Esc

↑↓ move↵ openIndex · Pagefind
Contracts

Contingency

Definition

Money set aside in a budget or contract to cover unknown costs and risks that are expected but can't be pinned down yet.

Part of: Construction cost reporting: accruals, earned revenue, EAC and WIP

Topic: Project delivery & contracts

Updated

Contingency drawdown against percent completeA chart of contingency remaining against percent complete. The planned line falls evenly from 100 percent at the start to zero at completion. The actual line falls faster: at 66 percent complete only 26 percent of the $960k contingency remains, against 34 percent planned. Burn index is 1.12, and open risks of $310k exceed the $250k remaining, a $60k shortfall. Illustrative numbers.Contingency left vs work done100%50%00%50%100%percent complete →planactual26% leftat 66% completeBurn index1.1274% used ÷ 66% doneShortfall$60k$310k risk − $250k
When contingency burns faster than the work progresses, the forecast needs to change before the next WIP. Illustrative numbers.

Contingency is money set aside in a budget or contract to cover costs that are likely to arise but can’t be identified yet: buyout gaps, coordination misses, unforeseen conditions, minor scope busts. Owner contingency covers owner-side risks; contractor contingency, common on GMP jobs, covers the contractor’s. Track each draw and compare drawdown with percent complete.

Contingency is a budget line for the things you know will go wrong but can’t yet name. It is different from profit and from an allowance, and every dollar drawn from it should have a documented cause. Tracked well, it is the early-warning gauge for margin fade.

In plain English

Contingency is the rainy-day fund inside a construction budget. Illustrative: a contractor prices a job at $10,000,000 and carries $300,000 (3%) as contingency because the drawings aren’t fully coordinated. Halfway through, the drywall and ceiling subs both exclude the same soffit framing, a $45,000 gap. Instead of losing margin, the PM moves $45,000 from contingency to the framing line, notes the cause, and $255,000 remains for the rest of the job.

What contingency is used for, and what it isn’t

Typically a contingency draw Typically not a contingency draw
Scope gaps between subcontracts found after buyout Owner-requested scope changes (change order)
Coordination misses, such as clashes found in the field Items covered by an allowance
Minor design development within the original intent Overruns with no documented cause
Estimating errors and quantity busts Fee or profit
Subcontractor default not recovered from the sub Owner-caused delays the contract lets you recover

Who may use contingency, and for what, is a contract question. On a GMP, the agreement or its GMP exhibit usually says what the contractor’s contingency covers and whether the owner must be notified or approve each draw.

Contingency in AIA and other standard contracts

Standard lump-sum forms don’t define contingency, because the contractor’s internal contingency is simply part of its price. GMP forms are different. The AIA cost-plus-fee-with-GMP agreements, such as A102-2017 and the construction manager as constructor agreement A133-2019, let the parties build the contractor’s contingency into the GMP and set out its amount and the assumptions behind it when the GMP is agreed. The forms don’t prescribe a percentage, and the terms for using it and for sharing what’s left are negotiated, so read your GMP exhibit rather than relying on a generic definition.

Types of contingency

Type Who holds it Typical use Usually approved by
Owner contingency Owner, outside the construction contract Owner changes, design changes, unforeseen conditions Owner
Contractor contingency Contractor, inside the price (often a GMP line) Buyout gaps, coordination misses, subcontractor default, estimating error Contractor, often with owner visibility on a GMP
Design contingency Estimator, inside early estimates Drawings that aren’t finished yet Shrinks as design completes
Escalation contingency Either Price increases over the job’s duration Per the contract

Contingency vs allowance

Contingency Allowance
Covers Unknown risks A known item not yet specified
Example Unforeseen rock, coordination misses $50,000 for lobby light fixtures to be selected
Reconciled by Documented draws; unused amount handled per contract Change order for actual cost vs allowance
Belongs to Depends on type and contract Owner (adjusted up or down)

How contingency drawdown works

  1. Set it. Size contingency from the risk register or the estimate’s uncertainty, not just a flat percentage.
  2. Book it as its own line. Keep it separate from cost codes so it can’t be quietly absorbed.
  3. Draw with a cause. Each use is a transfer from contingency to the cost line that needs it, with the reason, date and approver.
  4. Add buyout savings deliberately. Many GCs move buyout savings into contingency rather than profit.
  5. Compare with progress. Each month, compare percent of contingency used with percent complete.
  6. Re-forecast. If the remaining contingency won’t cover remaining identified risk, update the estimate at completion now.

