gross profit. Had it gone into the contract without its cost, EAC would read $43,601,900 and margin would look $78,100 better than it is. Both sides have to move together, or the forecast is wrong.
Cross-check. Suppose the revised budget (BAC) is $43,200,000 and the team assesses physical progress at 71%. Earned value = 0.71 × $43.2M = $30,672,000; CPI = $30.672M ÷ $31.7M = 0.968. A CPI-based EAC = $43.2M ÷ 0.968 ≈ $44.65M, about $970,000 above the bottom-up figure. That gap doesn’t prove the PM is wrong, but it’s the question to ask: what will make the remaining work more efficient than the work so far? Try your own numbers in the EAC calculator.
Why it matters
When EAC moves, reported profit moves. Under cost-to-cost, a higher EAC lowers percent complete, which lowers earned revenue to date, which can flip a job from under billed to over billed. If EAC exceeds contract value, the whole projected loss is generally recognized immediately as a loss provision. Tracking EAC month over month is the cleanest way to spot margin fade early.
Common mistakes
- Adding a change order to contract value without adding its cost to EAC, which inflates margin.
- Using remaining budget as the cost to complete, which hides every overrun until it’s spent.
- Building EAC from accounting actuals alone, without the PM’s view of remaining work.
- Leaving known pending costs out because the change isn’t approved yet.
- Revising EAC only at quarter-end.
How os.construction handles it
On the Budget’s Forecast tab, Forecast to Complete defaults to projected budget minus projected costs, never less than zero, and you can type your own number to override it on any line. Est. Cost at Completion is projected costs plus forecast to complete, and projected over/under is shown alongside. Monthly budget snapshots and the Variance tab give the trend; a per-line forecast history chart is planned. In the Accounting module’s WIP app, the EAC used for percent complete is the forecast frozen at period end. See Budget, Job cost reports and cost to complete and WIP over/under billing.
Watch the explainer · 1:57
How to read a construction cost report
- 0:00One row per cost code
- 0:14Budget and committed cost
- 0:32Cost to date and accruals
- 0:48Cost to complete and EAC
- 1:11From EAC to earned revenue
- 1:34The cost report in os.construction
Read the transcript
A construction cost report tells you what a job will cost when it's done. It has one row per cost code, and its bottom line, the estimate at completion, drives almost every other number in construction finance.
Read it left to right. Original budget plus approved changes is the revised budget. Committed cost is signed subcontracts and purchase orders, and it's the early warning column. On this illustrative job, HVAC commitments already run above the HVAC budget, months before cost to date showed it.
Cost to date means cost incurred, not just invoiced: posted invoices, payroll and equipment, plus accruals for work in place that hasn't been billed yet. Without the accrual, cost to date is understated until the invoice lands.
Cost to complete is the project manager's forecast of what's left. Cost to date plus cost to complete is the estimate at completion. Here, eight point three million spent, plus three point five million to go, is an EAC of eleven point eight million. Against an eleven point three four million revised budget, that's a four hundred sixty thousand dollar overrun.
The EAC then drives revenue. Percent complete is cost to date divided by EAC, about seventy percent. Times the twelve point six million dollar contract, that's about eight point eight six million earned. With nine point one five million billed, the job is over billed by about two hundred eighty-seven thousand. A stale cost to complete changes all of it.
In os.construction, the Budget tool is the cost report: budget, commitments, cost and forecast to complete by cost code, with month-end snapshots. Accounting builds a WIP snapshot from posted job cost, billings and approved forecasts, reviewed before it posts.
Video page with chaptersMore in Construction concepts explained
Watch the explainer · 2:02
Earned value explained: PV, EV, AC, CPI and SPI
- 0:00Three numbers, one status date
- 0:20Planned value
- 0:38Earned value and actual cost
- 0:57Variances, CPI and SPI
- 1:20Forecast the finish
- 1:39Earned value in os.construction
Read the transcript
Earned value compares three numbers at the same status date: what you planned to do, what you actually did, and what it cost. Spending against the budget alone can't tell you whether a job is under budget or just behind. Earned value can, because it measures progress in budget dollars.
Start with the budget at completion. Take an illustrative control account with a budget of one point two million dollars, spread over a ten month baseline schedule. Planned value is the budget for the work scheduled by each date. At the end of month six, planned value is seven hundred twenty thousand dollars.
Earned value is the budget for the work actually done. The team has completed half the scope, so earned value is fifty percent of one point two million: six hundred thousand dollars. Actual cost is what that work really cost, from job cost with accruals: six hundred sixty thousand dollars.
Now read the gaps. Cost variance is earned value minus actual cost: minus sixty thousand, so the work cost more than its budget. Schedule variance is earned value minus planned value: minus one hundred twenty thousand. As ratios, CPI is zero point nine one and SPI is zero point eight three. Below one is worse than plan.
If cost efficiency stays where it is, the estimate at completion is the budget divided by CPI: one point three two million dollars, one hundred twenty thousand over budget. One caution: SPI is a ratio of money, not time. It drifts back to one as the job finishes, so don't read it as a finish date.
In os.construction Scheduling, the Planner shows earned value for each activity against the project baseline, with variances, CPI, SPI and the estimate at completion. Storing period performance keeps each period's figures as a permanent record.
Video page with chaptersMore in Construction concepts explained
FAQ
What does estimate at completion (EAC) mean?
Estimate at completion means the total cost a job is now expected to have when it is finished, based on what has been spent so far and a current forecast of what is left. It replaces the original budget as the best view of final cost. Comparing EAC with the budget shows a projected overrun or underrun; comparing it with the contract shows projected profit.
What is the formula for estimate at completion?
The basic formula is EAC = actual cost to date + estimate to complete. In construction, cost to date comes from job cost (including accruals) and the estimate to complete comes from the project manager's line-by-line forecast of remaining cost. Earned value practice also uses index-based formulas, such as budget at completion divided by the cost performance index, as a cross-check.
What is the difference between EAC and budget at completion?
Budget at completion (BAC) is what the job was planned to cost: the original budget plus approved budget changes. EAC is what the job is now expected to cost based on actual performance and the current forecast. The difference, BAC minus EAC, is the variance at completion; a negative number means a projected overrun.
How does EAC affect revenue recognition?
Under the cost-to-cost method, percent complete equals cost to date divided by EAC, and earned revenue equals percent complete times the contract value. So when EAC rises, percent complete falls, earned revenue to date falls and reported profit drops. If EAC exceeds the contract value, the full projected loss is generally recognized right away.
What is the difference between EAC and ETC?
ETC, the estimate to complete or cost to complete, is the remaining cost to finish the job from today. EAC is the total: what has already been spent plus the ETC. A PM forecasts ETC line by line; EAC is the result, and it is the number that goes on the WIP schedule as estimated total cost.
How often should EAC be updated?
At least monthly, as part of the month-end WIP and cost report review, with the project manager signing off on the forecast. Jobs with fast-moving risk or large pending changes may need more frequent updates. Updating only at quarter-end lets problems build up and shows up later as sudden margin fade.