Formula

  • Contingency used % = contingency drawn ÷ original contingency (plus additions)
  • Burn index = contingency used % ÷ percent complete. Above 1.0 means contingency is burning faster than the work is progressing.
  • Contingency shortfall = expected value of open risks − remaining contingency. Positive means the forecast is too optimistic.

Worked example

Illustrative: a GMP includes a $960,000 contractor contingency.

Item Amount
Original contingency $960,000
Drawn to date (12 documented draws) $710,000
Remaining $250,000
Contingency used 74%
Percent complete 66%
Burn index (74 ÷ 66) 1.12
Expected value of open risks on the risk register $310,000
Shortfall $60,000

Only 26% of contingency remains while 34% of the work is left, and the risk register says the back half still carries $310,000 of expected exposure. Either risks were front-loaded, or the remaining contingency won’t cover what’s left. The PM should reflect the $60,000 shortfall in the EAC before the next WIP report and look for recovery (owner-caused items that belong in a change order rather than contingency).

Why it matters

Contingency is your buffer against margin fade. Track it like cash. If it burns faster than the job progresses, your forecast is lying to you. On a GMP, contingency use is also something the owner audits, so draws without a documented cause become disputes at final reconciliation.

Owners often carry separate hard cost and soft cost contingencies; hard costs vs soft costs explains the split.

Common mistakes

  • Using contingency to hide budget overruns instead of documenting each draw.
  • Spending owner contingency without written owner approval.
  • Drawing contingency for owner-caused changes that should be change orders.
  • Releasing unused contingency to profit early in the job.
  • Forgetting the contract terms on unused contingency (returned to owner, shared, or kept).

For setting contingency up as its own budget line when the job starts, see how to set up a construction project budget.

How os.construction handles it

In the Budget tool, transfers between lines are recorded as modifications, each with its from and to lines, amount and note, so contingency drawdown and buyout savings stay visible on the Modifications tab instead of being buried in a journal entry. A change event’s type can be set to Contingency or Allowance, so the cause of a draw travels with it. Owner billing on GMP jobs, including how contractor contingency moves into cost lines when used, is described in a planned concept page. See Budget, Change orders and Owner billing on GMP jobs.

FAQ

What is contingency in construction?

Contingency is money set aside in a budget or contract price for costs that are expected to arise but can't be identified yet, such as scope gaps, coordination problems, unforeseen conditions or estimating error. It is a risk buffer, not a slush fund: each draw on it should be documented with its cause and approved by whoever controls that contingency.

What is the difference between owner and contractor contingency?

Owner contingency sits in the owner's project budget, outside the construction contract, and covers owner-driven changes, design changes and unforeseen conditions. Contractor contingency sits inside the contractor's price, common on GMP contracts, and covers the contractor's own risks such as buyout gaps and coordination misses. The contract defines what each may be used for and who approves draws.

What is the difference between a contingency and an allowance?

An allowance is a sum for a known item whose details aren't selected yet, such as a finish hardware or flooring allowance, and it is usually reconciled against actual cost with a change order. A contingency covers unknown items. Allowances answer what will this specific thing cost, while contingency answers what might go wrong.

How much contingency should a construction project have?

There's no single right percentage. It depends on design completeness, project complexity, delivery method, site conditions and market volatility, and it should shrink as design and buyout firm up costs. Many teams size contingency from a risk register or a probabilistic analysis rather than a flat rule of thumb, then track it against progress.

What happens to unused contingency?

The contract decides. On many GMP contracts unused contractor contingency returns to the owner or is shared under a savings clause at final reconciliation. On lump-sum work, the contractor's internal contingency is part of its own margin. Owner contingency stays with the owner. Read the contract's contingency and savings provisions before the job starts.

What is construction contingency used for?

Contingency pays for real costs inside the agreed scope that couldn't be identified when the price was set: buyout gaps between trades, coordination misses, minor design development, estimating errors, a subcontractor default or unforeseen conditions the contract leaves with that party. It should not pay for owner-requested scope changes, which belong in change orders, or quietly absorb overruns nobody explains.

Sources

Keep exploring

Related across os.construction

Open file